Positive Preliminary Economic Assessment Completed for the Slivova Gold Project, Kosovo
1
TSX-V: AVU
US OTC: AVPMF
FRANKFURT: 8AM
410 – 325 Howe Street, Vancouver, BC Canada V6C 1Z7 T: (604) 687-3520 F: (888) 889-4874
September 6, 2023 NR 08 – 2023
Positive Preliminary Economic Assessment Completed
for the Slivova Gold Project, Kosovo
Avrupa Minerals Ltd. (AVU:TSXV) is pleased to announce that its partner at the
Slivova Gold Project in the Republic of Kosovo, Western Tethyan Resources (“WTR”),
has provided a positive, independent Preliminary Economic Assessment ( “PEA”) study
based on the NI 43- 101 Mineral Resources Estimate ( “MRE”) previously reported by
Avrupa on July 17, 2023 (see news release Slivova Mineral Resource Estimate ). Bara
Consulting completed the PEA in accordance with CIM standards, and Avrupa has
publicly disclosed the document under NI 43-101 reporting requirements.
The Slivova Project is located in the prolific Vardar Mineral Trend, about 30 km SE of
Pristina, the capital of Kosovo. WTR can earn- in to 75% of the Project by funding
exploration and development for Euro 1,800,000 over three years, and then a further
10% by making certain milestone and success payments, producing an Environmental
Impact Statement, delivering a Feasibility Study, and c ompleting a Mining License
application. WTR is 75%-owned by AIM-listed Ariana Resources.
Highlights from the PEA include:
• Slivova provides a conceptual pre- tax Net Present Value (NPV 8%) of US$27
million, and an internal rate of return (“IRR”) of 29% at a gold price of
US$1,835/oz.
• Capital expenditure is estimated at $33.4 million and sustaining capital
requirements of $9.4 million are envisaged in the study.
• Average production of 13,000 ounces of gold per annum projected over a seven-
year mine life from a combined open- pit and underground mining operation is
estimated from the study.
• Gold recovery by the Carbon- in-Leach (“CIL”) method, with recovery of gold at
92-94.5% Au (based on current testwork) and a processing rate of 142,000 tpa is
estimated from the study.
The full PEA document , which includes the NI 43- 101 Mineral Resource Estimate, may
be accessed on SEDAR+ or via the Avrupa Minerals website: Slivova PEA
The independent Qualified Person for Mineral Resources as defined by NI 43-101 is Mr.
Richard Siddle, MAIG, of Addison Mining Services Ltd. Mr. Siddle has reviewed and
approved the scientific and technical content of this news release. The Qualified
2
Person completed a site visit to the project on 13 June 2023, and has inspected the
property, drillhole locations and has reviewed selected intervals of the drill core used in
the Mineral Resource Estimate. No concerns were identified during the visit.
The independent Qualified Person for the disclosure of the Preliminary Economic
Assessment, as defined by NI 43-101, is Dr. Andrew Bamber, BSc, MASc, PhD, P.Eng.
of Bara Consulting Limited. Dr. Bamber has reviewed and approved the scientific and
technical content of this news release, in the form and context in which it appears. Dr.
Bamber completed a site visit to the project on 15 February 2023 and inspected the
property, core samples, and visited locations relevant to the project including the
gossan outcrop and potential access road, process plant, and tailings sites within the
license area.
Paul W. Kuhn, President and CEO of Avrupa Minerals, commented, “We are delighted
about the progress made at the Slivova Gold P roject by Western Tethyan Resources
and associated company Ariana Resources. In the past two months the Mineral
Resource Estimate has been updated, and a positive Preliminary Economic
Assessment has been completed by our partners. We look forward to seei ng more
positive results from the upcoming Q4 2023/Q1 2024 work field work program, including
trenching and drilling, the Q4 2023 initiation of an Environmental Baseline Study, and
continued, strong and proactive ESG work in the project area.”
Mentor Demi, Managing Director of Western Tethyan Resources, added, “The PEA
prepared by Bara Consulting provides strong evidence that the Slivova Gold Project has
the potential to develop into a profitable gold mine of modest size, even if no additional
resources are identified. By showcasing a compelling economic viability, it also provides
the basis for commencing the next phase of detailed exploration and techno -economic
studies. In conjunction with the pre- established infill resources drill program, WTR is
commencing a trenching program to enhance exploration in the areas bordering the
primary resource zone, specifically targeting Dzemailj and Valijevishte. Throughout Q4,
the company intends to initiate the Environmental Base Line Study, the Social Impact
Assessment, and complete the planning for a drilling program, with the actual drilling
activities scheduled to commence in the first quarter (Q1) of 2024.”
