Bunker Hill Provides July 2022 Project Restart Update
BUNKER HILL PROVIDES JULY 2022 PROJECT RESTART UPDATE
Live 6ix Summit by Video from Bunker Hill Site on Thursday, August 4 @ 11:00am ET / 8:00am PT
HIGHLIGHTS
• Underground decline advances; remains on track for break-through to 6 Level in September
• Two haul trucks and electric jumbo drill grows mobile equipment fleet
• Processing plant demobilization ahead of schedule - ball and regrind mills, cone crushers, flotation cells,
lime silo, truck scales, pumps, motors and other ancillary equipment transported to Bunker Hill
• Pilot water treatment study nearly complete, modifications of full-scale system design underway
• Prefeasibility Study progresses on schedule for publication in Q3 2022
NEXT STEPS
• Mill demobilization expected to be substantially complete by end of August
• CEO Sam Ash and CFO David Wiens to host interactive 6ix investor event on Thursday, August 4 at
11:00am ET / 8:00am PT, with live video at Bunker Hill site. Investors are invited to register at: [LINK]
• CEO Sam Ash interview with Kai Hoffmann available today at 12:00pm ET / 9:00am PT at
YouTube.com/soarfinancial or twitter.com/soarfinancial
TORONTO, August 3, 2022 – Bunker Hill Mining Corp. (the “Company”) (CSE: BNKR, OTCQB: BHLL) is pleased to
provide an update on restart project activities during the month of July 2022.
Sam Ash, CEO stated: “ It’s been a busy and exciting summer at Bunker Hill, with impressive progress across all
project and technical workstreams including mill demobilization, underground development and the Prefeasibility
Study. Given the pace of this development , we look forward to providing our investors with a formal monthly
project update going forward. We will also continue to share our progress through regular video updates.”
July 2022 Video Updates
- Underground development: [LINK]
- Pend Oreille mill demobilization: [LINK]
- Water treatment pilot plant: [LINK]
UNDERGROUND DEVELOPMENT AT BUNKER HILL MINE
As part of the restart plan, a decline continues to be driven from ‘5 Level’ (the highest accessible level of the mine)
to ‘6 Level’. The decline had advanced approximately 1,100 feet through the end of July, with supporting muck
bays and sumps and with a second ventilation fan in the process of being installed. On breaking through to 6 Level
the mine plan envisages rehabilitation of pre-existing decline infrastructure that already connects to 8 Level , a
substantial time and capital saving, as the next stage of development. Upon completion, this will provide access
to mineralization to support mine restart activities.
PLANT DEMOBILIZATION PROGRESS
At Teck’s Pend Oreille site, the dismantling and demobilization of the mill significantly advanced in July, with the
ball mills, regrind mill, crushers, flotation cells, lime silo, truck scales, pumps, motors, and other ancillary
equipment all dismantled and transported approximately ~145 miles to the Bunker Hill site. The last week of July
saw deployment of a 265 ton crane to complete the heavy lifts necessary for extraction of the ball mills, regrind
mill, larger flotation cells and the lime silo. All of these components are now located in the Bunker Hill yard, having
been transported intact to preserve integrity and to simplify recommissioning ( with the exception of the mills
which have been separated from their respective motors and trunnions). Remaining work at the Pend Oreille site
will focus on the loading and transportation of numerous spare parts, built-in overhead cranes, laboratory
equipment and the underground jaw crusher. This remaining demobilization work is expected to be substantially
complete by the end of August.
Photo 1:
Regrind mill prior to transport
Photo 2:
Ball mill hoisted by 265 ton crane
Photo 3:
Ball mill loaded on trailer
SURFACE ACTIVITY AT BUNKER HILL
Upon arrival at the Bunker Hill site, mill equipment is being inspected, laid down and inventoried in accordance
with requisite storage conditions for each piece. The previous work of clearing the yard and regaining key real
estate is allowing us to place and store equipment outside the areas in which construction will soon begin.
Concurrently, a maintenance and renovation program is being derived for the mill equipment.
Other above ground activity has also included a clean-up of the War dner yard area which will form the base of
mining operations for initial production. The Wardner yard will house future dry facilities and surface storage of
the growing heavy equipment fleet, which includes two additional underground haul trucks and an electric jumbo
drill. This new equipment will be used to further advance the ongoing decline, remove dependencies on single
pieces of equipment, and open up the possibility of simultaneous mine development and mining/sale of ore in
the pre-start period.
