1911 Gold Enters into Agreement with Grid Metals for Lithium Spodumene Concentrate Production at True North Mill

Metallurgy & Processing

1911 Gold Enters into Agreement with Grid Metals for Lithium

Spodumene Concentrate Production at True North Mill

TORONTO, Ontario, July 18, 2023 – 1911 Gold Corporation ("1911 Gold" or the "Company") (TSX-V:

AUMB; OTC: AUMBF) is pleased to announce the signing of a letter agreement (the “ Agreement”) with

Grid Metals Corp. (“ Grid”) to lease the True North mill complex for future processing of spodumene

pegmatite (lithium ore) from Grid’s Donner Lake Lithium Project in southeastern Manitoba, Canada.

Highlights:

 Significant cash payments on signing and throughout the leasing arrangement. Execution of the

agreement includes an upfront cash payment of C$750,000, with an additional C$1,000,000 cash

payment due in 90 days upon completion of further technical due diligence. The lease arrangement

involves milestone payments, a net smelter royalty of 1%, and ongoing payments to cover operating

and depreciation costs during the term.

 Capital investment into the True North mill and tailings facilities. Grid intends to upgrade and

modify the current mill configuration to provide for the processing of spodumene-bearing ore in addition

to gold ores. They have engaged Primero Group Ltd. (“Primero”), one of the pre-eminent engineering

consulting firms in the lithium industry, to complete a scoping study over the first 90 days to assess the

viability of modifying the current mill configuration to handle spodumene-bearing ore.

 Toll milling agreement to process future 1911 Gold ore during the lease term. The Agreement

includes the terms for a toll milling agreement to facilitate the processing of 1911 Gold ores during the

lease period. With this agreement 1911 Gold will maintain flexibility to phase-in gold ores from the True

North mine and other potential ore sources on its 63,000-hectare property.

“We are pleased to be entering into this agreement with Grid Metals to utilize the existing infrastructure at

True North.” Shaun Heinrichs, President and CEO, stated, “Our focus will continue to be on growing the

existing True North resource, through exploration and acquisitions, as well as further advancing the Central

Manitoba project to assess its potential for future high-grade gold production. This agreement with Grid

provides us with a valuable partner in maintaining our assets — a partner that is focused on strategic metals

and is backed by experienced management and long-term investors. The investments made into our

infrastructure under this agreement will ultimately support our own return to production and we will work

with our new partners to scale the facilities as required.”

The Agreement contains the primary terms which, upon completion of the 90-day due diligence period, will

form the basis of a Definitive Lease Agreement between 1911 Gold (lessee) and Grid (lessor). Primero has

been engaged by Grid to complete a detailed engineering analysis of the existing 1,300 ton per day mill to

assess the extent of the upgrades and modifications that will be required to support the processing of

spodumene-bearing pegmatite ore. A preliminary assessment has already been completed by Primero in

order to support the signing of this Agreement and make the required advance payments noted below.

Summary of the Terms

The key terms of the Agreement are as follows:

 Initial lease term of 5 years and a 2 year notice period for cancellation of the lease following the initial

lease term. The lease can be extended by mutual agreement for an additional 5 years.

 During the term of the lease, Grid shall have the right to reconfigure the mill and process spodumene-

bearing (lithium) ore, and to discharge from the mill to the existing tailings facility.

 Toll milling agreement terms for the processing of 1911 Gold ores during the lease period, to be

incorporated into the Definitive Lease Agreement.

 Grid will make the following initial payments to 1911 Gold on signing of the Agreement:

– An upfront non-refundable payment of C$300,000; and

– An equity investment of C$450,000 within 90 days, subject to the applicable regulatory

approvals. If regulatory approval cannot be obtained, Grid shall make a corresponding cash

payment to 1911 Gold.

– Unless terminated within 90 days by Grid, an additional C$1,000,000 will be paid to 1911 Gold

comprised of a C$250,000 lease payment and a C$750,000 financial assistance payment.

Financial assistance payments are non-interest bearing but secured by the True North mill,

such security to be released upon termination of either the Agreement or, once completed, the

Definitive Lease Agreement.

 Grid will make the following payments to 1911 Gold on signing and during the term of a Definitive Lease

Agreement:

– Financial assistance payment of C$1,000,000 to 1911 Gold’s financial security obligations to

the Province of Manitoba (relating to the mine closure plan for the True North complex) for the

period ending December 31, 2023, with an additional C$1,000,000 due by the end of 2024 and

a final C$900,000 due by the end of 2025.

– C$1,000,000 upon commencement of commercial production by Grid at the mill, defined as the

processing of at least 200,000 tonnes of spodumene-bearing ore.