Dr. Kerim Sener, Managing Director of Ariana Resources , added, “This is an excellent
positive outcome for the Slivova Gold Project, demonstrating its potential economics
and highlighting opportunities to enhance the project in the longer term. The broader
exploration potential of the Slivova project area, in particular the opportunity to define
further mi neralisation down- plunge of the existing orebody, bodes well for further
economic upside. We are now looking to complete further work to demonstrate this
upside, via a phased exploration programme, which will target the definition of additional
resources and further investigate various aspects of the proposed mine design and
processing route, among other technical matters.”
Following is a summary discussion of important points from the PEA (from Western
Tethyan Resources):
3
Introduction
The Slivova Gold -Silver Project (“the Project”) is located some 30 km southeast of
Pristina, the capital of Kosovo. The Project was acquired by AVU Kosova, a wholly
owned subsidiary of Avrupa Minerals (“Avrupa”), which was granted a seven- year
exploration licence for the Project in 2022. In May 2023, Western Tethyan Resources
Ltd (“Western Tethyan”, “WTR” or “the Company”) executed an earn- in agreement with
Avrupa, in which WTR can earn-in up to 85% of the project.
Bara Consulting Limited (“Bara”) was engaged by WTR to prepare a Preliminary
Economic Assessment (“PEA”) for Slivova. The study comprises the updated Mineral
Resource Estimate (announced separately on July 17, 2023) and mining and tailings
management assessments, which were used as inputs into a concept le vel techno-
economic evaluation prepared in accordance with CIM guidelines and disclosed in
accordance with NI 43-101 reporting requirements.
Project Location
The Slivova Project exploration license is located along the Vardar Mineral Trend,
approximately 30 km (30 minutes by car) southeast of Pristina, the capital city of
Kosovo. Access to the Project is via the Pristina- to-Gjilan, two-lane highway and then
an unsealed road beyond the village of Peshter.
There are four main exploration targets within the Slivova licence: Peshter, Dzemail,
Valjeviste, and Brus. The Peshter prospect is further subdivided into three portions: the
Main Gossan, Gossan Extension, and the Sandstone Gossan. The Peshter prospect is
the main subject of the PEA, for which there is material disclosure (Figure 1).
Figure 1: The Slivova deposit (Peshter Target), and its associated license boundary.
4
Project Geology
Within the Slivova license, two units are identified: the calcareous unit and the non -
calcareous greywacke unit. They are moderately - to steeply -dipping, northwest
striking, and beyond the minerali zed prospects, tend to be unaltered and weakly to
moderately oxidized.
Two types of intrusive dykes and sills were identified in the mapping and drilling:
hornblende-biotite porphyry dykes and stock, and a feldspar porphyry dyke. The dykes
represent less than 3% of the total rock volume within the Main Gossan, with the
hornblende-biotite porphyry representing 99.5% of the intrusive rocks. Within the
Gossan Extension, the hornblende-biotite porphyry is represented by a greater volume
of rock and may be a series of northeast-trending dykes, or a larger stock.
Economic mineralization in the Main Gossan and Gossan Extension is concentrated in
the calcareous pebble conglomerate and calcareous sandstones. Minerali zation at
Slivova is classified as a distal, intrusive -related, stratiform, massive to disseminated
gold-silver-lead-zinc deposit. The principal minerals of economic interest are gold with
minor amount s of galena, sphalerite, chalcopyrite, and silver. The gangue mineral
assemblage consists of ilvaite(?), trace magnetite, arsenopyrite, pyrrhotite, marcasite,
pyrite, quartz , and various carbonates. Trace elements include arsenic, bismuth,
chromium, manganese, nickel, and vanadium.
Mineral Resources
The Mineral Resource Estimate, as previously announced, has an effective date of 22
June 2023. The Mineral Resource Estimate for Slivova, completed on July 14, 2023, is
reported in Table 1 and is based on the block model shown in Figure 2. No estimates
of Mineral Reserves have been prepared. Mineral Resources are not Mineral Reserves
and do not have demonstrated economic viabil ity. The estimate of Mineral Resources
may be materially affected by environmental, permitting, legal, title, taxation, socio-
political, marketing, or other relevant issues. The Qualified Person is not aware of any
such issues at the time of writing.
5
Figure 2: Oblique view of the block model showing the estimated gold grades. WGS84 Z34N.
