Battery Mineral Resources Announces Intercept of 48 Meters of 1.31% Cu from the Cinabrio Norte Target at Its Punitaqui Copper MINE IN Chile

Drill Results

BATTERY MINERAL RESOURCES ANNOUNCES INTERCEPT OF 48 METERS OF

1.31% Cu FROM THE CINABRIO NORTE TARGET AT ITS PUNITAQUI

COPPER MINE IN CHILE

Vancouver, British Columbia – (June 27, 2022) – Battery Mineral Resources Corp.

(TSXV: BMR) (OTCQB: BTRMF) ("Battery" or “BMR” or the "Company") is pleased

to announce encouraging drill core assay results from the recently completed Phase

1 2021–2022 exploration and infill diamond drill program focused on extensions of

the Cinabrio orebody , the Dalmacia target and the San Andres target within the

Punitaqui mine complex (“Punitaqui”) in Chile . The Punitaqui mine is slated for

resumption of mine operations in the second half of 2022.

The Cinabrio Norte target represents a potential norther n extension of the main

Cinabrio mine orebody, which was historically the primary source of ore feed to the

Punitaqui copper ore concentration plant for eight -plus years. These drill results

continue to highlight the presence of strong copper mineralization and the significant

vertical extent of the Cinabrio Norte target (see Figure 1).

Highlights

• At Cinabrio Norte the Phase 1 drill program consisted of 53 diamond drill holes

with a total of 13,731 meters (“m”).

• To date, the drilling has outlined a significant zone of high-grade mineralization in

the northern portion of the target area and remains open at depth.

• The initial Phase 1 program of step-out holes was expanded from the planned 24

holes (for approximately 3,600m) to 53 holes to further test the down-dip extent

of the copper (“Cu”) mineralization ultimately reaching a depth of 350m below

surface.

• The results of the North Zone at Cinabrio Norte include:

o CNN-22-30: 164m at 0.80% Cu including 48.0m at 1.31% Cu, 12.5m

at 0.91% Cu and 19.4m at 1.15% Cu

o CNN-22-40: 14m at 1.62% Cu

o CNN-22-41: 9m at 1.15% Cu

o CNN-22-19: 4.1m at 1.38% Cu

o CNN-22-19A: 16.6m at 0.85% Cu including 5.4m at 1.16% Cu

• Results from the South and Central Zones at Cinabrio Norte include:

o CNN-22-33: 14.9m at 1.79% Cu including 2.8m at 3.66% Cu

o CNN-22-25: 4m at 0.48% Cu including 18.9m at 1.23% Cu

o CNN-22-26: 4m at 1.18% Cu

o CNN-22-29: 14m at 0.76% Cu including 5m at 1.01% Cu

o CNN-22-32: 9m at 0.43% Cu

o CNN-22-38: 4.3m at 1.09% Cu

Battery CEO Martin Kostuik states; “We are very pleased to report these encouraging

results from Cinabrio Norte at our former producing Punitaqui copper mine in Region

IV of Chile. Cinabrio Norte began as a collection of a few interesting holes to the

immediate north of the original Cinabrio mine. Cinabrio, until May of 2020, produced

feed to the Punitaqui copper concent rator for nine -plus years. Today’s reported

drillhole results conclude the initial drill program at Cinabrio Norte and, together with

the previously reported results, clearly demonstrate a new extension of Cinabrio to

the north. Th ese new targets have the potential to provide the Company with an

additional source of copper mineralization as feed for the Punitaqui processing plant.”

Furthermore, CEO Kostuik remarks: “The development of Punitaqui towards a restart

of mine operations, followed by a re -start of the copper concentrating plant, is

progressing well on all fronts . Efforts are multi -faceted and include drilling,

engineering, metallurgical test work and permit modifications. We look forward to

the potential of these latest assay results for th e Cinabrio Norte target contributing

significantly to the forthcoming resource report and subsequent restart plan for the

mine”.

Cinabrio Norte Drill Program

The Cinabrio Norte Phase 1 drilling was designed to follow-up on a limited number of

historic drillholes that targeted the northern extension of the Cinabrio orebody. The

historic exploration drilling confirmed that the favorable TSU that hosts the copper

mineralization within the Cinabrio orebody extends to the north. The TSU has been

mapped along a north -south strike from the Cinabrio mine. Of note, the Cinabrio

Norte target is only 110m north of the Cinabrio underground workings on level 200m.

Historic hole CNS-20-01, drilled in 2020 by the prior operators, was drilled completely

within the TSU resulting in multiple mineralized intercepts and, most notably,

confirmed the presence of TSU for over 200m of strike length with significant copper

sulphide mineralization (CNS-20-01: 48m at 0.64% Cu, 3m at 0.47% Cu and 6m

at 0.45% Cu).

The 20221-2022 Phase 1 drilling at Cinabrio Norte consisted of a series of step-out

holes to test the TSU along a 400m strike length (north-south) to a depth below

surface, or down-dip, of 350m. The current BMR drilling has outlined a significant

zone of high-grade mineralization in the northern portion of the target zone which

remains open down-dip.

