Vancouver, British Columbia – (April 13, 2022 ) – Battery Mineral Resources Corp.
(TSXV: BMR) (OTCQB: BTRMF) ("Battery" or “BMR” or the "Company") is extremely
pleased to announce encouraging drill core assay results from the recently completed
Phase 1 exploration and in-fill drill program at the Dalmacia target of the Punitaqui
mine complex (‘Punitaqui”) in Chile. Drilling continues at the Cinabrio Norte target
where two diamond drills are in operation. The Punitaqui mine is slated for
resumption of copper concentrate production in mid to late-2022.
The Dalmacia target is located in the southern portion of the Punitaqui area about six
kilometers (“km”) south of the Punitaqui copper processing plant. The Dalmacia
target has underground mining access, partially delineated mineralized zones and is
targeted as a potential new source of ore feed to the Punitaqui plant (see Figure 1).
Highlights
• Final assay results for the following Dalmacia drillholes include (see Table 1):
o DS-21-17: 12 meters (“m”) at 3.15% Copper (“Cu”), 47m at 1.34%
Cu including 28 at 1.39% Cu
o DS-21-30: 7m at 1.31% Cu and 3m at 1.31% Cu
o DS-21-31: 12m at 097% Cu, 3m at 1.55% Cu and 3m at 2.81% Cu
o DS-22-01: 3m at 1.26% Cu
o DS-22-02: 21m at 1.16% Cu, 11m at 1.28% Cu and 33m at 1.54%
Cu including 11m at 3.25% Cu
o DS-22-03: 5m at 0.97% Cu
o DS-22-05: 2m at 3.23% Cu
o DS-22-06: 17m at 2.21% Cu
o DS-22-07: 3m at 0.98 Cu
o DS-22-08: 24m at 0.81% Cu including 15m at 1.00% Cu and 9m at
1.24% Cu
• The phase 1 drill program at Dalmacia of 9,757 meters in 52 drill holes is
complete.
• Significant copper mineralization was reported in 43 of the 52 -hole phase 1
Dalmacia North program.
• Geological drill cross-sections are being compiled and updated. Once completed
an updated 3D geological model will be finalized.
• Once final assays results are received, the new 3D geological model and assay
database will form the basis of a resource estimate to be completed by JDS Energy
& Mining Inc., our independent consultants.
• Preliminary planning for a follow -up infill Reverse Circulation (“RC”) program at
Dalmacia North and an exploration and infill drill program of the remaining 1,000m
of strike length at Dalmacia is well underway.
Battery Vice President of Exploration, Peter Doyle states, “These drilling results
further confirm the presence of high-grade copper mineralization at Dalmacia North.
Overall, the 2021-2022 Dalmacia North assay results are far better than expected.
The current drilling has greatly enhanced our understanding of the structural controls
of the copper mineralization at Dalmacia North. The ongoing r e-interpretation of
historic and current drilling as a series of cross-sectional views is being collated into
an updated 3D geological model which will form the basis for a resource estimate.
This enhanced geological understanding will then be applied to future infill and step-
out drilling over the 1,000m of strike length at Dalmacia that remains untested during
the 2021-2022 phase 1 program.
Battery CEO Martin Kostuik adds, “ We are very pleased with the progress of the
Dalmacia drill program which is shaping up to give Dalmacia a strong potential to be
a significant contributor to the future of the Punitaqui mine. Continued results like
these as we move forward towards the updated resource statement and planned
restart of our former producing Punitaqui copper mine in Chile will give our investors
an opportunity to participate in a potentially signif icant re-rating in BMR’s valuation
as we transition from development to operations and positive cash flow. We look
forward to providing further exciting updates f rom the progression of the Punitaqui
project.”
