Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

BMR.V ·

Battery Mineral Resources Corp. Provides Corporate Update on Its Path to Production at its Punitaqui Mine

Corporate Updates

Battery Mineral Resources Corp. Provides Corporate Update on Its Path to

Production at its Punitaqui Mine

Vancouver, British Columbia – (July 13, 2022) – Battery Mineral Resources Corp.

(TSXV: BMR) (" BMR” “Battery" or the " Company") is very pleased to provide a

broad corporate update on its recent accomplishments in Chile as it moves its

Punitaqui mine complex towards a production restart. The Punitaqui mine and mill

have been on continuous care and maintenance since April 2020, when copper prices

as low as $2.00 per pound forced the previous operators to cease operations.

Drilling and Updated 43-101 Resource Estimates

The Phase 1 drill program at the Punitaqui Mining complex was completed in May and

all assays have now been received and reported. The final tally for the Phase 1

program totalled nearly 33,000 meters (“m”) of diamond drilling focusing on three

zones: San A ndres, Dalmacia and Cinabrio Norte . The results of these drilling

campaigns will be combined with historical drilling and resource estimates will be

calculated and reported. In addition, the current remaining resources for the Cinabrio

mine, which fed the Punitaqui copper processing plant for eight -plus years, will be

included in the report.

The Company’s management are very excited with the results of the Phase 1 program

for several reasons, as follows:

Dalmacia

- A change in drilling azimuth and dip discovered several new areas of

mineralization and was also able to connect several smaller zones into larger

bodies which are more suitable for larger scale mining.

- The focus area for the upcoming resource statement covers approximately

one-third of the known strike length and BMR is optimistic further infill drilling

could lead to a significantly larger resource as the remaining two-thirds of the

strike is explored.

Cinabrio Norte

- The drilling results reported from Cinabrio Norte were very encouraging as this

area immediately north of the Cinabrio mine had very minor drilling prior to

the recent Phase 1 surface drilling program.

- The Company now expects the Cinabrio Norte zone will be included in the

upcoming resource estimate. This is particularly important since this zone is

approximately 110m north of the 220m level in the Cinabrio mine and can

therefore be accessed from Cinabrio with relatively little effort.

- The Cinabrio Norte zone is open at depth, which BMR plans to continue drilling

from underground once access has been established.

San Andres

- Infill and step out drilling intersected broad areas of copper mineralization to

the north and south.

- The main mineralized zone has now been traced for up to 450m in strike, up

to 200m in width and up to 30m in thickness.

- The company expects that San Andres will be included in the upcoming

resource estimate.

- The planning for a Phase 2 RC infill drill program at San Andres is well

underway with the construction of all drill pads completed.

Figure 1: Punitaqui Project Tenement Holdings, Resource Targets & Plant

Location Map

JDS Energy and Mining, Inc. are working to complete the updated NI 43-101 resource

estimate at the Punitaqui mining complex since receiving all final assays from the

Phase 1 drill program. An NI 43-101 resource is to be received in the next three to

four weeks.

Punitaqui Mill Maintenance Audit

The Punitaqui mill is a standard crush, grind and flotation mill rated for processing of

up to 3,600 tonnes per day, which was improved upon and optimized by Glencore Plc

during the approximately 8 years that they operated the mill. As part of the planned

restart of production, the Company recently engaged a third-party firm to conduct a

full maintenance audit of the Punitaqui mill to assess its readiness to recommence

processing ore and producing copper concentrate . The audit scope included all

mechanical, electrical and instrumentation items. This included inspection of all

pumps, motors, conveyor belts, primary, secondary, and tertiary crushers, ball mills,

liners, flotation cells, concentrate filters, tailings thickeners, cranes and hoists ,

electrical supply and water supply.

The results of the audit confirmed that the budgeted cost estimate, which was based

on operating and maintenance records, was accurate and no new major repairs or

replacements are required. Finally, the audit confirmed that the Punitaqui mill is in

good working condition to restart production after the planned maintenance program

concludes, which is expected later this year.

Metallurgical Study on Processing of Punitaqui Ores

Although the Punitaqui copper processing plant successfully operated for nearly a

decade, the company elected to undertake a comprehensive metallurgical test

program on each potential different ore type s from the Punitaqui mining complex

including material from two zones at the Cinabrio mine (M1 & M2), the Cinabrio Norte,

San Andres, and Dalmacia zones. The samples were shipped to the SGS Laboratory

in Lakefield, Ontario, where a full flotation program was conducted. SGS Lakefield is

a recognized global leader in mineral processing and recovery and their work was

overseen by BMR metallurgical consultant Dr. Joseph Ferron. The goal of this study

was to minimize any potential start -up ri sk and maximize metal recoveries and

copper concentrate quality.

