Aya Gold & Silver Completes Front-End Engineering Design and Updates on Zgounder Expansion

Corporate Updates

PRESS RELEASE

Aya Gold & Silver Completes Front-End Engineering Design and Updates on

Zgounder Expansion

Montreal, Quebec, July 7 2022 - Aya Gold & Silver Inc. (TSX: AYA ; OTCQX: AYASF ) (“A ya” or the

“Corporation”) is pleased to report that it has completed the Front-End Engineering Design (“FEED”) with

Lycopodium, and to provide an update on the expansion of the Zgounder Silver Mine in the Kingdom of

Morocco.

“We are pleased to announce the timely completion of the FEED, which is an important first milestone in

Zgounder’s expansion, setting the pace for upcoming deliverables especially the procurement of long -

lead items and the finalization of the plant construction contract. Our updated, simplified flowsheet keeps

CAPEX and OPEX costs in line with the feasibility study and improve s operability,” said Benoit La Salle,

President & CEO. “As we prepare to break ground, our entire team remains focused on maintaining the

highest health and safety standard while advancing Zgounder on budget and on schedule.”

Zgounder Expansion Update Highlights

As of June 30, 2022, the following milestones have been achieved:

• Completion of the FEED, including flowsheet modifications. During the FEED phase, the following

was achieved:

o Completion of additional metallurgical test work at the SGS facilities in Lakefield, Canada,

and at other vendor testing facilities.

o Simplification of the process ing plant flowsheet (see exhibit 1 and Appendices), which

was a Feasibility Study (“FS”) recommendation. Based on the test work results obtained

during the FEED and a review of the process with Lycopodium Minerals Canada Ltd.

(“Lycopodium”), the Corporation decided to remove the flotation and CIP circuits and

process the whole ore flow in a leaching circuit, followed by Counter Current Decantation

(“CCD”) and a Merrill-Crowe circuit for the silver extraction.

o The new , whole-ore-leach process plant flowsheet will allow for better process water

management and recycling. F urthermore, the CCD circuit will offer greater operational

flexibility and leverage existing operating expertise.

o Revision and optimization of the p rocess design criteria, mass and water balances, and

the process flow diagrams.

o Initial draft of the piping and instrumentation diagram s, and issuance of a preliminary

process control philosophy document.

• Quotations for 21 mechanical equipment packages, including all key long -lead items, have been

received from a pre-approved list of vendors:

o All quotations received are firm price offers. More than 90% (in value) of the mechanical

equipment procurement offers for the new process plant have been received and re-

confirm the process plant CAPEX and OPEX estimated in the FS.

o A supplier for the ball mill package has been selected, and final terms and conditions are

being negotiated. A purchase order is expected shortly. When complete, it will be a key

milestone firming up the construction timeline of the project.

• Update and optimization of the 3D model of the plant developed during the FS:

o Inclusion of placeholders for additional process equipment that could potentially expand

the new process plant capacity from 2,000 tonnes per day (“tpd”) to 3,000 tpd with limited

adverse impact.

• Award of a contract for the earthworks for the new process plant and the new haulage road to a

major Moroccan contractor. Mobilisation to site is planned for the second half of July 2022.

• The Corporation is currently in discussions with two engineering and project delivery companies

regarding construction of the processing plant and expects to receive both offers before month-

end. The Corporation expects to select the contractor and award the contract in the coming

months.

• Groupement des Consultants et Ingénieurs du Maroc (“GCIM”), a local Moroccan civil engineering

firm, has been awarded the contract for the detailed design of the new Tailings Storage Facility

(“TSF”). Additionally, the Corporation has awarded the Engineer of Record (“EoR”) mandate to

EPOCH Resources Pty, a well-known South African civil engineering company. The companies

have begun to collaborate on the detailed design of the first phase of the new TSF.

• Following successful construction of the first 60,000 m³ water storage basin, the Corporation and

GCIM are working together to develop similar water storage facilities to ensure sufficient raw

water storage capacity prior to commissioning of the new process plant.

• Mine underground development on schedule and aligned with the FS:

o A total of 1,130 m of lateral underground mine development effected to date.

o Mobilisation of CMAC -Thyssen in July 2022 and start of vertical mine development in

August 2022.

• The Corporation’s internal construction team is complete.

• As of June 30, 2022, the Zgounder expansion is on budget and on schedule.