Dalmacia Drill Program
The 2021-22 phase 1 drill program, completed last week, consisted of 9,757m in 52
diamond core holes (see Figure 1 and Figure 2). The geological setting of the
Dalmacia target is different from the Cinabrio orebody which is located 20 kilometers
to the north. Dalmacia is situated within a roof-pendant of volcanic rocks, with minor
calcareous intercalations of Middle to Upper Jurassic age. This volcano -sedimentary
complex is intruded by younger aged granites located in a reverse fault.
Copper-gold mineralization is related to regional structures and deformation zones,
developed in the contacts between granite, sub-volcanic andesitic porphyry intrusives
and volcano-sedimentary rocks. Controls on mineralization include small scale shear
zones, intrusive contacts, vesicular andesites and alteration zones. High -grade
copper mineralization occurs in small pods which locally occur in clusters enveloped
within low-grade mineralization.
The upper portion of the Dalmacia target is accessed via a portal and an underground
ramp with limited level development. The c ompleted Phase 1 drill program was
designed to infill and confirm the continuity of mineralization between previous
drilling and includes a series of step -out holes to test th e potential adjacent to the
main zone of copper-gold-silver mineralization as defined by historic drilling.
Complete assay results were recently received for ten holes: DS-21-17, DS-21-30
and DS-21-31 as well as DS-22-01, DS-22-02, DS-22-03, DS-22-05, DS-22-06, DS-
22-07 and DS-22-08 (see Table 1). A summary of the targeting rationale and results
for the significant recent drillholes follows below.
DS-21-17 was planned to test continuity of mineralization between drill holes DAL-
38 (16m @ 1.24% Cu) and DS-11-14 (29 m @2.06% Cu). The drill hole intersected
47 meters of at 1.47% Cu from 97m, including 12 m at 1.87% Cu. This intersection
is interpreted to confirm continuity of mineralization between the intersection in DAL-
38 and DS -11-14. There are additional intersections shallower in the drill hole
including 9m at 1.24% oxide Cu from 37 m and 12m of 3.15% Cu from 60m. The
latter intersection in an extension of 17m at 4.38% Cu , in h istorical reverse
circulation drill hole SD-37.
DS-21-30 was designed to test an area between prior drill holes with multiple well
mineralized drill intersections. Results support the interpretation that mineralization
is primarily located in westward dipping lenses. Results include 7m at 1.31% Cu from
71m and 3m at 1.31% Cu from 110m.
DS-21-31 was drilled to test area of historic surface workings in the northeast part
of the target are and intersected massive porphyritic andesite at depth with intervals
of copper mineralization including 12m at 0.97% Cu from 60m and 3m at 2.81% Cu
from 77m. The relatively narrow zones of mineralization intersected confirm that the
primary host for mineralization at Dalmacia is ocoite.
DS-22-01 was drilled to test the northern limit of known mineralization in the target
area. The hole encountered principally variably altered ocoites which are locally
sheared. One zone of significant mineralization was intersected (3m at 1.26% Cu
from 99m) which is interpreted as the downdip and northward extension of a copper
intercept in DS-22-02 (2m at 1.22% Cu from 75m).
DS-22-02 is located in the northeastern part of the target area. It was designed to
test the same zones of mineralization encountered in DS -21-29 from a different
direction. The drill hole intersected 21m of oxide mineralization at 1.16% Cu from
40m, 11m at 1.28% Cu from 79m and 33m at 1.54% Cu from 174m. The oxide
mineralization from 40m is interpreted to corelate with the sulfide intersection in DS-
22-06 from 71m (17m at 2.21% Cu), the intersection of 11m at 1.28 % Cu is
interpreted to correlate with mineralized intercepts in DS-21-29. The intersection of
33m at 1.54% Cu is a newly discovered zone of mineralization.
DS-22-03 was planned to test the northeastern part of the target area north of
previous drilling. This vertical drill hole intersected two narrow zones of mineralization
and was too shallow to test deeper zones of mineralization discovered in subsequent
holes in the same area. Results include 5m at 0.97% Cu from 52m and 2 m at 1.22%
Cu from 75m. Follow-up drilling to a deeper extend is recommended.
