Artemis Gold Reports Q2 2023 Financial Results and Provides Construction Progress Update

Mine Development & Operations Financials

Artemis Gold Inc. | 595 Burrard St., Suite 3083, Vancouver, BC V7X 1L3

Phone: 604.558.1107 [email protected] www.artemisgoldinc.com

August 15, 2023 TSXV:ARTG

PRESS RELEASE

Artemis Gold Reports Q2 2023 Financial Results and Provides Construction Progress Update

Vancouver, British Columbia – Artemis Gold Inc. (TSX-V: ARTG) (“Artemis Gold” or the “ Company”)

reports financial results for the three and six months ended June 30, 2023 (“Q2 2023”) and provides an

update on construction progress at the Blackwater Mine in central British Columbia. The project remains

fully funded, on track for first gold pour in H2 2024 and there is no change to the initial capital expenditure

guidance at this time.

Q2 2023 Financial Results

Artemis Gold’s Q2 2023 financial results – including the consolidated interim financial statements and

Management’s Discussion and Analysis (“MD&A”) – have been filed and are available for review on

SEDAR+ (www.sedarplus.ca) and on the Company’s website (www.artemisgoldinc.com).

Construction Update

Overall construction at the Blackwater mine was 27% complete as of June 30, 2023. Project development

continues to advance on schedule, targeting first gold pour in H2 2024. Earthworks continued in priority

infrastructure areas, with approximately 400 hectares logged and cleared and 85% of access roads

needed for construction now operable.

Construction of a dditional accommodation dormitories is in progress, which will raise t he total camp

capacity from 420 to over 550 beds.

Construction of the tailings storage facility main wall is on track to commence as planned.

Total major works man -hours worked to June 30, 2023, stood in excess of 160,000 hours with a zero

LTIFR1 and an AIFR2 of 129.37.

Plant Site

Process plant construction progressed well on several work fronts including the mill building, ball mill,

carbon in leach (CIL) tanks, and the primary, secondary, and tertiary crusher s, as well as the reclaim

tunnel earthworks. The mill building struct ural steel has been delivered and assembly is expected to

commence in Q3 2023, with completion anticipated by the end of 2023.

Heavy Equipment

The construction fleet has been commissioned and is operational. Larger haul trucks are planned to

arrive in Q3 2023 to expand and support the existing fleet as earthworks ramp up over the summer.

Initial deliveries of the mining fleet, including the first 240-ton CAT 793 haul trucks, are also expected to

arrive in Q3 2023.

Engineering and Procurement

At the end of June 2023, the Sedgman EPC contract works passed 40% complete overall with

engineering and design over 85% complete. Procurement is over 90% complete, with fabrication and

Artemis Gold Inc. | 595 Burrard St., Suite 3083, Vancouver, BC V7X 1L3

Phone: 604.558.1107 [email protected] www.artemisgoldinc.com

shipping of critical items well advanced including key equipment such as the primary, secondary and

tertiary crushers, the ball mill heads and components, inter-tank screens and cyclone cluster. Electrical

machinery control centre fabrication is well advanced and on schedule.

Laboratory and oxygen plant tenders have been completed, and contracts ha ve been awarded for

production drilling and explosive supplies. The civil, mechanical and piping materials and equipment for

the water management pond, tailings storage facility as well as the diversion system infrastructure has

been ordered as planned.

Personnel

At the end of June 2023 there were approximately 350 staff and contractors on site at Blackwater Mine.

Of these, approximately 2 5% are female and over 30% identify as Indigenous. Over 5 0% of the

development team is from the local region and over 80% are B.C. residents.

Artemis Gold Chairman and CEO Steven Dean commented, “ We remain focused on a disciplined

approach to development of the Blackwater mine. We have formed strong partnerships with our local

communities and First Nations, and with Phase 1 fully funded and 27% complete, we remain on track to

pour first gold in H2 2024. Blackwater will be one of B.C.’s largest gold mines and a significant contributor

to the local, provincial, and federal economies.”