Exhibit 1 – 3D Model of New Zgounder Process Plant

Exhibit 2 – Zgounder Expansion Timeline

Video

An animated video of the Corporation’s FS including the updated flowsheet can be viewed here.

Qualified Person

The technical information contained in this news release has been reviewed and approved by Patrick

Perez, P.Eng, Director of Technical Services, a Qualified Person as defined under NI 43-101.

About Aya Gold & Silver Inc.

Aya Gold & Silver Inc. is a rapidly growing, Canada-based silver producer with operations in the Kingdom

of Morocco.

The only TSX-listed pure silver mining company, Aya operates the high-grade Zgounder Silver Mine and

is exploring its properties along the prospective South -Atlas Fault, several of which have hosted past -

producing mines and historical resources. Aya’s Moroccan mining assets are complemented by its Tijirit

Gold Project in Mauritania, which is being advanced to feasibility.

Aya’s management team has been focused on maximising shareholder value by anchoring sustainability

at the heart of its operations, governance, and financial growth plans.

For additional information, please visit Aya’s website at www.ayagoldsilver.com.

Or contact

Benoit La Salle, FCPA FCA

President & CEO

[email protected]

Alex Ball

VP, Corporate Development & IR

[email protected]

Forward-Looking Statements

This press release contains certain statements that constitute forward -looking information within the

meaning of applicable securities laws (“forward -looking statements”), which reflects management's

expectations regarding Aya’s future growth and business prospects (including the timing and

development of new deposits and the success of exploration activities) and other opportunities.

Wherever possible, words such as "improves”, “advance”, “allow”, “offer”, “confirm”, “expect”, “potentially”,

“ensure”, “expand”, “, “believe”, “intend”, “ability to” and similar expressions or statements that certain

actions, events or results “may”, “could”, “would”, “might”, “will”, or are “likely” to be taken, occur or be

achieved, have been used to identify such forward -looking information. Specific forward -looking

statements in this press release include, but are not limited to, statements and information with respect

to the exploration and development potential of Zgounder and the conversion of Inferred Mineral

Resources into Measured and Indicated Mineral Resources, future opportunities for enhancing

development at Zgounder, and timing for the release of the Company's disclosure in connection with the

foregoing, the capacity of the Company to continue to advance its expansion plan on time and on budget

and the capacity of the Company to finance its expansion plans. Although the forward -looking

information contained in this press release reflect management's current beliefs based upon information

currently available to mana gement and based upon what management believes to be reasonable

assumptions, Aya cannot be certain that actual results will be consistent with such forward -looking

information. Such forward-looking statements are based upon assumptions, opinions and analysis made

by management in light of its experience, current conditions, and its expectations of future developments

that management believe to be reasonable and relevant but that may prove to be incorrect. These

assumptions include, among other things, the closing and timing of equity or debt financing required for

the construction of the expansion project, the ability to obtain any requisite governmental approvals and

enter into necessary investment agreements to facilitate the investment with certain conces sions,

obtaining regulatory permits for on site work, importing goods and machinery and employment permits,

the accuracy of Mineral Reserve and Mineral Resource Estimates (including, but not limited to, ore

tonnage and ore grade estimates), the price of si lver, the price of gold, exchange rates, fuel and energy

costs, future economic conditions, anticipated future estimates of free cash flow, and courses of action.

Aya cautions you not to place undue reliance upon any such forward-looking statements.

The ri sks and uncertainties that may affect forward -looking statements include, among others: the

inherent risks involved in exploration and development of mineral properties, including government

approvals and permitting, changes in economic conditions, changes in the worldwide price of silver gold

and other key inputs, changes in mine plans (including, but not limited to, throughput and recoveries being

affected by metallurgical characteristics) and other factors, such as project execution delays, many of

which are beyond the control of Aya, as well as other risks and uncertainties which are more fully

described in Aya's 2021 Annual Information Form dated March 31, 2022, and in other filings of Aya with

securities and regulatory authorities which are available o n SEDAR at www.sedar.com. Aya does not

undertake any obligation to update forward -looking statements should assumptions related to these

plans, estimates, projections, beliefs, and opinions change. Nothing in this document should be

construed as either an offer to sell or a solicitation to buy or sell Aya securities. All references to Aya

include its subsidiaries unless the context requires otherwise.

Appendix 1 – 3D Image of Zgounder Expanded Processing Plant

Appendix 2 – Revised Flowsheet for Zgounder Expansion