– Monthly payments for operating costs incurred in support of milling activities.

– A 1% net smelter return royalty in favour of 1911 Gold, subject to Grid receiving a right of first

refusal on any disposition by 1911 Gold.

– A depreciation fee payment of $7.50 per tonne of lithium ore processed through the True North

mill.

 If Grid elects to extend the lease agreement for an additional 5-year period, subject to 1911 Gold’s

option to terminate the agreement with 2 years’ notice, the following additional payments will be made:

– Up to C$10,000,000 for the full five-year lease extension towards any increased financial

security costs arising from increased closure costs, prorated in the event that 1911 Gold

exercises the option to terminate the lease.

– C$1,000,000 on each of the fifth and sixth anniversaries of the lease.

 The Agreement will automatically terminate upon written notice from Grid for a period of up to 90 days

from date of signing provided the initial payments have been completed. Thereafter Grid may terminate

the Agreement once it has made a cumulative total of C$2,500,000 in total payments.

 Following the 90-day due diligence period and additional required payments, 1911 Gold shall permit

Grid to register a floating charge security interest on the True North mill assets in an amount

representing Grid’s total financial assistance payments and capital expenditures.

Grid is pursuing a two stage permitting process at Donner Lake. An Advanced Exploration Permit (“AEP”)

application is expected to be submitted which will enable a bulk sample of up to 50,000 tonnes from Donner

Lake. The second permitting step is an application for an Environmental Act Licence (mining permit). The

True North complex will require an amendment to its existing permits in order to enable the processing of

spodumene pegmatite (lithium ore) as well as for any increase in existing tailings capacity that will be

required.

About 1911 Gold Corporation

1911 Gold is a junior explorer that holds a highly prospective, consolidated land package totalling more

than 63,000 hectares within and adjacent to the Archean Rice Lake greenstone belt in Manitoba, and also

owns the True North mine and mill complex at Bissett, Manitoba. 1911 Gold believes its land package is a

prime exploration opportunity, with potential to develop a mining district centred on the True North complex.

The Company also owns the Apex project near Snow Lake, Manitoba and the Tully and Denton-Keefer

projects near Timmins, Ontario, and intends to focus on both organic growth and accretive acquisition

opportunities in North America.

1911 Gold’s True North complex and exploration land package are located within the traditional territory of

the Hollow Water First Nation, signatory to Treaty No. 5 (1875-76). 1911 Gold looks forward to maintaining

open, co-operative and respectful communication with the Hollow Water First Nation, and all local

stakeholders, in order to build mutually beneficial working relationships.

ON BEHALF OF THE BOARD OF DIRECTORS

Shaun Heinrichs

President and CEO

(604) 674-1293

[email protected]

CAUTIONARY STATEMENT REGARDING FORWARD-LOOKING INFORMATION

This news release may contain forward-looking statements. Often, but not always, forward-looking

statements can be identified by the use of words such as "plans", "expects" or "does not expect", "is

expected", "budget", "scheduled", "estimates", "forecasts", "intends", "anticipates" or "does not anticipate",

or "believes", or describes a "goal", or variation of such words and phrases or state that certain actions,

events or results "may", "could", "would", "might" or "will" be taken, occur or be achieved.

All forward-looking statements reflect the Company's beliefs and assumptions based on information

available at the time the statements were made. Actual results or events may differ from those predicted in

these forward-looking statements. All of the Company's forward-looking statements are qualified by the

assumptions that are stated or inherent in such forward-looking statements, including the assumptions

listed below. Although the Company believes that these assumptions are reasonable, this list is not

exhaustive of factors that may affect any of the forward-looking statements.

Forward-looking statements involve known and unknown risks, future events, conditions, uncertainties and

other factors which may cause the actual results, performance or achievements to be materially different

from any future results, prediction, projection, forecast, performance or achievements expressed or implied

by the forward-looking statements. All statements that address expectations or projections about the future,

including, but not limited to, statements about exploration plans and the timing and results thereof, are

forward-looking statements. Although 1911 Gold has attempted to identify important factors that could

cause actual actions, events or results to differ materially from those described in forward-looking

statements, there may be other factors that cause actions, events or results not to be as anticipated,

estimated or intended. There can be no assurance that forward-looking statements will prove to be

accurate, as actual results and future events could differ materially from those anticipated in such

statements. Accordingly, readers should not place undue reliance on forward-looking statements.

All forward-looking statements contained in this news release are given as of the date hereof. The Company

disclaims any intention or obligation to update or revise any forward-looking statements whether as a result

of new information, future events or otherwise, except in accordance with applicable securities laws.

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies

of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

SOURCE: 1911 Gold Corporation