Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

BKI.TO ·

Black Iron Files Re-Scoped Preliminary Economic Assessment Report FOR Phased Build Showing Post Tax 36.1% IRR and NPV of US$1.6 Billion

Economic Studies

BLACK IRON FILES RE-SCOPED PRELIMINARY ECONOMIC ASSESSMENT

REPORT FOR PHASED BUILD SHOWING POST TAX 36.1% IRR AND NPV OF

US$1.6 BILLION

For Immediate Release

TORONTO, CANADA, December 14, 2017 – Black Iron Inc. (“Black Iron” or the “Company”) (TSX: BKI;

OTC: BKIRF) has filed on SEDAR its National Instrument 43- 101 Technical Report entitled “ Preliminary

Economic Assessment of the Re -scoped Shymanivske Iron Ore Deposit” effective November 21, 201 7

(the “re-scoped PEA”) for its Shymanivske iron ore project located in Kryvyi Rih, Ukraine (the “Project”).

The re-scoped PEA is based on a two- phased build out of the mine and product ion plant with the first

phase operation producing 4MT per year of ultra high-grade 68% iron concentrate expanding to 8MT per

year starting in the fifth year of production. By phasing the build, it significantly reduces the up- front

construction costs of the Project thu s increasing the projected returns of the Project. The Project is able

to ex hibit superior projected economics due to its proximity to major infrastructure including, railway,

electrical power and a deep-sea port.

A long-term iron ore benchmark price of US$61.88/t for products containing 62% iron was used in the re-

scoped PEA and adjusted using the three-month average trailing spot iron premium of US$7.21 per 1%

Fe above 62% as of November 7, 2017. Based on this pricing, the Project forecasts a pre-tax unlevered

IRR of 42.6% and a NPV of US$2,115 million using a 10% discount rate as seen in the table below. The

after-tax unlevered IRR using this price and premium is 36.1% and NPV is US1,662 million.

Matt Simpson, Black Iron’s CEO, commented: “The long-term price used in the re-scoped PEA is lower

than the December month to date average price of US$69.95/t as reported by Metal Bulletin, which as

seen in the table below results in significant investor return projections. Further, once debt leverage is

added, the projected returns should further increase.”

Pre-Tax IRR and NPV at 10% Discount Rate

Sensitivity to Base 62% Fe CFR and %Fe Grade Premium

62% Fe

$/dmt

Fe Premium ($/dmt per 1% Fe)

$4.00 $5.00 $6.00 $7.21 $8.00 $9.00

$50.00

IRR 22.2% 26.4% 30.4% 35.2% 38.2% 41.9%

NPV10% $706M $977M $1,249M $1,577 M $1,792M $2,063M

$61.88

IRR 30.4% 34.3% 38.1% 42.6% 45.5% 49.1%

NPV10% $1,243M $1,515M $1,786M $2,115M $2,329M $2,600M

$70.00

IRR 35.6% 39.4% 43.1% 47.6% 50.4% 53.9%

NPV10% $1,611M $1,882M $2,153M $2,482M $2,696M $2,967M

$80.00

IRR 41.9% 45.6% 49.2% 53.5% 56.3% 59.7%

NPV10% $2,063M $2,334M $2,606M $2,934M $3,148M $3,420M

$90.00

IRR 48.0% 51.8% 55.1% 59.3% 62.0% 65.4%

NPV10% $2,515M $2,787M $3,058M $3,386M $3,601M $3,872M

Conditions considered to be extreme (combinations of low and high 62% benchmark price and %Fe

grade premium) are highlighted in brown in the above table as they are considered unlikely to occur.

The table below shows the highlights from the re- scoped PEA , which are further elaborated in the

detailed technical report filed on www.sedar.com under the Company’s profile.

PEA Highlights (all currency is US$)

IRR (pre-tax unlevered)

IRR (after-tax unlevered)

42.6%

36.1%

NPV at 10% discount (pre-tax unlevered)

NPV at 10% discount (after-tax unlevered)

$2.12 billion

$1.66 billion

Projected Years to Payback

Projected Years to Payback

2.6 years

2.9 years

Annual Production Rate: Phase 1

Phase 2

4 Mt

8 Mt

Capital Cost to build: Phase 1

Phase 2

$435.8 million

$312.2 million

Long Term Benchmark Iron Ore Price (62% Fe CFR Port in China) $61.88 /dmt

Final Product Iron Grade 68% Fe

Black Iron Projected Sale Price FOB Ukraine Port Yuzhny

(Including product quality adjustments and net shipping costs)

