Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

BLLG.CN ·

Blue Lagoon Delivers Positive PEA For Its Dome Mountain Gold Mine Project

Economic Studies

FSE: 7BL

CSE: BLLG

OTCQB: BLAGF

___________

BLUE LAGOON DELIVERS POSITIVE PEA FOR ITS

DOME MOUNTAIN GOLD MINE PROJECT

May 19, 2020 – Vancouver, British Columbia – Blue Lagoon Resources Inc. (the “Company”) (CSE: BLLG;

FSE: 7BL; OTCQB: BLAGF) is pleased to announce a mineral resource and a positive preliminary economic

assessment (PEA) for the company's Dome Mountain Mine (“Dome Mountain”) gold deposit, located a short 50

minute drive from the town of Smithers, B.C. The PEA was completed by Roughstock Mining Services of Bozeman,

Montana.

The Dome Mountain Gold Mine Project currently holds a Mining Permit and Environmental Management Act

Permit (EMA) providing for up to 75,000 tonnes annually. The PEA considers the economics of a 100 tonnes per

day mining operation, (~36K tonnes annually) which is half the tonnage provided for under the existing permit.

Over the 12 year planned mine life, the PEA projects that 85,000 payable ounces are recoverable, with the first five

years recovery to be 45,000 payable ounces, at a per ounce cash cost of $US 987 and selling price of $US 1,450 per

ounce of gold, providing on average $CAD 2.32 million per year after tax free cash flow, using a discount rate of

5%, during that initial five year period.

The fact that this project has extensive existing development and infrastructure results in the additional projected

capital cost to resume mining operations being only $CAD 1.46 million, primarily for completing items under three

required amendments to the existing mine permit. These items include the completion of the water treatment plant,

underground bolting and vent raise, and the completion of the mine reclamation and closure plan. This low capital

cost results in an internal rate of return of 277% using a 5% discount.

Furthermore, extensions along the Boulder Vein 43-101 resource area and the existing 17 high-grade vein targets

located on the 10,970-hectare property, (41 contiguous claims and one mining lease; BLLG Press release, May 4,

2020) offer an attractive opportunity to add additional ounces to the current mineral resource through step-out and

exploration drilling.

Blue Lagoon’s President and CEO, Rana Vig stated: "Dome Mountain is a technically simple gold project in a safe,

politically stable jurisdiction with a long tradition of gold mining. The PEA projects positive project economics and

IRR based on the relatively low capital expenditures which come from the fact that much of the investment in the

mine infrastructure was already made before we acquired the project, leaving less than $1.5 million needed to

complete the three key amendments required by the existing mine permit to re-commence mining.”

Mr. Vig added: "At US $1,450 per ounce gold, the PEA includes a projected free cash flow of $11.6 Million using

a discount rate of 5%, over the first 5 years of mining. This cash flow is prior to applying significant available tax

credits of Gavin Mines, the Company’s subsidiary that holds the project. This represents potential cash that, if

realized, will allow the company to focus on expanding future drill programs to explore the other 17 high grade

veins that surround the mine – while reducing potential dilution to shareholders."

Tax credits, including tax loss carry-forwards, CDE and CEE total $23 million. After applying those tax credits,

the Company projects a five year after-tax cash flow of $13.9 million using a 5% discount rate, or approximately

$2.8 million per year for that period.

PEA SUMMARY

Economics Overview

Economics are based on indicated and inferred resources as incorporated into a 12 year mine plan followed by three

years of reclamation for a complete project evaluation period. Five-year economics are presented only to

characterize the portion of the mine plan that develops indicated resources. Unless otherwise stated, all per ounce

values are in US dollars with all other dollar figures in Canadian dollars ("CAD$"). Masses are in metric tonnes.

Production rate used is 100 tonnes per day. Exchange rate is $0.71 USD for each $1.00 CAD$. Gold and silver per

troy ounce sales prices of US$1,450 and $14.50 respectively are chosen based on market at time of issuance of this

press release. All monetary values are in constant dollar terms (i.e., no inflation or escalation) and no leverage is

included.