Complete assay results were recently received for all 18 remaining drill holes from

the Phase 1 campaign at Cinabrio Norte (see Figure 1 and Table 1). As of this press

release, all assays from the entire Phase 1 program (Cinabrio Norte, San Andres and

Dalmacia) have now been reported.

Table 1: Current Cinabrio Norte Exploration Drill Intercepts

Drillhole

Number

From

(m)

To

(m)

Interval

(m)

Copper

(Cu %)

Silver

(Ag g/t)

Northern Zone of Cinabrio Norte Target

CNN-22-19 310.0 314.1 4.1 1.38 22.6

and 342.0 345.0 3.0 0.68 7.7

CNN-22-19A 184.8 201.4 16.6 0.85 1.5

including 196.0 201.4 5.4 1.16 0.8

CNN-22-30 209.0 373.0 164.0 0.80 9.9

including 209.0 257.0 48.0 1.31 6.4

including 248.0 254.0 6.0 1.83 6.3

and 285.0 297.5 12.5 0.91 10.5

and 315.6 335.0 19.4 1.15 34.6

and 370.0 373.0 3.0 1.25 7.0

CNN-22-35 191.6 195.0 3.4 0.37 4.76

and 329.7 334.0 4.3 0.05 3.2

and 359.5 361.0 1.5 0.37 7.9

and 363.0 367.4 4.4 0.43 1.7

CNN-22-39 324.0 329.0 5.0 0.50 10.60

CNN-22-40 279.0 293.0 14.0 1.62 5.0

and 386.0 395.0 9.0 0.12 3.31

and 397.0 402.0 5.0 0.17 12.40

CNN-22-41 133.0 135.0 2.0 0.63 1.20

and 219.0 221.5 2.5 0.73 2.80

and 237.1 240.1 3.0 0.87 8.37

including 237.1 239.0 1.9 1.20 10.89

and 281.0 290.0 9.0 1.15 12.00

including 283.0 288.0 5.0 1.70 16.60

South and Central Zones of Cinabrio Norte Target

CNN-22-25 357.0 361.0 4.0 0.48 9.5

CNN-22-26 208.0 212.0 4.0 1.2 0.80

CNN-22-27 210.0 212.0 2.0 0.40 1.51

CNN-22-28 128.0 131.0 3.0 0.38 2.33

and 136.0 138.0 2.0 0.38 3.50

and 148.0 149.7 1.7 0.50 1.00

CNN-22-29 183.0 197.0 14.0 0.76 2.86

including 183.0 185.0 2.0 0.97 2.00

including 192.0 197.0 5.0 1.01 4.20

CNN-22-31 202.2 203.5 1.3 0.41 1.00

and 213.0 218.0 5.0 0.07 2.08

CNN-22-32 253.0 262.0 9.0 0.43 5.44

CNN-22-33 301.9 316.8 14.9 1.79 6.47

including 314.0 316.8 2.8 3.66 0.40

CNN-22-34 234.3 242.0 7.7 0.07 4.12

and 244.0 249.0 5.0 0.22 3.20

CNN-22-37 94.0 98.0 4.0 0.47 2.81

CNN-22-38 141.8 146.0 4.3 1.09 6.53

and 146.0 149.0 3.0 0.20 0.60

Note: All intervals are downhole length

Significant intercepts reported earlier from the phase 1 drilling include:

o CNN-21-02: 13m at 1.36% Cu including 7.6m at 2.08% Cu

o CNN-21-06: 53m at 0.91% Cu including 20.8m at 1.14% Cu

o CNN-21-07: 9.7m at 0.70% Cu

o CNN-21-11: 7m at 1.21% Cu

o CNN-22-01: 26m at 1.28% Cu

o CNN-22-06: 15m at 1.24% Cu

o CNN-22-07: 41.5m at 1.36% Cu

o CNN-22-08: 33.4m at 1.08% Cu including 18.9m at 1.23% Cu

o CNN-22-09: 25m at 0.65% Cu

o CNN-22-10: 3.3m at 0.82% Cu

o CNN-22-13: 4.9m at 1.25% Cu

o CNN-22-16: 22.5m at 1.15% Cu

o CNN-22-21: 34.1m at 1.35% Cu including 19.5m at 1.60% Cu

Please refer to news releases dated December 29, 2021, March 15, 2022 and April

26, 2022 for previous drill assays.

Figure 1: Cinabrio Norte Drill Collar Plan (2021-22 completed holes in green, historic holes

in grey)

Quality Control

Sample preparation, analysis and security procedures applied on the BMR exploration

projects is aligned with industry best practices. BMR has implemented protocols and

procedures to ensure high-quality collection and management of samples resulting

in reliable ex ploration assay data. BMR has implemented formal analytical quality

control monitoring for all field sampling and drilling programs by inserting blanks and

certified reference materials into every sample sequence dispatched.

