Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

AUMN.TO ·

Golden Minerals Completes Updated Technical Reports for Two Properties

Technical Reports (NI 43-101)

Golden Minerals Completes Updated Technical Reports for Two Properties

GOLDEN, Colo.--(BUSINESS WIRE)--March 22, 2022--Golden Minerals Company (“Golden

Minerals”, “Golden” or the “Company”) (NYSE-A: AUMN and TSX: AUMN) announces that a

Technical Report (“TR”) has been completed for each of its Rodeo open pit gold-silver mine and

its Velardeña Properties, both located in Durango State, Mexico.

Each TR has been completed in accordance with Canadian National Instrument 43-101 -

Standards of Disclosure of Mineral Projects (“NI 43-101”). The Resources used for each report

were developed by the independent engineering firm of Tetra Tech and comply with the

requirements of NI 43-101. Preliminary results of each economic analysis are shown in pre-tax

U.S. Dollars. The Company also plans to file a technical report summary pursuant to Subpart

1300 of Regulation S-K for each of the Rodeo mine and the Velardeña Properties in connection

with its annual report on Form 10-K.

Rodeo

The Rodeo mine is currently in operation and the Rodeo TR assumes a life of mine (“LOM”)

starting point of November 1, 2021. The TR assumes prices of $1,800/ounce (“oz”) gold (“Au”)

and $25.00/oz silver (“Ag”). Mineral resources were calculated having an effective date of

October 31, 2021 with a cutoff grade of 1.6 grams per tonne (“g/t”) for processing and 1.0 g/t for

stockpiling.

Estimated Resources

Classification

Cutoff Au (g/t)

Tonnes

Grade

Au g/t

Au (oz)

Grade

Ag g/t

Ag (oz)

Low-Grade (Stockpile)

Measured 1.0 208,500 1.24 8,350 10.03 67,200

Indicated 1.0 56,400 1.18 2,140 5.18 9,400

Measured + Indicated 1.0 264,900 1.23 10,500 9.00 76,600

Inferred 1.0 1,500 1.20 58 4.09 198

High-Grade

Measured 1.6 310,700 3.11 31,100 13.10 131,000

Indicated 1.6 43,700 3.17 4,500 10.67 15,000

Measured + Indicated 1.6 354,400 3.12 35,600 12.80 146,000

Note: Columns may not total due to rounding

Capital and Operating Costs

Required capital costs for the Rodeo mine consist of an estimated $0.4 million for closure and

reclamation. No additional capital is required at the mine. No capital costs are estimated for Plant

2 for the life of the Project. Estimated operating costs are shown below.

Description LOM Cost

($000s)

Unit Cost

($/t-milled)

Mining $3,790 $10.79

Processing $18,278 $52.04

G&A $1,352 $3.85

Total $23,421 $66.68

Economic Analysis

The LOM (life of mine) consists of 24 months of operation and assumes 12 months to perform

closure and reclamation. The starting point for the LOM is November 1, 2021. The pre-tax net

present value (“NPV”) of the project is $22.9 million using a discount rate of 8%. Royalties are

calculated at 2% for La Cuesta and 0.5% for the Mexico precious metals royalty.

Description

Unit Cost

($/t-milled)

Total Value

($000s)

NSR1

$141.70 $49,767

Net Revenue $141.70 $49,767

Operating Costs

Mining $10.79 ($3,790)

Processing $52.04 ($18,278)

G&A $3.85 ($1,352)

Operating Costs $66.68 ($23,421)

Operating Margin $75.01 $26,346

Capital Costs

Mining - $0

Process Plant

$0

Infrastructure - $0

Closure - ($447)

Capital Costs - ($447)

La Cuesta Royalty - ($995)

Mexico Precious Metals Royalty - ($249)

Pre-Tax Cash Flow - $24,655

Pre-Tax NPV 8% - $22,928

1 Net smelter revenue

Sensitivity Analysis

Sensitivity analyses on metal price and operating costs were performed on the economic model

results. Due to the lack of capital cost requirements, no sensitivity analysis was conducted on

capital costs. Results of sensitivity analyses show that a reduction in gold price of $100/oz would

result in a 10% reduction in NPV, while an increase in operating costs of 10% would result in a

9% decrease in NPV.

