Artemis Gold Provides an Update on Site Activities at Blackwater Mine
Artemis Gold Inc. | 595 Burrard St., Suite 3083, Vancouver, BC V7X 1L3
Phone: 604.558.1107 [email protected] www.artemisgoldinc.com
May 17, 2023 TSXV: ARTG
PRESS RELEASE
Artemis Gold Provides an Update on Site Activities at Blackwater Mine
Vancouver, British Columbia –Artemis Gold Inc. (TSX-V: ARTG) (“Artemis Gold” or the “Company”) is
pleased to provide an update on activities at the Blackwater Mine site.
Overview
Site works continue to progress with over 280 hectares logged and cleared including priority infrastructure
areas such as topsoil areas , borrow source locations, the mine haul road network , and water
management structures. Where required, the existing road network has been upgraded to allow access
for heavy construction equipment to key infrastructure locations.
A laydown area has been completed to accommodate the construction fleet, maintenance facilities, and
construction offices and will serve as a key staging area for earthworks activities throughout the project
construction.
The construction camp has been completed, including the installation and commissioning of a
wastewater treatment plant, expanding the site capacity to 420 persons. Additional accommodation
dormitories are planned to be completed during Q2-2023, which will then raise the total camp capacity
to in excess of 500 people.
Construction Fleet
Key mobile construction equipment has been delivered to site, including excavators, backhoe loaders,
compactors, grader, telehandlers, and a fuel and lube truck. Further to the delivery of the owner fleet,
additional rental equipment has been mobilized to Blackwater Mine in alignment with the Company’s
construction plan. The earthworks fleet now contains approximately 35 individual pieces of equipment.
Plant Site
Sedgman site mobilization activities continue to progress with the establishment of facilities for
subcontractors well advanced.
Bulk earthworks at the plant site are nearing completion and handover of the first work fronts has
occurred. Detailed excavation for concrete civil works has commenced and the concrete batch plant
has been commissioned. First concrete pour in the ball mill foundation has been completed.
Reinforcing Steel (rebar) installation has commenced at the ball mill.
Engineering and Procurement
As of the end of April 2023, Sedgman had completed approximately 73% of the detailed engineering for
the processing plant.
Artemis Gold Inc. | 595 Burrard St., Suite 3083, Vancouver, BC V7X 1L3
Phone: 604.558.1107 [email protected] www.artemisgoldinc.com
Over 90% of the procurement packages have been awarded, including all critical path items. The
remaining procurement packages will be awarded in accordance with schedule requirements.
Manufacturing of the process buildings is well advanced and initial shipments have started to arrive at
the Blackwater Mine site. Other major equipment packages delivered to site to-date include the agitator
shafts for the carbon-in-leach (CIL) tanks, as well as reinforcing bar for civil works activity (see photos
enclosed).
Personnel
The recruitment activities for Blackwater Mine have focused on hiring heavy equipment operators and
key personnel for the bulk earthworks activities. Personnel numbers at the Blackwater Mine are
increasing and currently there are over 200 staff and contractors working on-site.
At the end of Q1-2023, approximately 30% of on-site personnel were women and 31% of on-site
personnel identified as Indigenous.
Quote from Steven Dean, Artemis Gold Chairman and CEO:
“Site activities at Blackwater Mine continue to plan. We are pleased with the progress of our team, and
the milestones achieved so far. We look forward to continued success at the site to prepare the mine
for first gold pour in the second half of 2024.”
Blackwater Mine site photos
Construction Camp - March 2023 Wastewater Treatment Plant - April 2023
Artemis Gold Inc. | 595 Burrard St., Suite 3083, Vancouver, BC V7X 1L3
Phone: 604.558.1107 [email protected] www.artemisgoldinc.com
Processing Plant Area at Blackwater Mine – May 2023
Concrete Batch Plant - April 2023 Construction Fleet at Blackwater Mine - April 2023
Artemis Gold Inc. | 595 Burrard St., Suite 3083, Vancouver, BC V7X 1L3
Phone: 604.558.1107 [email protected] www.artemisgoldinc.com
Ball Mill Foundation Blinding – May 2023
Ball Mill Foundation Formwork Installation- May 2023 Ball Mill Foundation with rebar - May 2023
Artemis Gold Inc. | 595 Burrard St., Suite 3083, Vancouver, BC V7X 1L3
Phone: 604.558.1107 [email protected] www.artemisgoldinc.com
Process Plant Building structural steel arrival- May 2023 CIL Agitators Shafts arrival – May 2023
About Artemis Gold Inc.
