JANUARY 21, 2015                                                                                                                                         BHS2015‐04    

BAYHORSE SILVER CLARIFIES TECHNICAL DISCLOSURE ON BAYHORSE SILVER PROJECT, OREGON, USA, AND  ALEXANDER RIVER GOLD PROJECT, NEW ZEALAND 

Bayhorse  Silver  Inc.  (the  “Company”  or  "Bayhorse")  reports  that  as  a  result  of  a  review  by  the  British Columbia  Securities  Commission  ("BCSC")  it  is  issuing  the  following  news  release  to  clarify  its  technical disclosure.

With  respect  to  disclosure  of  an  historic  silver  resource  reported  at  the  Bayhorse  Silver  Mine  in  the Company's news releases of January 14, 2014, March 4, 2014, March 31, 2014, May 6, 2014, May 12, 2014 and  June  10,  2014,  and  on  the  Company's  website  http://www.bayhorsesilver.com,  the  disclosure  of  the historic resource did not meet the requirements of S. 2.4 and S. 3.4 of National Instrument NI‐43‐101, in that the disclosure did not include the grade of the historic resource. The Company hereby retracts the disclosure as made in its news releases, and on its website as incomplete and potentially misleading.

The Company hereby restates the disclosure of the historic resource to read: 

In  his  Examination  and  Compilation  Report  dated  April  1981,  Melvin  A.  Herdrick,  Consulting  Geologist, estimated probable  tonnages in the main orebody, based upon geology, to be as follows.

"Upper level, 329 ft long x 80 ft wide x 22 ft thick to be                                  50,688 tons Intermediate Level 200 ft long x 85 ft wide x 22 ft thick to be                      33,660 tons West projection to fault 525 ft x 85 ft wide x 22 ft thick to be                      88,360 tons Less 6,500 tons mined                                                                                           ‐ 6,500 tons Total probable ore at 7.5 oz/t cutoff  at 17‐20 oz Ag/t                                   166,208 tons"

In  his  conclusions  Herdrick  (1981)  stated  "  Because  mineralization  is  controlled  by  stratigraphy,  close proximity  to  the  fold  axis,  and  co‐incidence  of  the  Sunshine  Fault  near  mineralization,  continuity  of mineralization is projected to extend more than 600 ft westerly, beyond the previous exposures within the mine."

He further stated "Previous exposures verify that more than 400 ft of ore strike length is exposed from the upper  level  through  the  intermediate  level.      Projections  of  ore  tonnages  in  the  main  body,  based  upon geology, yield a probable tonnage of approximately 160,000 tons within the 7.5 oz cutoff, having an grade 

of approximately 17 to 20 oz Ag/ton"  

Herdrick's assumptions, parameters and methods used to calculate the  grade and tonnage of the reported historic resource are unknown.

Herdrick (1981) also estimated in the report that if on‐site milling was contemplated from the two levels and the west projection, he could quantify a larger possible tonnage using a 3.5 oz per ton  cutoff, but while determining a possible tonnage, did not ascribe a grade to the tonnage.

The Company advises that a qualified person has not done sufficient work to verify the historical estimates  nor  classify  the  historical  estimates  as  current  mineral  resources  or  mineral  reserves.  There  can  be  no  assurance  that  additional  work  will  result  in  the  definition  of  any  current  resource  or  reserve.    The  Company is not treating the historical estimates as current mineral resources or mineral reserves. 

For  the  historical  resource  figures  to  be  upgraded  or  verified  to  qualify  as  National  Instrument  43‐101 resources or reserves would require measuring and  resampling of the underground workings, and if needed, core drilling to confirm the potential tonnage  The Company has engaged APEX Geoscience (news release dated June 23, 2014) to conduct this work. 

The Company has retained Dr. G. E. Ray, P.Geol, to update the current Technical Report on the Bayhorse Mine that includes the reported historic resource.

Further, the Company reports that when the Company changed its name to Bayhorse Silver Inc and created the new website for the Company, it included an incorrect version of the Alexander River NI‐43‐101 Technical Report dated 23 April, 2013.  This incorrect version of the report contained a non‐compliant resource estimate that had previously been retracted by the Company in its news release February 19, 2013, the Company further retracts the disclosure as follows:

The Company is fully retracting all prior disclosure of a historic potential resource estimate at the Alexander River Gold Project on its website.

The  historic  potential  resource  estimate,  as  disclosed  in  these  news  releases,  and  in  the  Company’s promotional  videos,  was  insufficiently  compliant  with  National  Instrument  NI‐43‐101  rules  for  historical disclosure,  and  was  unsupported  by  a  compliant  NI‐43‐101  technical  report.  The  disclosure  omitted mandatory  cautionary  language  always  required  by  NI  43‐101  with  disclosure  of  a  historical  resource estimate. Some of the potential resource disclosure was potentially misleading, as it sometimes appeared as disclosure of a current resource estimate, and in a manner restricted by the disclosure requirements of NI‐ 43‐101. The Company hereby retracts all prior disclosure of a potential resource at Alexander River as made in its news releases and promotional video and written material.

The correct version of the Alexander River NI‐43‐101 Report is disclosed on the Company's website.

*************************************************************************************** This News Release has been prepared on behalf of the Bayhorse Silver Inc. Board of Directors, which accepts full responsibility for its contents. The contents of this news release has been reviewed and approved by Dr. G.E. Ray, P.Geol., and Dr. Stewart Jackson, P. Geol, qualified persons as recognized by National Instrument NI‐43‐101.

On Behalf of the Board

Graeme O'Neill, President

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies  of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.