Velardeña

The Velardeña Technical report (TR) assumes prices of $1,744/oz gold, $23.70/oz silver,

$0.97/pound (“lb”) lead (“Pb”) and $1.15/lb zinc (“Zn”). Mineral resources were calculated

having an effective date of February 28, 2022, as diluted to a minimum of 0.7 meters and are

reported at a $175 NSR cutoff. A federal precious metal royalty of 0.5% is assumed.

Estimated Resources

Classification Mineral

Type

NSR

Cutoff Tonnes Grade

Ag g/t

Grade

Au g/t

Grade

Pb%

Grade

Zn% Ag oz Au oz Pb lb Zn lb

Measured Oxide 175 128,800 268 5.69 1.74 1.53 1,108,000 23,500 4,936,000 4,333,400

Indicated Oxide 175 280,300 262 5.06 1.73 1.45 2,361,200 45,600 10,681,500 8,936,600

Measured +

Indicated Oxide 175 409,100 264 5.26 1.73 1.47 3,469,200 69,100 15,617,500 13,270,000

Inferred Oxide 175 351,400 417 4.95 2.55 1.45 4,714,600 56,000 19,729,500 11,248,200

Measured Sulfide 175 256,200 357 5.52 1.56 1.91 2,942,800 45,500 8,819,300 10,769,700

Indicated Sulfide 175 603,500 341 4.79 1.46 1.91 6,619,400 92,900 19,475,600 25,408,900

Measured +

Indicated Sulfide 175 859,700 346 5.01 1.49 1.91 9,562,200 138,400 28,294,900 36,178,600

Inferred Sulfide 175 1,357,700 348 4.76 1.52 1.97 15,179,000 207,800 45,534,200 58,952,900

Measured All 175 385,000 327 5.58 1.62 1.78 4,050,800 69,000 13,755,300 15,103,100

Indicated All 175 883,800 316 4.88 1.55 1.76 8,980,600 138,500 30,157,100 34,345,500

Measured +

Indicated All 175 1,268,800 319 5.09 1.57 1.77 13,031,400 207,500 43,912,400 49,448,600

Inferred All 175 1,709,200 362 4.8 1.73 1.86 19,893,600 263,800 65,263,700 70,201,100

Notes:

(1) Resources are reported as diluted Tonnes and grade to 0.7 metres fixed width

(2) Metal prices for NSR cutoff are: US$23.70/troy ounce Ag, US$1,744/troy ounce Au, US$0.97/lb Pb, and

US$1.15/lb Zn

(3) Columns may not total due to rounding

Economic Analysis

Economic model results are summarized below. The model includes Measured, Indicated, and

Inferred resources. Reclamation costs are assumed to be canceled by salvage value and are

therefore not included. The LOM is 11 years, with a pre-tax NPV of $119 million using a

discount rate of 8%.

Item Total

($000s)

Pb

Concentrate

Zn

Concentrate

Doré

Gross Payable $556,905 $311,680 $59,772 $185,453

TCs, RCs and penalties ($35,939) ($19,791) ($14,663) ($1,485)

Freight & Insurance ($14,512) ($5,885) ($5,195) ($3,432)

NSR $506,454 $286,004 $39,914 $180,536

Operating Costs

Mining Costs - Stoping ($131,261)

Mining Costs -

Development ($33,653)

Milling costs ($105,234)

Contingency and Other ($27,015)

Federal Mining Royalty ($2,532)

($299,695)

$/t-milled ($242.23)