Category Tonnes Bulk Density AuEq
(g/t)
Au
(g/t)
Ag
(g/t)
Au
(oz)
Ag
(oz)
Total Mineral Resources (Gross to the Project)
Measured 835,000 2.9 4.3 4.2 15 113,000 402,000
Indicated 296,000 2.8 3.6 3.5 15 33,200 144,000
Meas + Ind 1,130,000 2.9 4.1 4.0 15 146,000 546,000
Inferred 250,000 2.8 3.7 3.7 13 30,000 100,000
Open Pit Resources Above 0.5g/t AuEq
Measured 110,000 2.9 3.2 3.2 14 11,200 48,300
Indicated 39,300 2.6 2.8 2.7 13 3,390 16,500
Meas + Ind 150,000 2.8 3.1 3.0 13 14,600 64,800
Inferred nil nil nil nil nil nil nil
Underground Resources Above 1.5g/t AuEq
Measured 725,000 2.9 4.4 4.4 15 102,000 354,000
Indicated 257,000 2.9 3.7 3.6 15 29,800 127,000
Meas + Ind 982,000 2.9 4.2 4.2 15 131,000 481,000
Inferred 250,000 2.8 3.7 3.7 13 30,000 100,000
Table 1: Estimated Mineral Resources for Slivova. Numbers are rounded to an appropriate number of
significant figures, and as such, discrepancies may exist between individual values, products, and totals.
Notes to the Mineral Resource Estimate (1-9):
1. The independent Qualified Person responsible for Mineral Resource disclosure, as defined by NI 43-101, is Mr. Richard
Siddle, MSc, MAIG, of Addison Mining Services Ltd. The effective date of the Mineral Resource Estimate is 22 June 2023.
6
2. Mineral Resources are not Mineral Reserves and do not have demonstrated economic viability. There is no certainty that
all or any part of the Mineral Resource will be converted to Mineral Reserves.
3. A gold equivalent (AuEq) grade was calculated for each block using the formula AuEq = (Ag g/t x 0.05) + Au g/t. It is the
opinion of the Qualified Person that all elements included in the Au Equivalent calculation have a reasonable prospect of
being recovered and sold, the calculation of the Au equivalent value considers the relative recovery and payability of each
element (recovery by cyanide leaching of 93.4% for gold and 50% for silver and 95% and 85% payability, respectively, as
informed by metallurgical test work completed to date) as well as the assumed commodity prices.
4. Reasonable prospects of eventual economic extraction are satisfied by the estimation of break-even cut-off grades for
each anticipated mining scenario (0.5g/t AuEq for open pit and 1.5g/t AuEq for underground mining). These cut-off grades
were used to report the Mineral Resource. The cut-off grades were estimated on the basis of the following assumptions: a
gold price of US$1850/oz (selected following consideration of (1, 2 and 3 year trailing average LMBA gold price and LMBA
2023 average forecast gold price, a silver price of US$20/oz, underground mining costs of US$43.7/t, processing costs
(including tailings disposal) of US$29.5/t and G&A costs of US$3/ROMt.
5. Estimates in the above table have been rounded to three significant figures for Measured and Indicated Resources and two
significant figures for Inferred Mineral Resources.
6. CIM Definition Standards for Mineral Resources have been followed.
7. The independent Qualified Person for Resources is not aware of any additional known environmental, permitting, legal,
title, taxation, socio-political, marketing, or other relevant issues that could materially affect the Mineral Resource
Estimate.
8. The Mineral Resource figures set out above are quoted gross with respect to the Project. WTR of which Ariana owns 75%,
has yet to establish a net attributable interest under the Earn-in and accordingly, no separate net attributable figures are
reported.
9. Western Tethyan Resources is the operator of Slivova.
Mine Design
A revised approach to the mining of Slivova involves a small starter pit to access the
outcropping mineralized gossan area, followed by underground extraction of the gold
resource below the open pit at an appropriate extraction rate to suit the size and grade
of the deposit. Mine design involved a more detailed analysis of the potential mining
method and a mineable stope optimi zation exercise to fully assess and define the
underground stoping extents.
A geotechnical review was undertaken to validate extraction methods. Ore zones and
host rocks are either non- calcareous or calcareous sequences of altered sedimentary
rocks with ore zone strengths varying between 45 MPa and 50 Mpa. Mine design was
adapted to be flexible to varying competencies of host rock, particularly in the contact
areas.
The starter pit has been designed to be mined from the top bench downwards with ore
being accessible and extracted immediately, i.e., there is no requirement or need for
any pre-stripping. It has been assumed that this small open pit can be mined by local
contractors who have quarries within the vicinity of the proposed mine at Slivova. The
revised starter pit design is also situated such that there is now no requirement for
stream re -alignment where the pit can be accessed for initial extraction via existing
tracks on the north side of the stream. Pit extents minimi ze the impact on the
surrounding countryside and local communities.
Due to the requirement for a 25 m crown pillar , the bottom bench was modified to a
base of 865 mRL. Bench access was linked into the existing tracks and roads on the
site. This allows for easy access to each bench for overburden and ore removal
7
without the need for any ramps. Ac cess to the bottom bench is directly in from
topography. Pit operations cease after Year 1.
