Asante Accelerates Bibiani RAMP-up

Mine Development & Operations

ASANTE ACCELERATES BIBIANI RAMP-UP

Vancouver, British Columbia, January 30, 2025 – Asante Gold Corporation ( CSE:ASE | GSE:ASG |

FRANKFURT:1A9 | U.S.OTC:ASGOF) (“Asante” or the “Company”) is pleased to report a significant

ramp-up in activity to accelerate growth initiatives at Bibiani, supported by the immediate deployment of

proceeds from the initial US$100 million gold forward sale.

Highlights

• Acceleration of stripping activities at the Main pit and the Russel pit, with 300% increase in monthly

material movement expected by June 2025 compared to recent levels

• Sulphide treatment plant commissioning expected to be complete in May 2025

• Bibiani monthly gold production expected to increase to 9,000 ounces by February 2025 and to 23,000

ounces by September 2025.

Dave Anthony, President and CEO stated,

“We are pleased to report a rapid increase in operational activities at the Bibiani mine, funded by the $100

million gold forward agreement with our key strategic partner Fujairah. This will more than double monthly

gold production by February 2025, with additional catalysts for growth expected to follow over the course

of the year supported by the Company’s financing plans that continue to advance.”

Russel Pit Rapidly Expands Beyond “Starter Pit” Size

Operational activities at the Bibiani Mine are accelerating, driven by ongoing expansion of the Russel pit

and a rapid increase in equipment availability from the primary mining contractor. The Russel pit continues

to outperform our expectations, with gold production up by more than 700% during the last quarter of 2024,

to upwards of 7,000 ounces per month. As a result, an aggressive drilling program has been initiated to

confirm the southward extension into Cutback #3 during the second half of 2025. This will support

advancement of waste stripping at the Main pit during the first half of 2025.

2

Main Pit Stripping Activity Accelerates

At the Main pit, mining is ahead of schedule by approximately 200% since start ing the build-up program

in November 2024. The mining contractor is increasing its fleet to meet an agreed schedule of the

production build- up. Main pit Cut back # 2 also starts during Q1 2025 to ensure consistent supply of

mineralized material. The Underground Mine project preparation is targeted to start during the last quarter

of 2025.

3

As shown in the below table, the Company expects the primary mine contractor fleet to double by June

2025 in terms of trucks and excavators at work.

The planned ramp-up activities and completion of commissioning the sulphide treatment plant in May 2025

will support a sharp increase in monthly gold production to 9,000 ounces by February 2025, 12,000 ounces

by June 2025 and 23,000 ounces by September 2025.

4

Qualified Person Statement

The scientific and technical information contained in this news release has been reviewed and approved by

David Anthony, P.Eng., Mining and Mineral Processing, President and CEO of Asante, who is a "qualified

person" under NI 43-101.

About Asante Gold Corporation

Asante is a gold exploration, development and operating company with a high-quality portfolio of projects

and mines in Ghana. Asante is currently operating the Bibiani and Chirano Gold Mines and continues with

detailed technical studies at its Kubi Gold Pr oject. All mines and exploration projects are located on the

prolific Bibiani and Ashanti Gold Belts. Asante has an experienced and skilled team of mine finders,

builders and operators, with extensive experience in Ghana. The Company is listed on the Canadian

Securities Exchange, the Ghana Stock Exchange and the Frankfurt Stock Exchange. Asante is also

exploring its Keyhole, Fahiakoba and Betenase projects for new discoveries, all adjoining or along strike

of major gold mines near the centre of Ghana’s Golden Triangle. Additional information is available on the

Company’s website at www.asantegold.com.

About the Bibiani Gold Mine

Bibiani is an operating open pit gold mine situated in the Western North Region of Ghana, with previous

gold production of more than 4.5 million ounces. It is fully permitted with available mining and processing

infrastructure on-site consisting of a newly refurbished 3 million tonne per annum process plant and existing

mining infrastructure. Asante commenced mining at Bibiani in late February 2022 with the first gold pour

announced on July 7, 2022. Commercial production was announced November 10, 2022.

For additional information relating to the mineral resource and mineral reserve estimates for the Bibiani

Gold Mine, please refer to the 2024 Bibiani Technical Report filed on the Company’s SEDAR profile

(www.sedarplus.ca) on April 30, 2024 and the Company’s press release dated January 14, 2025.

About the Chirano Gold Mine

Chirano is an operating open pit and underground mine located in the Western Region of Ghana,

immediately south of the Company’s Bibiani Gold Mine. Chirano was first explored and developed in

1996 and began production in October 2005. The mine comprises the Akwaaba, Suraw, Akoti South, Akoti

North, Akoti Extended, Paboase, Tano, Obra South, Obra, Sariehu and Mamnao open pits and the Akwaaba

and Paboase underground mines.

For additional information relating to the mineral resource and mineral reserve estimates for the Chirano

Gold Mine, please refer to the 2024 Chirano Technical Report filed on the Company’s SEDAR profile

(www.sedarplus.ca) on April 30, 2024.

For further information please contact:

Dave Anthony, President & CEO

Frederick Attakumah, Executive Vice President and Country Director

[email protected]

+1 604 661 9400 or +233 303 972 147

5

Cautionary Statement on Forward-Looking Statements

Certain statements in this news release constitute forward-looking statements, including but not limited to,

statements relating to increases in monthly material movement at the Bibiani mine, timing of

commissioning of the sulphide treatment plant, potential increases in monthly gold production, timing of

underground mine project preparation, increases in primary mine contractor fleet , estimated mineral

resources, reserves, exploration results and potential and development programs. Forward- looking

statements involve risks, uncertainties and other factors that could cause actual results, performance,

prospects, and opportunities to differ materially from those expressed or implied by such forward-looking

statements. Factors that could cause actual results t o differ materially from these forward -looking

statements include, but are not limited to, variations in the nature, quality and quantity of any mineral

deposits that may be located, the Company’s inability to obtain any necessary permits, consents or

authorizations required for its planned activities, the Company’s inability to raise the necessary capital or

to be fully able to implement its business strategies, and the price of gold. The reader is referred to the

Company’s public disclosure record which i s available on SEDAR ( www.sedarplus.ca). Although the

Company believes that the assumptions and factors used in preparing the forward -looking statements are

reasonable, undue reliance should not be placed on these statements, which only apply as of the date of this

news release, and no assurance can be given that such events will occur in the disclosed time frames or at

all. Except as required by securities laws and the policies of the securities exchanges on which the Company

is listed, the Company disclaims any intention or obligation to upda te or revise any forward -looking

statement, whether as a result of new information, future events or otherwise.

LEI Number: 529900F9PV1G9S5YD446. Neither IIROC nor any stock exchange or other securities

regulatory authority accepts responsibility for the adequacy or accuracy of this release.