Operating Margin $206,759

Capital Costs Full LOM Pre-

Production

LOM

Pre-Production

Development ($788) ($788) $0

Process Plant ($17,248) ($14,498) ($2,750)

Contingency and Other ($3,130) ($1,755) ($1,375)

Cash Flow $185,594

Pre-Tax NPV8% $118,933

IRR 114%

Payback (years) 1

Sensitivity Analysis

Results of the sensitivity analyses show the project is most sensitive to operating costs and gold

price. A 10% increase in operating costs results in a 16% reduction in project NPV. Due to the

sensitivity to operating costs, efforts to control or reduce the operating costs are material to the

economic success of the project.

Cautionary Note Regarding Inferred Resources

The discounted cash flows shown above are prepared in compliance with NI 43-101. There is no

certainty that the economic results described above will be realized. The Company proceeded to

production at the Rodeo project without completion of customary feasibility studies

demonstrating the economic viability of the Rodeo project, and may elect to do likewise at the

Velardeña Properties. A mine production decision that is made without a feasibility study carries

additional potential risks which include, but are not limited to, (i) increased uncertainty as to

projected initial and sustaining capital costs and operating costs, rates of production and average

grades, and (ii) the inclusion of Inferred Mineral Resources, as defined by NI 43-101 that are

considered too speculative geologically to have the economic considerations applied to them that

would enable them to be converted to a Mineral Reserve, as defined by NI 43-101. Mine design

and mining schedules, metallurgical flow sheets and process plant designs may require additional

detailed work and economic analysis and internal studies to ensure satisfactory operational

conditions and decisions regarding future targeted production.

No mineral reserves have been estimated for either the Rodeo mine or the Velardeña Properties.

Mineral resources that are not mineral reserves do not have demonstrated economic viability.

The economic model for each of the Rodeo project and the Velardeña Properties is preliminary

in nature and includes inferred mineral resources that are too speculative geologically to have

economic considerations applied to them that would enable the inferred mineral resources to be

classified as mineral reserves, and there is no certainty that the preliminary economic model for

the Rodeo project, the Velardeña Properties, or both, will be realized.

About Golden Minerals

Golden Minerals is a growing gold and silver producer based in Golden, Colorado. The

Company is primarily focused on producing gold and silver from its Rodeo Mine and advancing

its Velardeña Properties in Mexico and, through partner funded exploration, its El Quevar silver

property in Argentina, as well as acquiring and advancing selected mining properties in Mexico,

Nevada and Argentina.

Forward-Looking Statements

This press release contains forward-looking statements within the meaning of Section 27A of the

Securities Act of 1933, as amended and Section 21E of the Securities Exchange Act of 1934, as

amended, and applicable Canadian securities legislation, including statements regarding

estimated resources and projected economic analyses associated with the Rodeo mine and the

Velardeña Properties. These statements are subject to risks and uncertainties, including changes

in interpretations of geological, geostatistical, metallurgical, mining or processing information,

and interpretations of the information resulting from exploration, analysis or mining and

processing experience. Golden Minerals assumes no obligation to update this information.

Additional risks relating to Golden Minerals may be found in the periodic and current reports

filed with the SEC by Golden Minerals, including the Company’s Annual Report on Form 10-K

for the year ended December 31, 2020.

Qualified Person:

The following Qualified Persons from Tetra Tech will co‐author the technical report that will be

filed on SEDAR within 45 days of this news release: Dr. Guillermo Dante Ramírez Rodríguez,

Mr. Randolph P. Schneider, and Ms. Kira Lyn Johnson. Each of these Qualified Persons has

reviewed and approved the information presented in this news release that was derived from the

sections of the PEA study for which they were responsible. Each of the named Qualified Persons

is independent of Golden Minerals.

Contacts

For additional information please visit http://www.goldenminerals.com/ or contact:

Golden Minerals Company

Karen Winkler, Director of Investor Relations

(303) 839-5060