In partnership with Avista, the local ele ctricity provider, the Company is also finalizing plans and procuring
electrical components for a major upgrade of th e electrical infrastructure at Wardner to allow a transition from
diesel generators to the main electricity grid by early Q4 2022.
PILOT WATER TREATMENT STUDY PROGRESS
A pilot water treatment study is nearly complete , which has involved adjustment of multiple parameters during
the critical spring freshet period at Bunker Hill Mine. This is the period of the year where both water flows and
metal concentrations in the mine’s effluent peak. The result is a significant spike in the metal load of the mine’s
effluent that needs to be removed. The testing program modified target pH levels of the plant’s reactor tank at
varying influent flow rates using different types of flocculants to determine the performance capabilit ies of the
plant. The plant’s Lamella clarifier removes metals that precipitate from the mine’s discharge water after being
treated with lime and flocculant. The testing program documents the conditions under which this system can and
did meet water discharge standards. The pilot system was built at approximately 1/20th of the full-scale plant, for
which modifications are now underway using the results of the pilot study. The pilot plant, the pilot study and
the full-scale system design are all being provided by MineWater LLC.
Photo 4: Flotation cell lifted
through roof of Pend Oreille Mill
Photo 5: Balls mills, flotation cells
and lime silo unloaded in Bunker
Hill yard
Photo 6: Ball mills arriving by
lowboy trailer at Bunker Hill
Photo 7: Lime silo being prepared
for transport
Photo 8: Wardner clean-up area Photo 9: Pilot water treatment
plant at Bunker Hill Mine
NEXT STEPS
Mill demobilization is expected to be substantially complete over the coming weeks, followed by the
commencement of demolition activities. The Company remains on track to publish the results of a Prefeasibility
Study by the end of the third quarter of 2022, and its overall development timeline remains unchanged (see
Figure 1 below). Project progress will be reported on a monthly basis going forward.
Figure 1: Bunker Hill Planned Development Timeline
QUALIFIED PERSON
Mr. Scott E. Wilson, CPG, President of RDA and a consultant to the Company, is an independent “qualified person”
as defined by NI 43-101 and is acting as the qualified person for the Company. He has reviewed and approved the
technical information summarized in this news release.
ABOUT BUNKER HILL MINING CORP.
Under new Idaho -based leadership the Bunker Hill Mining Corp, intends to sustainably restart and develop the
Bunker Hill Mine as the first step in consolidating a portfolio of North American mining assets with a focus on
silver. Information about the Compa ny is available on its website, www.bunkerhillmining.com, or within the
SEDAR and EDGAR databases.
For additional information contact:
David Wiens, CFA
CFO & Corporate Secretary
+1 208 370 3665
Cautionary Statements
Certain statements in this news release are forward-looking and involve a number of risks and uncertainties. Such
forward-looking statements are within the meaning of that term in Section 27A of the Securitie s Act of 1933, as
amended, and Section 21E of the Securities Exchange Act of 1934, as amended, as well as within the meaning of
the phrase ‘forward-looking information’ in the Canadian Securities Administrators’ National Instrument 51-102 –
Continuous Disclosure Obligations. Forward -looking statements are not comprised of historical facts. Forward -
looking statements include estimates and statements that describe the Company’s future plans, objectives or
goals, including words to the effect that the Company or management expects a stated condition or result to occur.
Forward-looking statements may be identified by such terms as “believes”, “anticipates”, “expects”, “estimates”,
“may”, “could”, “would”, “will”, or “plan”. Since forward -looking statements are b ased on assumptions and
address future events and conditions, by their very nature they involve inherent risks and uncertainties. Although
these statements are based on information currently available to the Company, the Company provides no
assurance that actual results will meet management’s expectations. Risks, uncertainties and other factors involved
with forward-looking information could cause actual events, results, performance, prospects and opportunities to
differ materially from those expressed or implied by such forward-looking information.