Economic Summary - $CDN Millions

5 year 12 year

Gross Revenue $95.4 $179.0

Pre-tax NPV 5 $13.8 $15.2

Pre-tax Internal Rate of Return 280% 280%

LOM Pre-tax cash flow (undiscounted) $17.0 $19.4

After-tax NPV 5 $11.6 $11.7

After-tax Internal Rate of Return 277% 277%

LOM after-tax cash flow (undiscounted) $14.2 $14.2

Payable Au Sold - ounces 45,433 85,231

Gold price - $US/oz $1,450 $1,450

Cash operating costs - $US/oz $987 $1,124

Preproduction Capital $1.46 $1.46

The PEA is preliminary in nature and includes inferred mineral resources that are considered too speculative

geologically to have the economic considerations applied to them that would enable them to be categorized as

mineral reserves. There is no certainty that the PEA will be realized.

Gold Price Sensitivities

The following table presents the after-tax sensitivities of NPV and IRR to gold price changes.

Five Year Gold Price Sensitivity Base Case

Gold price $1,250 $1,450 $1,650

After-tax NPV 5 $7.2 $11.6 $16.0

After-tax Internal Rate of Return 152% 277% 397%

LOM after-tax cash flow

(undiscounted) $8.9 $14.2 $19.4

PEA Details

The PEA included consideration of the following summary elements.

Project Background

Dome Mountain Mine has a large and detailed database as a result of $28M spent in the last 12 years on exploration,

engineering, environmental studies and mine infrastructure construction on the project. During that period,

exploration drilling and resource modeling, geotechnical drilling and modelling, bulk mining and test milling

provided a large data set to the project team. The project also has metallurgical sampling and testing completed both

by previous owners and an independent lab, reviewed by Roughstock Mining Services, to support the initial

engineering design (Godfrey Mhembere, Senior Mining Engineer). This data provides important background and

will also aid in the design of future work on the project.

Mining & Processing

The PEA utilizes an underground mining scenario where the Boulder Veins are mined from existing underground

infrastructure and extend the existing underground ramp system to access additional resources. A 3-month period

of rehabilitation of existing underground development is proposed in Year 0 of the mine plan and is accounted for

in pre-production capital. Gavin Mines has an off-site toll milling and profit-sharing agreement with Nicola Mining

Inc. to provide for offsite milling and concentrating of Dome mineralized material. Completion of a 33m long

ventilation raise is also included in pre-production capital. The PEA conceptual mine plan provides for an average

mining rate of 100 tonnes per day. The Company owns 78% of the Dome Mountain Mine. All references herein

are presented on a 100% ownership basis.

Mining Plan and Processing Summary

Volumes of mineralized material, waste and produced and salable gold are tabulated below for the full

12 year mine plan and a 5-year subset.

Production and Grade Summary

5 year 12 year

Tonnes 183,970 436,321

Waste Tonnes 112,649 114,401

Au Grade - g/tonne 8.42 6.66

Ag Grade - g/tonne 34.57 27.35

Mined Au Ounces 49,817 93,455

Mined Ag Ounces 204,484 383,604

Payable Au Ounces [1] 45,433 85,231

Payable Ag Ounces [2] 139,049 260,851

[1] Payable Au Ounces = Mined Ounces X Mine Recovery Factor (95.0%) X Processing Recovery Factor (96.0%)

[2] Payable Ag Ounces = Mined Ounces X Mine Recovery Factor (85.0%) X Processing Recovery Factor (80.0%)

Operating Costs

Mining costs for mining, processing and other costs were developed from a mix of first-principle engineering and

guidance provided from Company consultants.

Operating Cost Summary - $CAD/tonne

5 year 12 year

Total Mining $ 157.41 $ 97.63

Mine G&A $ 37.72 $ 37.72

Transportation $ 87.50 $ 87.50

Processing $ 60.00 $ 60.00

Total Operating Cost $ 342.63 $ 282.85

Diesel fuel price is $0.90 per liter.

Unit Costs - $US per ounce sold

5 year* 12 year

Total Mining $ 453.67 $ 449.01

Mine G&A $ 108.71 $ 137.44

Transportation $ 252.18 $ 318.82

Processing $ 172.92 $ 218.62

Total Operating Cost $ 987.48 $ 1,123.88

* reclamation costs not in subset, only in full mine plan.