Subsequen t to June 30 , 2023

Artemis Gold took proactive measures during July 2023 to temporarily reduce the number of non -

essential staff and contractors as a result of an uncontrolled wildfire reaching the immediate vicinity of

the mine site. Following the wildfire, all mine site infrastructure remains intact, including the construction

camp, process plant area, construction fleet and contractors’ fleets, and damage to property was minimal

as previously reported. Site construction activities resumed in early August. Current staff and contractor

numbers are over 400 at Blackwater Mine, with all scheduled work fronts active.

There is no change to the targeted gold pour in H2 2024. The Company continues to assess the impact

of the wildfire on the Company’s estimates of initial capital. Any cost impact depends on various factors,

including contractual remedies and insurance recoveries available to the Company and its contractors.

At this time, the Company is not m aking any change to its initial capital expenditure guidance and the

project remains fully funded.

The initial capital to complete to first gold pour is estimated to range between C$730 million and C$750

million, of which the Company had incurred approximately C$186 million as at the end of June 2023. The

Company’s cash and cash equivalents at the end of June 2023 totalled approximately C$63 million. At

the same date, the Company had funding committed from its streamer in the amount of US$136 million

(approximately C$180 million ) undrawn as at June 30, 2023 , committed project loan facilities in the

amount of C$385 million (including up to C$25 million of capitalized interest), along with a C$40 million

standby cost overrun facility. The Company also has 26.3 million warrants outstanding which are

exercisable at C$1.08 per warrant before August 27, 2024 for anticipated proceeds of C$28 million.

Artemis Gold Inc. | 595 Burrard St., Suite 3083, Vancouver, BC V7X 1L3

Phone: 604.558.1107 [email protected] www.artemisgoldinc.com

Site photos

Water management pond – June 2023 Mobile equipment service area – June 2023

CIL tank foundations – June 2023 Ball mill foundation and pedestals – June 2023

Artemis Gold Inc. | 595 Burrard St., Suite 3083, Vancouver, BC V7X 1L3

Phone: 604.558.1107 [email protected] www.artemisgoldinc.com

Plant site area – June 2023

Secondary and tertiary crusher slabs with rebar work underway – June 2023

Artemis Gold Inc. | 595 Burrard St., Suite 3083, Vancouver, BC V7X 1L3

Phone: 604.558.1107 [email protected] www.artemisgoldinc.com

Mechanical equipment ready to ship – June 2023

Air systems Reclaim tunnel sections Trial assembly

Tank sections Pump skid assembly

About Artemis Gold

Artemis Gold is a well -financed, growth -oriented gold development company with a strong financial

capacity aimed at creating shareholder value through the identification, acquisition, and development of

gold properties in mining -friendly jurisdictions. The company’s current focus is construction of the

Blackwater Mine project in central British Columbia approximately 160km southwest of Prince George

and 450km northeast of Vancouver. The project is one of the largest capital investments in the Bulkley -

Nechako, Fraser-Fort George and Cariboo regions of B.C. in the last decade. The first pour of gold and

silver from Blackwater Mine is expected H2 2024 and the mine is expected to be in production for a

minimum of 22 years. Artemis Gold trades on the TSX-V under the symbol ARTG. For more information

visit www.artemisgoldinc.com.

Qualified Person

Jeremy Langford, FAUSIMM, a Qualified Person as defined by National Instrument 43-101, has

reviewed and approved the scientific and technical information in this press release.

Artemis Gold Inc. | 595 Burrard St., Suite 3083, Vancouver, BC V7X 1L3

Phone: 604.558.1107 [email protected] www.artemisgoldinc.com

On behalf of the Board of Directors

Steven Dean

Chairman and Chief Executive Officer

+1 604 558 1107

Investor Relations contact

Meg Brown

Vice President, Investor Relations

[email protected]

+1 (778) 899-0518

Media relations contact

[email protected]

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the

policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this

release.