Sample preparation is performed by ALS Global - Geochemistry Analytical Lab in La

Serena, Chile and sample analyses by ALS in Lima, Peru. ALS analytical facilities are

commercial laboratories and are independent from BMR. All BMR samples are

collected and packaged by BMR staff and deli vered upon receipt at the ALS

Laboratory. Samples are logged in a sophisticated laboratory information

management system for sample tracking, scheduling, quality control, and electronic

reporting. Samples are dried then crushed to 70% < -2 millimeters and a riffle split

of 250 grams is then pulverized to 85% of the material achieving a size of <75

microns. These prepared samples are then shipped to the ALS Laboratory in Lima

Peru for analyses by the following methods:

• ME-ICP61: A high precision, multi -acid digest including Hydrofluoric, Nitric,

Perchloric and Hydrochloric acids. Analysed by inductively coupled plasma

(“ICP”) mass spectrometry that produces results for 48 elements.

• ME-OG62: Aqua -Regia digest: Analysed by ICP -AES (Atomic Emission

Spectrometry) or sometimes called optical emission spectrometry (ICP -OES)

for elevated levels of Co, Cu, Ni and Ag.

Certified standards are inserted into sample batches by ALS. Blanks and duplicates

are inserted within each analytical r un. The blank is inserted at the beginning,

certified standards are inserted at random intervals, and duplicates are analysed at

the end of the batch.

Additional Information

Michael Schuler, Battery Mineral Resources Corp. Chile Exploration Manager,

supervised the preparation of and approved the scientific and technical information

in this press release pertaining to the Punitaqui Exploration Drill Program. Mr. Schuler

is a qualified person as defined by National Instrument 43 -101 - Standards of

Disclosure for Mineral Projects.

About Battery Mineral Resources Corp.

Battery Mineral Resources (“BMR”) is a battery minerals company providing

shareholders exposure to the global mega-trend of electrification while being focused

on growth through cash -flow, ex ploration, and acquisitions in favourable mining

jurisdictions. Battery Mineral’s mission is the discovery, acquisition, and development

of battery metals (namely cobalt, lithium, graphite, and copper), in North America,

South America and South Korea, to b ecome a premier and responsible supplier of

battery minerals to the electrification marketplace. BMR is currently pursuing a

potential near-term resumption of mine operations, followed by copper production in

late 2022, of the Punitaqui Mining Complex, a p ast copper-gold producer located in

the Coquimbo region of Chile. Punitaqui, operating as recently as April of 2020, has

a 9+ year operating history and produced between 20 and 25 million pounds of

copper annually. BMR is the largest mineral claim holder i n the historic Gowganda

Cobalt-Silver Camp in Ontario, Canada, and continues to pursue a focused program

to build on the recently announced, +1-million-pound high-grade cobalt resource at

McAra. In addition, Battery Mineral owns 100% of ESI Energy Services, Inc., and its

US subsidiary Ozzie’s, Inc. (http://ozzies.com), a profitable mainline pipeline and

renewable energy equipment rental and sales company with operations in Alberta,

Canada and Arizona, USA. Battery Mineral Resources is based in Canada and its

shares are listed on the Toronto Venture Exchange under the s ymbol “BMR” and on

the OTCQB under the symbol “BTRMF”. Further information about BMR and its

projects can be found on our website, www.bmrcorp.com.

For more information, please contact:

Martin Kostuik, CEO

Martin Kostuik

Phone: +1 (604) 229 3830

[email protected]

Mars Investor Relations

+1 (604) 335-1976

[email protected]

Harbor Access Corp.

475-477-9402

[email protected]

Twitter: @BMRcorp_

www.bmrcorp.com

Neither the TSXV nor its Regulation Services Provider (as that term is defined in the

policies of the TSXV) accepts responsibility for the adequacy or accuracy of this

press release.

Forward Looking Statements

This news release includes certain “forward -looking statements” under applicable

Canadian securities legislation. There can be no assurance that such statements will

prove to be accurate, and actual results and future events could differ materially from

those anticipated in such statements. Forward-looking statements reflect the beliefs,

opinions and projections of the Company on the date the statements are made and

are based upon a number of assumptions and estimates that, while considered

reasonable by the Company, are inherently subject to significant business, economic,

competitive, political and social uncertainties and contingencies. Many factors, both

known and unknown, could cause actual results, performance, or achievements to be

materially different from the results, performance or achievem ents that are or may

be expressed or implied by such forward -looking statements and the parties have

made assumptions and estimates based on or related to many of these factors. Such

factors include, without limitation, the ability of the Company to obtain sufficient

financing to complete exploration and development activities, the ability of the

Company to complete the Debenture offering, risks related to share price and market

conditions, the inherent risks involved in the mining, exploration and development of

mineral properties, the ability of the Company to meet its anticipated development

schedule, government regulation and fluctuating metal prices. Accordingly, readers

should not place undue reliance on forward-looking statements. Battery undertakes

no obligation to update publicly or otherwise revise any forward -looking statements

contained herein, whether because of new information or future events or otherwise,

except as may be required by law.