DS-22-05 was designed to test the northern limit of mineralization in the north
central part of the target area. The drill hole intersected principally variably altered
ocoites with numerous unmineralized shear zones. Results successfully include 2m at
3.23% Cu from 115m. This intersection is interpreted to be the down dip extension
of mineralization intersected by DS-22-06 (17m at 2.21% Cu).
DS-22-06 was planned to test the northern limit of mineralization in the north central
part of the target area. The drill hole intersected principally variably altered ocoites
with a strong zone of mineralization concentrated along the contact of ocoite with
vesicular ocoite. This contact zone successfully returned results of 17m at 2.21 % Cu
from 71 m. Follow up drilling to continue furthering the extents to the north in this
area is warranted.
DS-22-07 was drilled to test the northern limits of mineralization in the target area.
The drill hole encountered principally variably altered ocoites with narrow zones of
copper mineralization. Results include 1m at 1.62% Cu from 51m, 3m at 0.98% Cu
from 111m and 2m at 0.92% Cu from 150m. Along with other drill holes, the results
indicate that the mineralization is reducing towards the north in this north-western
part of the target area.
DS-22-08 was designed to better determine the geometry of a zone of mineralization
intersected by DS-21-06 (14m at 2.44% Cu) and DS-21-14 (9m at 1.53% Cu). DS-
22-08 successfully intersected 6m at 1.30% Cu from 147m, 24m at 0.81% Cu from
182m and 3m at 1.14% Cu from 217 m. The i ntersection of 6m from 147m is
interpreted to correlate with the intersection of 14m at 2 .44% Cu in DS-21-06. The
deeper intersection in DS-22-08 from 217m depth correlates with the intersection of
24m at 0.81% Cu in DS-22-08.
Significant BMR prior assay results received to date for the Dalmacia 2021-22 drilling
include the following (see Table 2):
• DS-21-01: 23m at 1.16% Cu, including 13m at 1.56% Cu
• DS-21-06: 32m grading 0.73% Cu including 16m at 1.15% Cu and
95m at 0.78% Cu including 29m at 1.45% Cu, including a higher-grade
interval of 14m at 2.44% Cu
• DS-21-07: 33m at 1.77% Cu, including intervals of 9.0m at 3.44% Cu,
and 7m at 2.54% Cu, and 10m at 0.84% Cu, and 6m at 2.19% Cu
• DS-21-08: 102m at 1.41% Cu including 78m at 1.67% Cu and 16m at
3.52% Cu
• DS-21-11: 24m at 1.04% Cu including 4m at 1.60% Cu and an interval
of 6m at 1.95% Cu
• DS-21-18: 68m at 1.14% Cu including 14m at 2.07% Cu
• DS-21-19: 36m at 0.99% Cu and 6m at 1.30% Cu
• DS-21-21: 53m at 2.34% Cu including 17m at 3.77% Cu