Cautionary Note Regarding Forward-looking Information

This press release contains certain forward -looking statements and forward -looking information as defined under

applicable Canadian and U.S. securities laws. Statements contained in this press release that are not hist orical

facts are forward-looking statements that involve known and unknown risks and uncertainties. Any statements that

refer to expectations, projections or other characterizations of future events or circumstances contain forward -

looking statements. In c ertain cases, forward-looking statements and information can be identified using forward-

looking terminology such as “may”, “will”, “expect”, “intend”, “estimate”, “anticipate”, “believe”, “continue”, “plans”,

“potential” or similar terminology. Forward-looking statements and information are made as of the date of this press

release, and include, but are not limited to, statements regarding the potential of the Blackwater mine project; the

jobs to be created in connection with the project; the contribution of the project to the economy; opinions of the

Province of British Columbia regarding the project and the region; agreements and relationships with Indigenous

partners; the future of mining in British Columbia; the plans of the Company with respect to the project, including

construction, site preparation, clearing, consultation with indigenous groups, and other plans and expectations of

the Company with respect to the project.

These forward-looking statements represent management’s current beliefs, expectations, estimates and projections

regarding future events and operating performance, which are based on information currently available to

management, management’s historical experience, perception of trends and current business conditions, expected

future developments and other factors which management considers appropriate. Such forward-looking statements

involve numerous risks and uncertainties, and actual results may vary. Important risks and other factors that may

cause actual results to vary include, wi thout limitation: risks related to the ability of the Company to accomplish its

plans and objectives with respect to the development of the project within the expected timing or at all, the timing

and receipt of certain required approvals, changes in commodity prices, changes in interest and currency exchange

rates, risks inherent in exploration estimates and results, risks inherent in exploration and development activities,

changes in development or mining plans due to changes in logistical, technical or o ther factors, unanticipated

operational difficulties (including failure of plant, equipment or processes to operate in accordance with

specifications, cost escalation, unavailability of materials, equipment or third party contractors, delays in the receipt

of government approvals, industrial disturbances, job action, and unanticipated events related to heath, safety and

environmental matters), changes in governmental regulation of mining operations, political risk, social unrest,

changes in general economic conditions or conditions in the financial markets, and other risks related to the ability

of the Company to proceed with its plans for the project and other risks set out in the Company’s most recent MD&A,

which is available on the Company’s website at www.artemisgoldinc.com and on SEDAR at www.sedar.com.

Artemis Gold Inc. | 595 Burrard St., Suite 3083, Vancouver, BC V7X 1L3

Phone: 604.558.1107 [email protected] www.artemisgoldinc.com

In making the forward -looking statements in this press release, the Company has applied several material

assumptions, including without limitation, the assumptions that: (1) market fundamentals will result in sustained

mineral demand and prices; (2) any necessary approvals and consents in connection with the development of the

project will be obtained; (3) financing for the development, construction and continued operation of the project will

continue to be available on terms suitable to the Company; (4) sustained commodity prices will continue to make

the project economically viable; and (5) there will not be any unfavourable changes to the economic, political,

permitting and legal climate in which the Company operates. Although the Company has attempted to identify

important factors that could affect the Company and may cause actual actions, events, or results to differ materially

from those described in forward-looking statements, there may be other factors that cause the actual results or

performance by the Company to differ materially from those expressed in, or implied by, any forward -looking

statements. Accordingly, no assurances can be given that any of the events anticipated by the forward -looking

statements will transpire or occur, or if any of them do so, what impact they will have on the results of operations or

financial condition of the Company. Investors should therefore not place undue reliance on forward -looking

statements. The Company is under no obligatio n, and expressly disclaims any obligation, to update, alter or

otherwise revise any forward -looking statement, whether written or oral, that may be made from time to time,

whether because of new information, future events or otherwise, except as may be req uired under applicable

securities laws.

1 LTIFR or Lost Time Injury Frequency Rate refers to the number of lost time injuries occurring per million man-hours worked,

divided by total man-hours worked.

2 AIFR or All Injury Frequency Rate refers to the total number of recordable incidents occurring per million man-hours worked,

divided by total man-hours worked.