Production Results

Atico Produces 2.08 Million Pounds of Cu and 1,465 Ounces of Au in Second

Quarter 2026

VANCOUVER, British Columbia, Aug. 06, 2026 -- Atico Mining Corporation (the “Company” or “Atico”) (TSX.V: ATY | OTCIQ:

ATCMF) announces its operating results for the three months ended June 30, 2026 from its El Roble mine. Production for the

quarter totaled 2.08 million pounds of copper and 1,465 ounces of gold in concentrates.

“The El Roble mine performed as planned during this period and delivered incremental improvements compared to the first

quarter, particularly in copper grades and metal recovery. Gold grade as well as output were impacted as we temporarily mine

through a lower gold grade zone of the deposit,” said Fernando E. Ganoza, CEO. “In the second half of the year, we are

targeting an updated reserve report and anticipate further gains in production as we optimize new operational equipment,

gaining further access to higher-grade ore zones.”

Second Quarter Operational Highlights

• Production of 2.08 million pounds of copper contained in concentrates; a decrease of 4% over Q2 2025.

• Production of 1,465 ounces of gold contained in concentrates; a decrease of 38% over Q2 2025.

• Average processed tonnes per day of 786, a decrease of 5% over Q2 2025.

• Copper head grade of 1.91%, an increase of 10% over Q2 2025.

• Gold head grade of 1.25 grams per tonne; a decrease of 40% over Q2 2025.

• Copper and gold recovery of 92.3% and 68%; no significant change for copper and an increase of 18% for gold,

respectively, over Q2 2025.

Second Quarter Operational Details

Q2 2026

Total  

Q2 2025

Total  

% Change

Production (Contained in Concentrates)         

Copper (000s pounds) 2,081  2,155  -4%  

Gold (ounces) 1,465  2,385  -38%  

Mine         

Tonnes of ore mined 53,156  60,633  -12%  

Mill         

Tonnes processed 53,585  62,007  -14%  

Tonnes processed per day 786  830  -5%  

Copper grade (%) 1.91  1.74  10%  

Gold grade (g/t) 1.25  2.08  -40%  

Recoveries         

Copper (%) 92.3  91.2  1%  

Gold (%) 68.0  57.6  18%  

Concentrates         

Copper and Gold Concentrates (dmt) 5,332  5,592  -5%  

Payable copper produced (000s lbs) 1,951  2,032  -4%  

Note: Metal production figures are subject to adjustments based on final settlement. The reported results are preliminary in

nature and are awaiting independent lab verification.

Concentrate Inventory

The number of shipments the Company can export in any given quarter depends on several variables some of which the

Company does not control, hence there may be an inherent variability in tonnes shipped quarter to quarter.

  Q2 2026   

Amounts in dry metric tonnes   

Opening inventory 1,266  

Production 5,332  

Sales -4,989  

Adjustments (118)  

Closing inventory 1,491  

Number of shipments 1  

Note: Concentrate figures are subject to adjustments based on final surveys and final settlement of sales.

El Roble Mine

The El Roble mine is a high grade, underground copper and gold mine with nominal processing plant capacity of 1,000 tonnes

per day, located in the Department of Choco in Colombia. Its commercial product is a copper-gold concentrate.

Since obtaining control of the mine on November 22, 2013, Atico has upgraded the operation from a historical nominal

capacity of 400 tonnes per day.

El Roble’s reserves estimate, with an effective date of March 12, 2024, includes Proven and Probable mineral reserves of 828

thousand tonnes averaging 2.49% Cu, 2.20 g/t Au and a life of mine until Q1-2027. A full NI 43-101 technical report is available

on SEDAR+. For more information on the reserves estimate refer to SEDAR+ and on the Company’s website.

Mineralization is open at depth and along strike and the Company plans to further test the limits of the deposit. On the larger

land package, the Company has identified a prospective stratigraphic contact between volcanic rocks and black and grey

pelagic sediments and cherts that has been traced by Atico geologists for ten kilometers. This contact has been determined

to be an important control on VMS mineralization on which Atico has identified numerous target areas prospective for VMS

type mineralization occurrence, which is the focus of the current surface drill program at El Roble. 

Qualified Person

Mr. Thomas Kelly (SME Registered Member 1696580), advisor to the Company and a qualified person under National

Instrument 43-101 standards, is responsible for ensuring that the technical information contained in this news release is an

accurate summary of the original reports and data provided to or developed by Atico.

About Atico Mining Corporation

Atico is a growth-oriented Company, focused on exploring, developing and mining copper and gold projects in Latin America.

The Company generates significant cash flow through the operation of the El Roble mine and is developing its high-grade La

Plata VMS project in Ecuador. The Company is also pursuing additional acquisition of advanced stage opportunities. For more

information, please visit www.aticomining.com .

ON BEHALF OF THE BOARD

Fernando E. Ganoza

CEO

Atico Mining Corporation

Trading symbols: TSX.V: ATY | OTCQX: ATCMF

Investor Relations

Igor Dutina

Tel: +1.604.633.9022

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX

Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

No securities regulatory authority has either approved or disapproved of the contents of this news release. The securities

being offered have not been, and will not be, registered under the United States Securities Act of 1933, as amended (the

‘‘U.S. Securities Act’’), or any state securities laws, and may not be offered or sold in the United States, or to, or for the

account or benefit of, a "U.S. person" (as defined in Regulation S of the U.S. Securities Act) unless pursuant to an exemption

therefrom. This press release is for information purposes only and does not constitute an offer to sell or a solicitation of an

offer to buy any securities of the Company in any jurisdiction.

Cautionary Note Regarding Forward Looking Statements

This announcement includes certain “forward-looking statements” within the meaning of Canadian securities legislation. All

statements, other than statements of historical fact, included herein, without limitation the use of net proceeds, are forward-

looking statements. Forward- looking statements involve various risks and uncertainties and are based on certain factors and

assumptions. There can be no assurance that such statements will prove to be accurate, and actual results and future events

could differ materially from those anticipated in such statements. Important factors that could cause actual results to differ

materially from the Company’s expectations include uncertainties relating to interpretation of drill results and the geology,

continuity and grade of mineral deposits; uncertainty of estimates of capital and operating costs; the need to obtain additional

financing to maintain its interest in and/or explore and develop the Company’s mineral projects; uncertainty of meeting

anticipated program milestones for the Company’s mineral projects; and other risks and uncertainties disclosed under the

heading “Risk Factors” in the Company’s Annual Information Form (“AIF”) dated September 4, 2024, filed with the Canadian

securities regulatory authorities on the SEDAR+ website at www.sedarplus.com and as available on the Company's website for

further details.