$97.19/dmt

Life of Mine FOB OPEX

(Includes mining, beneficiation, rail, ship loading and G&A costs)

$31.46/t

Proposed Initiation of Phase 2 Construction Post Phase 1 Startup Year 3

Estimated Mine Life (based on in-pit resources) 20 Years

The re-scoped NI 43- 101 PEA Report replaces the Company’s 2014 bankable feasibility study (“2014

BFS”) as the current technical report for the Project. Significant portions of the PEA remain unchanged

from the 2014 BFS, including sections relating to geology, exploration, drilling, sampling and data

verification, and the miner al resource estimate. Consistent with practice in the industry, this PEA has

been prepared with an engineering accuracy of +/ -35%. Please see the Company’s press release dated

November 21, 2017 for a summary of the assumptions used in the re-scoped PEA.

Re-scoped Preliminary Economic Estimate Study Report

The re-scoped PEA has been prepared in accordance with the guidelines of National Instrument 43- 101

by the independent firms BBA Inc. and Watts, Griffis and McOuat Limited (with the individual authors

identified below) and is effective as of November 21 st, 2017. The results of the re -scoped PEA are based

on 100% ownership of the Project by Black Iron.

Qualified Persons

The contents of this press release have been reviewed and approved by Qualified Persons, as follows:

• Angelo Grandillo, P. Eng. of BBA Inc. QP for Study Supervisor.

• Jeffrey Cassoff, P.Eng. of BBA Inc. QP for In-Pit Resource estimate and mining engineering.

• Michael Kociumbas, P.Geo. and Rick Risto, P.Geo., Wat ts, Griffis and McOuat Limited, QPs for

mineral resources estimate and QA/QC and data verification;

These persons are Qualified Persons as defined by NI 43- 101, are independent of Black Iron, and have

authored the technical report in respect of the re-scoped PEA.

Cautionary Statement

The PEA is preliminary in nature, and it includes inferred mineral resources that are considered

too speculative geologically to have the economic considerations applied to them that would

enable them to be categorized as m ineral reserves. There is no certainty that the PEA will be

realized.

For more information, please contact:

Derek Wood Matt Simpson

Manager, Investor Relations Chief Executive Officer

Tel: +1 (403) 200-3569 Tel: +1 (416) 309-2138

[email protected]

Forward-Looking Information

This press release contains forward- looking information. Forward- looking information is based on what

management believes to be reasonable assumptions, opinions and estimates of the date such statements

are made based on information available to them at that time, including those factors discussed in the

section entitled ‘‘Risk Factors’’ in the Company’s annual information form for the year ended December

31, 2016 or as may be identified in the Company’s public disclosure from time to time, as filed under the

Company’s profile on SEDAR at www.sedar.com. Forward- looking information may include, but is not

limited to, statements with respect to the P roject, the mineralization of the Project, the results of the PEA,

the realization of the PEA, the expectations of future cash flows, the expected economics forecast, the

geo-political climate in Ukraine, the Company’s ability to obtain the requisite land rights for the Project

and other requisite permits or approvals , and future plans for the Company’s development. Generally,

forward looking information can be identified by the use of forward- looking terminology such as "plans",

"expects" or "does not expect", "is expected", "budget", "scheduled", "estimates", "forecasts", "intends",

"anticipates" or "does not anticipate", or "believes", or variations of such words and phrases or state that

certain actions, events or results "may", "could", "would", "might" or "will be taken", "occur" or "be

achieved". Forward- looking information is subject to known and unknown risks, uncertainties and other

factors that may cause the actual results, level of activity, performance or achievements of the Company

to be materially different from t hose expressed or implied by such forward- looking information, including

but not limited to: general business, economic, competitive, geopolitical and social uncertainties; the

actual results of current exploration activities; other risks of the mining industry and the risks described in

the annual information form of the Company. Although the Company has attempted to identify important

factors that could cause actual results to differ materially from those contained in forward- looking

information, there may be other factors that cause results not to be as anticipated, estimated or intended.

There can be no assurance that such information will prove to be accurate, as actual results and future

events could differ materially from those anticipated in such statements. Accordingly, readers should not

place undue reliance on forward looking information. The Company does not undertake to update any

forward-looking information, except in accordance with applicable securities laws.