BacTech Outiines Plans for 2020
BacTech Environmental Outlines Plans For 2020
Ecuador Arsenic/Gold Processing
February 20, 2020
Toronto, Canada: BacTech Environmental Corporation (“BacTech or the
Company”) (CSE:BAC; OTC:BCCEF) today announced its plans for the current year
with respect to the Company’s Ecuador project.
BacTech has identified the Ponce Enriquez area of southern Ecuador as an area
where the Company’s bioleaching technology can be successfully deployed for
environmental processing of locally produced concentrates. Given the high levels
of arsenic contained in the ore from the area, miners receive significantly reduced
prices for their concentrates due to penalties applied by the buyers. The buyers
tend to be from Asia where concentrates are shipped for conventional smelting
and/or roasting. The concentrates are subject to a 3% royalty on the gold value
payable to the government of Ecuador. BacTech believes that by implementing an
in-country bioleach plant it can offer superior pricing for these concentrates to
the local producers, provide domestic Ecuadorian employment opportunities;
and, increase local and federal tax revenue for the government. It should be
noted that the final arsenical product resulting from bioleaching, ferric arsenate,
is a US Environmental Protection Agency approved land-fillable form of arsenic.
Plans for 2020
The initial capacity for the proposed plant would be 40 tonnes per day of
arsenopyrite and refractory pyrite concentrates. At this stage the Company will be
pursuing its goals with 100% ownership but BacTech would consider a joint
venture partner going forward. An Ecuadorian partner-company would be our
preference. BacTech will act strictly as a purchaser and processor of third party
concentrates and will not own any mineral properties in Ecuador.
In the above chart we can see that the first step in the process involves ear-
marking suitable concentrates for which a detailed bioleach test program will be
undertaken. In previous visits to Ponce Enriquez the Company has already
identified 2 mines, each of which produce approximately 15 tons of concentrate
per day. The estimated time to complete the test work is 16-20 weeks after which
BacTech would establish the projected gold recovery and sulphide oxidation
ratios as well as gaining a good understanding of the flow sheet for the plant.
Previous test work carried out at Laurentian University on sample from Ponce
Enriquez showed very high oxidation levels for the sulphide minerals with over
99% of the arsenic stabilized as ferric arsenate.
During this period BacTech would begin the process of obtaining permits for the
plant. Applications will be made to the Ministries of Mining, Water and
Environment, for approval of a water usage license, and tailings approval for the
post bioleach residues. There will also be consultation with the local municipal
government with respect to land acquisition and approval for building permits for
the plant. It should be noted that Ponce Enriquez is a very active mining area with
over 90 producing mines of various sizes, and we do not expect to face local
opposition given the environmental and economic benefits associated with our
project.
If the results of the bioleach test work are in line with projections, BacTech will
begin a combination of a pre-feasibility followed by a bankable feasibility study. It
should be noted that these studies are for a commercial operating plant and do
not involve any aspects of underground resource estimation or mining
engineering. For this reason, the study should be relatively straight forward and
less costly than a full-blown bankable study.
Using the flow sheet developed during the bioleach test work, the final piece of
this phase of the project would be detailed engineering. It is our intent to rely
heavily on the designs from previous plants that BacTech has built which
addressed material with very similar mineralogical structure.
We estimate that the cost to get the project to a “shovel ready” state will be
approximately US$800,000. The actual budget for construction, procurement and
materiel is estimated to be $US7.5M with a 20% variance based on costs from
past projects. The detailed engineering will allow the company to reduce the
variance in the budget. The estimated time to complete the pre-construction
studies is approximately 12 months with the permitting being the longest part of
the process. At the end of this process BacTech will actively pursue contractual
concentrate feeds from local sources and quite possibly from neighbouring
countries such as Peru. Once the Company successfully completes the initial
plant, it is conceivable we will attract enough feed to exceed the plant’s capacity.
This could lead to a straight-forward expansion as BacTech’s plants are modular in
design.
With respect to the current financing, BacTech will use a portion of the proceeds
to obtain representative samples from 2 mines in Ponce Enriquez to begin the
bioleach test phase. Results will be published at the end of the study in
approximately 5-6 months. Representatives of the Company met with the
Ecuadorian Government last week to outline the permitting process.
About Arsenic
The effects of exposure to arsenic include increased risks of lung and bladder
cancer and skin changes in people ingesting arsenic in drinking water at
concentrations of 50 µg/litre, or even lower. Exposure to arsenic in the workplace
by inhalation can also cause lung cancer.
In addition, by using bioleaching instead of traditional smelting/roasting we avoid
the creation of sulphur dioxide emissions into the atmosphere created by burning
sulphide mineralization.
Company Overview
BacTech is investigating the use of its proprietary bioleach processing technology
to treat historic arsenopyrite concentrates and tailings produced in the Ponce
Enriquez area of Southern Ecuador.
BacTech has agreed to participate with a group looking to reprocess the Arsenic
Stockpile in Snow Lake, Manitoba as a technology part.
For further information contact: Ross Orr, President & CEO, BacTech Environmental
Corporation/ 416- 813-0303 ext. 222, Cell 416- 346-5529 and Email:
Robin Cook, Investor Relations: 416-809-1738, Email: [email protected]
Follow us on:
Facebook http://www.facebook.com/BacTechGreen
Twitter:http://twitter.com/BacTechGreen
LinkedIn http://www.linkedin.com/company/1613873
Vimeo http://vimeo.com/bactechgreen
YouTube http://www.youtube.com/user/bactechgreen
Special Note Regarding Forward-Looking Statements
This news release contains “forward-looking information”, which may include, but
is not limited to, statements with respect to future tailings sites, sampling or other
investigations of tailing sites, the Company’s ability to make use of infrastructure
around tailings sites or operating performa nce of the Company and its projects.
Often, but not always, forward -looking statements can be identified using words
such as “plans”, “expects”, “is expected”, “budget”, “scheduled”, “estimates”,
“forecasts”, “intends”, “anticipates”, or believes” or variations (including negative
variations) of such words and phrases, or state that certain actions, events or
results “may”, “could”, “would”, “might” or “will” be taken, occur or be achieved.
Forward-looking statements involve known and unknown risks, uncerta inties and
other factors which may cause the actual results, performance or achievements of
the Company to be materially different from any future results, performance or
achievements expressed or implied by the forward- looking statements. Forward-
looking statements contained herein are made as of the date of this news release
and the Company disclaims, other than as required by law, any obligation to update
any forward -looking statements whether because of new information, results,
future events, circumsta nces, or if management’s estimates or opinions should
change, or otherwise. There can be no assurance that forward-looking statements
will prove to be accurate, as actual results and future events could differ materially
from those anticipated in such statements. Accordingly, the reader is cautioned not
to place undue reliance on forward-looking statements.