Forward looking information in this news release includes, but is not limited to, the Company’s intentions regarding
its objectives, goals or future plans and statements, including statements relating to the Bu nker Hill mine project
restart, underground development, demobilization activities, surface activity, the pilot water study, the timing and
completion of a pre feasibility study, the timing and completion of a proposed $37m stream, overall development
timeline and other matters relating to the Bunker Hill mine. Factors that could cause actual results to differ
materially from such forward -looking information include, but are not limited to: the ability to predict and
counteract the effects of COVID -19 on th e business of the Company, including but not limited to the effects of
COVID-19 on the price of commodities, capital market conditions, restriction on labour and international travel
and supply chains; failure to identify mineral resources; failure to convert estimated mineral resources to reserves;
the inability to complete a feasibility study which recommends a production decision; the preliminary nature of
metallurgical test results; the Company’s ability to restart and develop the Bunker Hill Mine and the risks of not
basing a production decision on a feasibility study of mineral reserves demonstrating economic and technical
viability, resulting in increased uncertainty due to multiple technical and economic risks of failure which are
associated with th is production decision including, among others, areas that are analyzed in more detail in a
feasibility study, such as applying economic analysis to resources and reserves, more detailed metallurgy and a
number of specialized studies in areas such as mining and recovery methods, market analysis, and environmental
and community impacts and, as a result, there may be an increased uncertainty of achieving any particular level
of recovery of minerals or the cost of such recovery, including increased risks assoc iated with developing a
commercially mineable deposit with no guarantee that production will begin as anticipated or at all or that
anticipated production costs will be achieved; failure to commence production would have a material adverse
impact on the Co mpany's ability to generate revenue and cash flow to fund operations; failure to achieve the
anticipated production costs would have a material adverse impact on the Company's cash flow and future
profitability; delays in obtaining or failures to obtain re quired governmental, environmental or other project
approvals; political risks; changes in equity markets; uncertainties relating to the availability and costs of financing
needed in the future; the inability of the Company to budget and manage its liquidity in light of the failure to obtain
additional financing, including the ability of the Company to complete the payments pursuant to the terms of the
agreement to acquire the Bunker Hill Mine Complex; inflation; changes in exchange rates; fluctuations in
commodity prices; delays in the development of projects; capital, operating and reclamation costs varying
significantly from estimates and the other risks involved in the mineral exploration and development industry; and
those risks set out in the Company’s public documents filed on SEDAR. Although the Company believes that the
assumptions and factors used in preparing the forward -looking information in this news release are reasonable,
undue reliance should not be placed on such information, which only appl ies as of the date of this news release,
and no assurance can be given that such events will occur in the disclosed time frames or at all. The Company
disclaims any intention or obligation to update or revise any forward -looking information, whether as a result of
new information, future events or otherwise, other than as required by law. No stock exchange, securities
commission or other regulatory authority has approved or disapproved the information contained herein.
Cautionary Note to United States Investors Concerning Estimates of Measured, Indicated and Inferred
Resources
This press release has been prepared in accordance with the requirements of the securities laws in effect in Canada,
which differ from the requirements of U.S. securities laws. Unless otherwise indicated, all resource and reserve
estimates included in this press release have been disclosed in accordance with NI 43 -101 and the Canadian
Institute of Mining, Metallurgy, and Petroleum Definition Standards on Mineral Resources a nd Mineral Reserves.
NI 43-101 is a rule developed by the Canadian Securities Administrators which establishes standards for all public
disclosure an issuer makes of scientific and technical information concerning mineral projects. Canadian disclosure
standards, including NI 43 -101, differ significantly from the requirements of the United States Securities and
Exchange Commission (“SEC”), and resource and reserve information contained in this press release may not be
comparable to similar information disclosed by U.S. companies. In particular, and without limiting the generality
of the foregoing, the term “resource” does not equate to the term “reserves”. Under U.S. standards, mineralization
may not be classified as a “reserve” unless the determination has b een made that the mineralization could be
economically and legally produced or extracted at the time the reserve determination is made. The SEC’s disclosure
standards normally do not permit the inclusion of information concerning “measured mineral resource s”,
“indicated mineral resources” or “inferred mineral resources” or other descriptions of the amount of mineralization
in mineral deposits that do not constitute “reserves” by U.S. standards in documents filed with the SEC. Investors
are cautioned not to assume that any part or all of mineral deposits in these categories will ever be converted into
reserves. U.S. investors should also understand that “inferred mineral resources” have a great amount of
uncertainty as to their existence and great uncertainty as to their economic and legal feasibility. It cannot be
assumed that all or any part of an “inferred mineral resource” will ever be upgraded to a higher category. Investors
are cautioned not to assume that all or any part of an “inferred mineral resource ” exists or is economically or
legally mineable. Disclosure of “contained ounces” in a resource is permitted disclosure under Canadian
regulations; however, the SEC normally only permits issuers to report mineralization that does not constitute
“reserves” by SEC standards as in-place tonnage and grade without reference to unit measures. The requirements
of NI 43-101 for disclosure of “reserves” are also not the same as those of the SEC, and reserves disclosed by the
Company in accordance with NI 43 -101 may not qualify as “reserves” under SEC standards. Accordingly,
information concerning mineral deposits contained in our website may not be comparable with information made
public by companies that report in accordance with U.S. standards.