As previously announced in our June 9 th press release, metallurgical studies

confirmed that the combined copper concentrate to be produced from the four main

deposits (Cinabrio, Cinabrio Norte, Dalmacia and San Andres) is commercially

marketable and the company has received strong interest from several concentrate

off-takers. Moreover, the testing demonstrated the combined future sources of ore

to the Punitaqui mill demonstrate an average of overall 84% copper recovery – a 5%

higher recovery than historically realised at Punitaqui by prior opera tors.

Additionally, we are working to refine and improve upon these initial very positive

results.

The Punitaqui samples were prepared and submitted for complete chemical and

mineralogical analyses. In addition, the sample hardness was measured using the

Bond work index procedure (BWI). Most relevant results are presented in the

following Table #1.

Table #1 – Chemical & Mineralogical Results of Punitaqui Feed Material

The flotation program included: rougher kinetics tests, open circuit cleaner tests and

locked cycle tests. The main parameters examined were copper and precious metals

recovery, fineness of primary grind, use of regrind and circuit configuration. The

results of the locked cycle tests are presented in the following Table #2.

Table #2 – Concentrate Recoveries & Grades by Zone

Unit M1 M2 Norte

Chemical

Cu Total % 0.92 0.96 1.39 1.02 0.98

Gold g/t 0.22 <0.02 <0.02 0.03 0.02

Silver g/t 2.8 1.7 5.5 5.1 0.5

Mineralogical

Copper Minerals

Chalcopyrite % 2.86 3.31 3.37 2.7 1.42

Bornite % 0.01 0.02 0.78 0.4 0.67

Chalcocite/Covellite % <0.01 <0.01 0.07 0.04 <0.01

Gangue Minerals %

Quartz (silica) % 11.5 13.8 6.4 23.6 2.2

Plagioclases % 10.0 12.1 9.1 6.7 54.0

Sericite/Muscovite % 16.6 15.9 11.8 20.5 3.2

Calcite % 10.3 15.8 43.5 14.5 0.4

Iron Oxides % 16.7 6.1 0.3 0.4 6.5

Hardness (BWI) KWh/tonne 17.0 19.3 14.3 23.3 12.3

Cinabrio San Andres DalmaciaANALYSES

Copper Concentrates

Unit M1 M2 Norte

Copper Total % 31.5 27.5 21.6 22.0 27.8

Gold g/t 4.8 n.a 0.04 0.6 0.5

Silver g/t 78.4 n.a 91.0 110 17

Copper Recovery % 94.3 95.7 81.0 84.2 96.5

Rougher Tails

Copper Total % 0.039 0.032 0.2700 0.160 0.023

Primary Grind

P 80 um 116 95 86 67 102

Cinabrio San Andres Dalmacia

The flotation circuit used during these locked cycle tests incorporated a regrind of the

entire rougher concentrate, and an open circuit first cleaner stage. Results clearly

indicated that the copper recovery was directly related to the percent liberation of

the copper sulphides. Copper concentrate grades for all five ore types were squarely

in ranges which are marketable (ranging from 21.6% up to 31.5%). Representative

copper concentrates produced from each ore sample were submitted to standard

smelter analysis. Significant results are presented in Table 3.

Table #3 – Punitaqui Copper Concentrate Chemical Analysis

Final Punitaqui Permitting

The permitting process which is a combination of modifying and combining existing

environmental and operating permits is progressing in lockstep with the goal

restarting the Punitaqui copper mine complex. Permits for operation of the Punitaqui

mill, tailings deposition and re-starting underground mine development have already

been approved by the regulators.

After resources are updated, mine designs are modified and the remainder of the

capital required for recommencing operations is secured, Cinabrio will be the first

area to be mined, to be followed soon after by a sequence that brings in mining at

San Andres, Cinabrio Norte and Dalmacia.

To recommence underground mining of ore at Cinabrio and San Andres , BMR

submitted a simplified environmental impact study (DIA) for the Cinabrio mine and

San Andres zone in December 2021 as requested by the authorities. After reviewing

the DIA study, regulators are afforded two rounds of comments/questions for

clarification. BMR is in the process of preparing the answers to the second and final

round of comments sent by the regulatory authorities. These will be filed on July 15th,

with final approval expected within 60 days.