Artemis Gold Inc. is a well-financed, growth-oriented gold development company with a strong financial
capacity aimed at creating shareholder value through the identification, acquisition, and development of
gold properties in mining-friendly jurisdictions. The company’s current focus is construction of the
Blackwater Mine project in central British Columbia approximately 160km southwest of Prince George
and 450km northeast of Vancouver. The project is one of the largest capital investments in the Bulkley-
Nechako, Fraser-Fort George and Cariboo regions of B.C. in the last decade. The first pour of gold and
silver from Blackwater Mine is expected H2 2024 and the mine is expected to be in production for a
minimum of 22 years. Artemis trades on the TSX-V under the symbol “ARTG”. For more information
visit: artemisgoldinc.com
-30-
Qualified Person
Jeremy Langford, FAUSIMM, a Qualified Person as defined by National Instrument 43-101, has
reviewed, and approved the scientific and technical information in this news release.
ARTEMIS GOLD INC.
On behalf of the Board of Directors
“Steven Dean”
Chairman and Chief Executive Officer
+1 604 558 1107
For further information
Investor Relations contact
Gerrie van der Westhuizen
Chief Financial Officer and Corporate Secretary
+1 (604) 558-1107
Artemis Gold Inc. | 595 Burrard St., Suite 3083, Vancouver, BC V7X 1L3
Phone: 604.558.1107 [email protected] www.artemisgoldinc.com
Media relations contact
Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the
policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this
release.
Cautionary Note Regarding Forward-Looking Information
This news release contains certain “forward looking statements” and certain “forward-looking information”
as defined under applicable Canadian and U.S. securities laws. Forward- looking statements and
information can generally be identified by the use of forward -looking terminology such as “may”, “will”,
“expect”, “intend”, “estimate”, “anticipate”, “believe”, “continue”, “plans”, “potential” or similar terminology.
Forward-looking statements and information are not historical facts, are made as of the date of this news
release, and include, but are not limited to, statements regarding the potential of the Project; the jobs to
be created in connection with the Project; the contribution of the Project to the economy; opinions of the
Province of British Columbia regarding the Project and the region; agreements and relationships with
Indigenous partners; the future of mining in British Columbia; the plans of the Company with respect to
the Project, including construction, site preparation, clearing, consultation with indigenous groups ;; and
other plans and expectations of the Company with respect to the Project. These forward -looking
statements involve numerous risks and uncertainties and actual results may vary. Important factors that
may cause actual results to vary include without limitation, risks related to the ability of the Company to
accomplish its plans and objectives with respect to the development of the Project within the expected
timing or at all, the timing and receipt of certain required approvals, changes in commodity prices,
changes in interest and currency exchange rates, risks inherent in exploration and development activities,
changes in development or mining plans due to changes in logistical, technical or other factors,
unanticipated operational difficulties (including failure of plant, equipment or processes to operate in
accordance with specifications, cost escalation, unavailability of materials, equipment or third party
contractors, delays in the receipt of government approvals, industrial disturbances, job action, and
unanticipated events related to heath, safety and environmental matters), the COVID -19 pandemic,
political risk, social unrest, changes in general economic conditions or conditions in the financial markets,
and other risks related to the ability of the Company to proceed with its plans for the Project and other
risks set out in the Company’s most recent MD&A. In making the forward-looking statements in this news
release, the Company has applied several material assumptions, including without limitation, the
assumptions that: (1) market fundamentals will result in sustained mineral demand and prices; (2) the
receipt of any necessary approvals and consents in connection with the development of the Project; (3)
the availability of financing on suitable terms for the development, construction and continued operation
of the Project; (4) sustained commodity prices such that the Project remains economically viable; and (5)
that the COVID-19 pandemic and restrictions related thereto will not materially impact the Company or
prevent the Company from operating its business as planned. The actual results or performance by the
Company could differ materially from those expressed in, or implied by, any forward-looking statements.
Accordingly, no assurances can be given that any of the events anticipated by the forward- looking
statements will transpire or occur, or if any of them do so, what impact they will have on the results of
operations or financial condition of the Company. Except as required by law, the Company is under no
obligation, and expressly disclaim any obligation, to update, alter or otherwise revise any forward-looking
statement, whether written or oral, that may be made from time to time, whether as a result of new
information, future events or otherwise, except as may be required under applicable securities laws.