• DS-21-24: 21m at 0.64% Cu including 4m at 1.21% Cu
• DS-21-25: 20m at 1.22% Cu including 6m at 2.87% Cu and 6m at
1.46% Cu and 5m at 1.57% Cu
• DS-21-26: 33m at 1.64% Cu including 21m at 2.05% Cu
• DS-21-28: 20m at 1.38% Cu and 3m at 1.13% Cu
Table 1: New BMR-Dalmacia Target Significant Assays
Drillhole
Number
From
(m)
To
(m)
Sample
Interval
(m)
Copper
(%)
Silver
(g/t)
Gold
(g/t)
DS-21-17 37 46 9 1.24 0.5
and 60 72 12 3.15 2.32
and 97 144 47 1.34 0.66
including 97 125 28 1.39 1.02
and 132 144 12 1.87 0.14 0.021
DS-21-30 71 78 7 1.31 0.91 0.106
DS-21-30 102 113 11 0.68 0.53
including 110 113 3 1.31 1.23 0.017
DS-21-31 60 72 12 0.97 0.52
including 60 63 3 1.76 0.8
and 69 72 3 1.55 1.07
and 77 80 3 2.81 2.17 0.057
DS-22-01 99 102 3 1.26 0.4
DS-22-02 40 61 21 1.16 1.24
and 61 63 2 1.50 0.7
and 79 90 11 1.28 1.16
including 79 84 5 1.33 1.04
and 86 90 4 1.78 1.7 0.005
and 110 118 8 0.71 1.0
including 110 112 2 1.12 2.5
and 115 118 3 0.94 0.6
and 130 132 2 1.18 0.4 0.051
and 145 149 4 0.92 0.4 0.007
and 174 207 33 1.54 3.78
including 174 197 23 2.07 4.94
including 186 197 11 3.25 8.82 0.012
DS-22-03 52 57 5 0.97 1.6 0.066
and 75 77 2 1.22 0.7 0.042
DS-22-05 115 117 2 3.23 1.2
DS-22-06 71 88 17 2.21 2.38
DS-22-07 32 34 2 0.81 0.4
and 51 52 1 1.62 0.4
and 57 59 2 0.55 0.7
and 111 114 3 0.98 0.6
and 150 152 2 0.92 0.4
DS-22-08 79 82 3 0.82 0.4
and 147 153 6 1.30 0.7
including 147 149 2 2.99 1
and 157 165 8 0.57 0.4
DS-22-08 182 206 24 0.81 0.64
including 182 185 3 1.07 1.13
and 191 206 15 1.00 0.6
including 196 205 9 1.24 0.47
and 217 220 3 1.14 0.4
Note: All intervals are downhole core lengths
Table 2: Prior (2021) BMR - Dalmacia Target Significant Drill Assay Intervals
Drillhole
Number
From To Sample
Interval
(m)
Copper Silver Gold
(m) (m) (%) (g/t) (g/t)
DS-21-01 79 91 12 1.79 2.5 0.028
including 80 88 8 2.44 3.2 0.035
and 105 128 23 1.16 1.7 0.016
including 115 128 13 1.56 2.1 0.024
including 115 122 7 2.32 3.1 0.036
and 137 139 2 1.06 0.7 0.03
and 180 184 4 0.89 0.4 -
and 220 224.9 4.9 0.72 0.6 -
DS-21-02 22 29 7 1.67 2.6 0.08
and 64 74 10 1.03 2.1 -
including 64 67 3 1.49 2.3 -
and 71 73 2 2.34 5 -
and 99 106 7 2.58 2.7 -
and 177 188 11 1.08 0.9 0.08
including 177 181 4 2.32 1.4 0.17
including 177 180 3 2.9 1.7 0.22
DS-21-03 46 61 15 1.01 1.2 0.017
including 46 50 4 2.47 3.1 0.05
DS-21-04 70 76 6 0.71 0.9 0.012
including 72 76 4 0.87 1 0.01
and 89 102 13 0.64 0.9 -
including 93 95 2 1.24 1.5 -
DS-21-05 52 58 6 1.16 1.7 0.017
and 131 132 1 1.81 0.4 0.695
and 141 143 2 2.98 5 3.835
and 155 156 1 3.22 2 -
DS-21-06 37 69 32 0.73 0.5 -
including 37 53 16 1.15 0.6 0.06