Pre-Production Capital Costs

Initial capital costs in the PEA are CAD $1. 46 million including a 10% contingency of $132,724. The pre-

production capital includes the following line items:

Rehabilitation Capital - $CAD

Rehab UG workings $ 326,612

Vent Raise $ 134,125

Water Treatment Plant $ 285,000

Rescue Station $ 120,000

Mined Material Storage Building $ 100,000

Environmental Consulting $ 211,500

Loader Purchase $ 150,000

Contingency @ 10% $ 132,724

Total Pre-Production Capital $ 1,459,961

Opportunities to Enhance Value

Although Blue Lagoon considers the PEA results for the base case to be excellent, future opportunities are available

which can further enhance the value of the Dome Mountain Project beyond the base case. Some of those

opportunities are as follows:

• Life of mine in the current PEA is twelve years. The resource update highlights 128,173 ounces Au

currently estimated in the inferred category. Blue Lagoon will target this inferred resource in its 2020 phase

one drilling program with the goal of updating a significant portion of this category to indic ated and

potentially increasing the overall life-of-mine scenario.

• The Dome Mountain Project hosts several identified gold bearing quartz vein targets which are available

for drilling on the 10,970-hectare property. These targets offer opportunity to potentially expand the

resource at the Dome Mountain project through exploration drilling.

• The Economic Sensitivities to gold price are highlighted in this PEA. Forward looking opportunities exist

at a higher gold price.

• The mine plan delimited in this PEA uses a 100 tonne per day mine rate (~36K tonnes annually). The mine

production limit in the Company’s current mine permit is 75,000 tonnes annually. Blue Lagoon’s goal is to

initiate mining at the lower production rate and complete a safe and efficient mining production schedule.

In due course, following additional exploration drilling, Blue Lagoon would evaluate incorporating any

potential expansion of the resource into the mine plan to increase production up to the defined limits of the

Mining Permit.

• The current mine plan at Dome Mountain includes ramp and fill, and sub-level longhole mining methods

with a minimum mining width of 2.25 meters. Once production is re-started at Dome, resue or narrow vein

back-stoping methods, will be tested in narrow mineralized material widths to reduce the overall dilution,

and improve the mined/shipped material grades. With success of resue mining, mined waste tons will be

reduced, grade of the shipped material to the off-site mill will be increased, potentially reducing mining,

shipping, and milling costs and improving the overall profit margin.

Mineral Resource Estimate

The mineral resource estimate incorporates work completed on the project database since the previous historical

resource provided in the April 2010 technical report entitled “Technical Report on the Dome Mountain Gold-Silver

Project Omineca Mining Division British Columbia” prepared by Gary Giroux, Peng for Gavin Mines. In addition,

the update utilizes drilling that took place in 2016 and consisted of 35 Drill holes (DDH) totalling 6969.2 meters.

The current mineral resource estimate represents a substantial increase to the historical resource estimate provided

in the 2010 technical report. Based on Cut and Fill parameters and a Au cutoff of 3.42g/tonne, this current mineral

resource estimate adds 10,926 ounces gold and 70,893 ounces silver to the indicated category and, 59,073 ounces

gold and 160,354 ounces silver to the inferred category, when compared to the 2010 historical resource estimate

(note that NI 43-101 incorporated a revised definition of “inferred mineral resource” in 2014).

The current resource estimate shown below is based on 398 holes (39,398 meters) completed at the Dome Project

over the period from 1985 to 2016 and were determined with an effective date of May 1, 2020. Holes drilled prior

to 2009 have been verified using cumulative frequency plots showing reasonable comparison between gold assay

results from the more recent drilling to those holes drilled earlier. The data underlying the resource estimate was

verified by Ms. Jennifer Evans, P.G., Senior Resource Geologist with Roughstock Mining Services, and a qualified

person as defined in NI 43-101.

The following parameters were used for the resource estimation

• Cut-off grade 3.42 gram/ton using a 2.25 meter cut and fill mining width.

• All veins were estimated using ordinary kriging.

• Inferred resource has 30m drill spacing. Indicated resource has 15m drill spacing.

• Effective Date of resource estimate, May 1, 2020.