Local Community Engagement

Battery Mineral Resources is committed to a strong focus of continuous improvement

on community relations by proactively engaging with our local communities and

especially with the residents of the town of Punitaqui. Earlier this year, BMR engaged

the services of consulting firm Integratio Mediação Social e Sustentabilidade

Element Unit M1 M2 Norte

Cu % 30.8 23.9 27.0 26.8 26.3

Fe % 29.3 24.6 16.3 19.4 18.2

S % 31.3 26.1 19.8 23.8 20.5

As % 0.01 0.12 0.06 0.26 0.12

Al % 0.41 1.45 2.19 1.34 2.25

Mg % 0.21 0.52 0.56 0.21 2.67

Si % 1.16 5.03 6.33 7.39 10.8

Pb % 0.04 0.05 0.07 0.03 0.004

Zn % 0.42 0.15 0.37 0.46 0.007

Hg g/t 4.40 23.3 1.60 24.7 1.00

Cinabrio San Andres Dalmacia

(“Integratio”). Integratio is a socio -environmental management, strategic

relationship, and stakeholder engagement consultant group operating for over 17

years and based in Belo Horizonte, Brazil. Integratio has recently delivered a report

to BMR with communit y assessment and stakeholder mapping that also highlights

the main issues to be focused on in our community relations and social license

program and provides the framework for a wholistic and proactive approach to social

engagement. As a next step to the responses received in the report, BMR plans to

initiate a social management and engagement plan that considers the entire

relationship and communication of the company with in the area, including the

establishment of a social investment program, which will allow direct communication

with the entities and population in the area of influence of our Punitaqui mine

complex. This program is now being prepared, reviewed and should be implemented

by the end of the month. We look forward to continuing to engage in a proactive and

positive manner with all our stakeholders and local communities.

About Battery Mineral Resources Corp.

Battery Mineral Resources (“BMR”) is a battery mineral company focused on growth

through cash-flow, exploration, and acquisitions in favourable mining jurisdictions.

BMR is currently developing the Punitaqui Mining Co mplex, a past copper -gold

producer, in the Coquimbo region of Chile and pursuing a potential near -term

resumption of operations in late 2022. Battery Mineral’s mission is the discovery,

acquisition, and development of battery metals (namely cobalt, lithium , graphite,

nickel, and copper), in North America, South America and South Korea, to become a

premier and responsible supplier of battery minerals to the electrification

marketplace. BMR is the largest mineral claim holder in the historic Gowganda Cobalt-

Silver Camp in Ontario, Canada, and continues to pursue a focused program to build

on the recently announced, +1 -million-pound high-grade cobalt resource at McAra.

In addition, Battery Mineral owns 100% of ESI Energy Services, Inc. a profitable

pipeline equipment rental and sales company with operations in Alberta, Canada and

Arizona, USA. Battery Minerals Resources is based in Canada and its shares are listed

on the Toronto Venture Exchange under the symbol “BMR” and on the OTCQB under

the symbol “BTRMF”. Further information about BMR and its projects can be found

on www.bmrcorp.com

For more information, please contact:

Martin Kostuik, CEO

Phone: +1 (604) 229 3830

[email protected]

Mars Investor Relations

+1 (604) 335-1976

[email protected]

Harbor Access Corp.

475-477-9402

[email protected]

Twitter: @BMRcorp_

www.bmrcorp.com

Neither the TSXV nor its Regulation Services Provider (as that term is defined in the

policies of the TSXV) accepts responsibility for the adequacy or accuracy of this

press release.

Forward Looking Statements

This news release includes certain “forward -looking statements” under applicable

Canadian securities legislation. There can be no assurance that such statements will

prove to be accurate, and actual results and future events could differ materially from

those anticipated in such statements. Forward-looking statements reflect the beliefs,

opinions and projections of the Company on the date the statements are made and

are based upon a number of assumptions and est imates that, while considered

reasonable by the Company, are inherently subject to significant business, economic,

competitive, political and social uncertainties and contingencies. Many factors, both

known and unknown, could cause actual results, performance, or achievements to be

materially different from the results, performance or achievements that are or may

be expressed or implied by such forward -looking statements and the parties have

made assumptions and estimates based on or related to many of these factors. Such

factors include, without limitation, the ability of the Company to obtain sufficient

financing to complete exploration and development activities, the ability of the

Company to complete the Debenture offering, risks related to share price and market

conditions, the inherent risks involved in the mining, exploration and development of

mineral properties, the ability of the Company to meet its anticipated development

schedule, government regulation and fluctuating metal prices. Accordingly, re aders

should not place undue reliance on forward-looking statements. Battery undertakes

no obligation to update publicly or otherwise revise any forward -looking statements

contained herein, whether because of new information or future events or otherwise,

except as may be required by law.