including 37 44 7 1.75 0.8 0.079
and 112 115 3 2.14 0.6 0.03
and 134 139 5 1.58 0.4 0.019
and 167 262 95 0.78 0.5 -
including 167 170 3 1.84 0.8 0.096
and 183 187 4 1.75 0.6 0.071
and 19 262 65 0.93 0.5 -
including 197 211 14 2.44 0.7 0.039
and 243 262 19 1.1 0.6 0.022
including 243 251 8 1.88 0.7 0.029
and 260 262 2 1.79 0.7 0.06
DS-21-07 24 57 33 1.77 1.5 0.052
including 24 33 9 3.44 1.6 0.167
and 39 46 7 2.54 3.5 0.02
and 84 94 10 0.84 1.2 0.032
and 176 182 6 2.19 0.4 -
DS-21-08 48 150 102 1.41 1.2 -
including 48 126 78 1.67 1.4 -
including 48 64 16 3.52 4.5 0.017
DS-21-10 138 140 2 2.4 1 -
DS-21-11 59 61 2 1.14 2 0.043
and 78 102 24 1.04 0.5 -
including 78 88 10 1.06 0.5 -
including 78 82 4 1.6 0.4 -
including 86 88 2 1.78 1 -
and 96 102 6 1.95 0.4 -
DS-21-12 116 121 5 0.62 1 -
and 143 145 2 0.95 1 -
and 161 172 11 0.82 0.5 -
DS-21-13 44 62 18 1.61 0.7 0.01
and 135 147 12 2.13 1.5 -
including 139 147 8 2.95 1.9 -
and 157 162 5 3.26 0.9 -
and 181 188 7 1.87 0.7 -
DS-21-14 73 82 9 0.74 0.7 0.038
including 78 82 4 1.03 0.7 0.05
and 145 160 15 1.16 0.4 -
including 145 152 7 1.44 0.4 -
and 172 174 2 1.11 0.4 -
and 186 195 9 1.53 1.6 0.052
and 205 209 4 1.5 0.4 0.24
DS-21-16 74 82 8 5.29 0.026
and 102 110 8 3.53 0.065
DS-21-09 89 91 2 0.88 1.3 -
and 98 114 16 1.84 0.5 -
including 101 113 12 2.18 0.6 -
and 234 236 2 1.35 0.5 -
DS-21-15 128 136 8 1.14 1.2 0.023
including 128 131 3 1.58 1.8 0.032
and 133 136 3 1.36 1.3 0.025
DS-21-18 12 80 68 1.14 0.9 -
including 12 38 26 1.48 0.8 -
including 12 26 14 2.07 1 -
and 46 62 16 1.43 1.4 -
and 72 80 8 1.5 1.1 0.009
DS-21-19 12 48 36 0.99 0.3 -
and 66 72 6 1.3 0.7 -
DS-21-20 56 70 14 1.3 0.7 -
including 62 70 8 1.27 0.9 0.521
and 116 120 4 0.72 0.1 -
and 140 144 4 1.79 0.4 -
DS-21-21 68 121 53 2.34 0.8 -
including 76 121 45 2.57 0.9 0.047
including 104 121 17 3.77 0.8 0.1
DS-21-22 60 64 4 3.6 2.5 -
and 93 96 3 1.12 0.3 0.044
and 128 130 2 1.06 0.1 -
DS-21-23A 39 57 18 1.05 0.3 -
including 40 44 4 1.92 0.9 0.069
including 48 50 2 2.05 0.1 0.178
including 55 57 2 1.54 0.1 0.065
and 94 113 19 1.36 0.8 -
including 97 102 5 2.44 1.1 0.468
and 110 113 3 1.96 1.7 0.112
DS-21-24 75 96 21 0.64 0.8 -
including 92 96 4 1.21 2.1 -
and 115 117 2 1.02 0.6 -
DS-21-25 52 72 20 1.22 1.2 -
including 52 58 6 2.87 3.2 0.149
and 210 216 6 1.46 0.3 -
and 224 229 5 1.57 0.1 -
DS-21-26 72 105 33 1.64 4.8 -
including 77 98 21 2.05 6.9 -
DS-21-27 68 73 5 1.45 0.7 -
including 68 72 4 1.64 0.8 0.005
DS-21-28 79 99 20 1.38 0.6 -
and 106 109 3 1.13 0.9 0.079
and 121 123 2 1.15 0.1 0.079
Note: All intervals are downhole core lengths