Underground access is envisaged as a portal developed directly into the south valley
wall, supporting mining typically by sublevel open stoping, unless ore zone geometry
dictates a step down to cut -and-fill methods. Main sublevels are 20 m, with stoping
separated 25 m from the open pit bottom by a crown pillar which will be mined by
sublevel caving methods at the end of mine life.
Mining is suggested to be via small teams of approximately 16 people per shift, using
small diesel fleet appropriate for production at between 300 t/day and 400 t/day. Mined
material to be trammed directly from underground operations through the portal to the
primary crusher tip located at the plant site on the saddle of the southern ridge 500 m
to the east.
Recovery Methods
Results of extensive characterisation and testing of the Slivova ore by a range of
methods suggest that treatment would be via carbon- in-leach (“CIL”) methods,
delivering gold recovery of 92- 94.5% and silver recovery of 19.8- 22.5%. Some gold
may be extrac ted via gravity recovery methods. Nominal plant throughput will be
142,000 tpa, with primary, secondary , and tertiary crushing of the ore, followed by ball
milling to 106 µ m and leaching of the ore by CIL methods. Loaded carbon is stripped,
with electrowinning and final EAF smelting of the doré to bullion on site.
Environmental
The environmental and social work completed to date is in line with that required for the
PEA based on the revised mining plan. No environmental or social fatal flaws have
been identified, and Bara is not aware of any environmental or social issue that would
prevent the project from proceeding to the PFS phase, during which time various
potential environmental risks would need to be evaluated further.
Economic Analysis
The economic analysis presented here is preliminary in nature and is based in part on
Inferred Mineral Resources that are considered too speculative geologically to have the
economic considerations applied to them that would enable them to be categorised as
Mineral Reserves. There is therefore no certainty that the PEA presented here will be
realised.
PEA level economic analysis is based on the production schedule presented with
capital and operating cost estimates for the Slivova Project and other information as of
July 2023. The discounted cashflow analysis (“DCF”) is presented in United States
Dollars (US$) in real money terms, free of escalation or inflation. Revenue has been
determined through application of the recovered troy ounces produced by Slivova t o
the gold and silver prices as stated, less payability.
Depreciation has been calculated on the assumption that 100% of capital expenditure
may be deducted from profits in the year that they are incurred (Deductibility Rate). It is
assumed that all capital expenditure is eligible for deduction. A discount rate of 8% has
been used for the evaluation, and no tax treatment has been applied.
8
The conceptual DCF analysis shows the Project is economic with a pre- tax net present
value (“NPV”), at 8% discount rate , of US$27 million, and an internal rate of return
(“IRR”) of 29% with upfront capital requirements of $33.4 million, and sustaining capital
requirements of $9.4 million.
Western Tethyan Minerals (WTR) is a UK- registered, mineral exploration and
development company focused on South East Europe. The company has a strategic
alliance with Newmont Corporation and Ariana Resources and is currently focused on
exploration for major copper -gold deposits in the Lecce Magmatic Complex and Vardar
Belt. The company is assessing several other exploration project opportunities across
Eastern Europe, targeting copper-gold deposits across the porphyry -epithermal
transition.
Ariana Resources is an AIM-listed mineral exploration and development company with
an exceptional track-record of creating value for its shareholders through its interests in
active mining projects and investments in exploration companies. Its current interests
include gold production in Turkey and copper -gold exploration and development
projects in Cyprus and Kosovo.
Avrupa Minerals Ltd. is a growth -oriented junior exploration and development
company directed to discovery of mineral deposits, using a hybrid prospect generator
business model. The Company holds one 100% -owned license in Portugal , the
Alvalade VMS Project, presently optioned to Sandfire Mineira Portugal in an earn- in
joint venture agreement. The Company now holds one 100% -owned exploration
license covering the Slivova gold prospect in Kosovo, and is actively advancing four
prospects in central Finland through its in -process acquisition of Akkerman Finland Oy.
Avrupa focuses its project generation work in politically stable and prospective regions
of Europe, presently including Portugal, Finland, and Kosovo. The Company continues
to seek and develop other opportunities around Europe.
For additional information, contact Avrupa Minerals Ltd. at 1- 604-687-3520 or visit our
website at www.avrupaminerals.com.
On behalf of the Board,
“Paul W. Kuhn”
Paul W. Kuhn, President & Director
This news release was prepared by Company management, who take full responsibility for its content. Paul W.
Kuhn, President and CEO of Avrupa Minerals, a Licensed Professional Geologist and a Regis tered Member of the
Society of Mining Engineers, is a Qualified Person as defined by National Instrument 43- 101 of the Canadian
Securities Administrators. He has reviewed the technical disclosure in this release. Mr. Kuhn, the QP, has not only
reviewed, but prepared and supervised the preparation or approval of the scientific and technical content in the news
release.