INDICATED RESOURCE

CUT and FILL

AU CUTOFF GRADE

AG CUTOFF

GRADE

3.42 G/Tonne 23.94 G/Tonne

Gold Gold Gold Gold

Silver Ounces Tonnes Grade Grams Ounces

Boulder Vein 213,647 10.46 2,233,698 71,815 380,523

Boulder East Vein 13,629 14.71 200,462 6,445 25,260

TOTAL 227,276 10.71 2,434,160 78,260 405,783

INFERRED RESOURCE

CUT and FILL

AU CUTOFF

GRADE AG CUTOFF GRADE

3.42 G/Tonne 23.94 G/Tonne

Gold Gold Gold Gold Silver Ounces Tonnes Grade Grams Ounces

Boulder Vein 198,452 7.48 1,483,637 47,700 260,791

Boulder East Vein 174,754 6.75 1,178,854 37,901 35,820

Argillite Vein 108,175 9.39 1,015,467 32,648 167,781

Boulder HW Vein 48,803 6.32 308,671 9,924 8,162

TOTAL 530,183 7.52 3,986,629 128,173 472,554

Mineral resources that are not mineral reserves do not have demonstrated economic viability.

Planned 2020 Surface Diamond Drill Program

A surface diamond drilling program has been planned for the Dome Mountain Mine during the summer of 2020,

designed to infill drill on the Boulder East vein system. The primary goal of this infill drilling is to upgrade

approximately 33% of the zones currently classified as an inferred resource to an indicated resource. The drill

program is planned for 22 holes drilled from 8 existing drill pads for a planned total of 2,780 meters of HQ drill

core. The table below details the planned holes.

DOME MOUNTAIN MINE

PHASE ONE 2020 DRILL PROGRAM

Drill Pad Number of Holes Pad Total Meters

13 3 315

15 2 170

16 3 285

17 1 210

29 7 1,180

30 1 60

26 3 295

2020 Total Meters 2,515

Two additional drill holes have been planned for the summer 2020 drill program that would target a roughly

north/south trending mineralized zone, the 79 Trend, which has been identified in previous drilling but remains

poorly defined. These holes would be drilled from an existing pad and is targeted to provide better definition of the

79 Trend.

79 TREND DRILL PROGRAM

Drill Pad Number of Holes Pad Total Meters

8 2 265

79 Trend Total Meters 265

The PEA was prepared pursuant to National Instrument 43-101 ("NI 43-101") by Roughstock Mining Services

(Montana) – Steve Cutler, P.G, QP; Jason Todd, P.G Senior Geologist; Jennifer Evans, P.G. Senior Resource

Geologist; Godfrey Mhembere, Senior Mining Engineer. The team was led by Steve Cutler, P.G, QP. The Company

plans to file a technical report on the PEA on SEDAR at www.sedar.com within 45 days in accordance with NI 43-

101.

The scientific and technical data contained in this news release was approved by William Cronk, P.Geo., a qualified

person as defined in NI 43-101 and a consultant to the Company.

For further information, please contact:

Rana Vig

President and Chief Executive Officer

Telephone: 604-218-4766

Email: [email protected]

The CSE has not reviewed and does not accept responsibility for the adequacy or accuracy of this release.

Statement Regarding Forward-Looking Information: This release includes certain statements that may be deemed

"forward-looking statements". All statements in this release, other than statements of historical facts, that address

events or developments that Blue Lagoon Resources Inc. (the "Company") expects to occur, are forward-looking

statements. Forward-looking statements are statements that are not historical facts and are generally, but not

always, identified by the words "expects", "plans", "anticipates", "believes", "intends", "estimates", "projects",

"potential" and similar expressions, or that events or conditions "will", "would", "may", "could" or "should" occur.

Although the Company believes the expectations expressed in suc h forward-looking statements are based on

reasonable assumptions, such statements are not guarantees of future performance and actual results may differ

materially from those in the forward-looking statements. Factors that could cause the actual results to differ

materially from those in forward-looking statements include results of exploration activities may not show quality

and quantity necessary for further exploration and exploitation of minerals deposits, market prices, and continued

availability of capital and financing, permitting and other approvals, and general economic, market or business

conditions. In addition, forward-looking statements in this news release includes gold and silver price assumptions,

cash flow forecasts, projected capital and operating costs, metal or mineral recoveries, mine life and production

rates, and other assumptions used in the PEA. Investors are cautioned that any such statements are not guarantees

of future performance and actual results or developments may differ materially from those projected in the forward-

looking statements. Forward-looking statements are based on the beliefs, estimates and opinions of the Company's

management on the date the statements are made. Except as required by applicable securities laws, the Company

undertakes no obligation to update these forward-looking statements in the event that management's beliefs,

estimates or opinions, or other factors, should change.