Artemis Gold Obtains BC Mines Act Permit for Blackwater Mine Major Construction Activities to Commence as Planned in Q1 2023

Mine Development & Operations Permits & Approvals

Artemis Gold Inc. | 595 Burrard St., Suite 3083, Vancouver, BC V7X 1L3

Phone: 604.558.1107 [email protected] www.artemisgoldinc.com

March 9, 2023 TSXV: ARTG

PRESS RELEASE

Artemis Gold Obtains BC Mines Act Permit for Blackwater Mine

Major Construction Activities to Commence as Planned in Q1 2023

Vancouver, British Colombia – March 9, 2023 – Artemis Gold Inc. (TSX -V: ARTG) (“Artemis Gold” or

the “Company”) is pleased to announce the approval of its BC Mines Act Permit for the Blackwater Mine

project in Central British Columbia (“Blackwater”, “Blackwater Mine” the “Project” or the “Mine”). The

approval of the BC Mines Act Permit is the final step required to allow Artemis Gold to commence major

works construction activities at Blackwater Mine in Q1 2023, with the expectation of an initial gold pour

in H2 2024.

“Congratulations to Artemis Gold, the Lhoosk’uz Dené Nation, Ulkatcho First Nation, and Carrier Sekani

First Nations, and communities in the area for their work together to advance this critically important

project through the mine permitting and review process to final approval and construction. The Blackwater

Gold project will put lots of people to work and create a wide range of opportunities and benefits for local

businesses, communities and First Nations while ensuring the highest standards of environmental

protection, mitigation and sustainability ,” said David Eby , Premier of British Columbia (or “B.C.”),

Canada.

“British Columbians will benefit from hundreds of new jobs from this new mine, with both its construction

and multiple decades of operation,” said Josie Osborne, Minister of Energy, Mines and Low Carbon

Innovation, for British Columbia, Canada. “Artemis Gold has designed a world-class mine that supports

the economic needs of the local region; brings First Nations in as partners in training, business

development and jobs opportunities; and helps to meet provincial climate targets with the use of

sustainable, clean electricity.”

Steven Dean, Artemis Gold Chairman and CEO commented, “We would like to thank the Government of

British Columbia, the Lhoosk’uz Dené Nation, Ulkatcho First Nation, and the Carrier Sekani First Nations

for their substantial efforts during the consultation and review process for the BC Mines Act Permit. The

approval of the BC Mines Act Permit is the culmination of a substantial amount of work completed by our

team in collaboration with our First Nation partners and the provincial government. The Blackwater Mine

has been designed to have one of the smallest carbon footprints for an open pit gold project in the world,

with a defined path forward to substantially reduce that footprint further and potentially achieve net zero

carbon emissions through the integration of a zero-exhaust-emission haul fleet by 2029. Blackwater also

represents a generational opportunity to create em ployment and economic activity for our First Nation

partners, each of their communities , and B.C.’s Nechako and Cariboo regions. This approval is further

evidence that Blackwater meets world class standards for responsible mineral exploration and

development in British Columbia.”

The Blackwater Mine is estimated to be the largest gold mine development project in the Cariboo region

of B.C. in more than a decade, supporting regional employment over multiple decades with the potential

to be extended through further exploration. Blackwater has also been designed to some of the highest

environmental standards and in accordance with pr oven best practices. The Company is committed to

being a responsible steward of the environment and to identifying opportunities to reduce its impact on

the ecosystems where it operates. Blackwater is to be connected to the BC Hydro grid, which is powered

Artemis Gold Inc. | 595 Burrard St., Suite 3083, Vancouver, BC V7X 1L3

Phone: 604.558.1107 [email protected] www.artemisgoldinc.com

by hydroelectricity providing it with a sustainable source of renewable energy. This provides the

foundation for Blackwater to be developed into one of the lowest greenhouse gas (“GHG”) emitting open

pit mining operations in the world. Artemis Gold has invested in a fully electrified process plant with all

diesel and propane components replaced with electric equipment, further reducing the carbon footprint

of the mine. A unique agreement with Caterpillar Inc. provides a potential path to replace the initial diesel

fueled haul fleet with a zero -exhaust-emission fleet by 2029, which would help support the Provincial

Government’s target to reduce GHG emissions by 40% by 2030.

As part of the permitting process, Artemis Gold collaborated with the federal and provincial governments,

Lhoosk'uz Dené Nation, Ulkatcho First Nation, Carrier Sekani First Nations, and Nazko First Nation on

the development of innovative and precedent -setting environmental management plans related to

caribou habitat offsetting, fish habitat offsetting, wetlands offsetting and conservation and enhancement

activities. The company has also received significant support and input from the District of Vanderhoof

and other local communities in the project area.

An economic impact study completed by KPMG on the Blackwater Project in November 2020 anticipates

the Project will create 457 direc t full-time jobs per year over the operating life of the mine and with 825

direct full-time jobs per year created during the construction/expansion phases of mine development.

Additionally, the mine is expected to contribute $13.2 billion to the provincial economy, over the life of the

mine, including $2.3 billion to provincial revenues.

The Province of British Columbia signed an Economic and Community Development Agreement with the

Lhoosk’uz Dené and Ulkatcho First Nations in 2020 to share mineral tax revenue. The Company has a

project participation agreement with Lhoosk’uz Dené Nation and Ulkatcho First Nation, and a cooperation

agreement with Nazko First Nation for the Blackwater Mine. Artemis Gold continues to develop

relationships with other First Nations partners, including the Carrier Sekani First Nations. The

development of the Blackwater Mine has the potential to provide long -term economic benefits, training

and health and wellness support, and advances reconciliation with Indigenous peoples in B.C.

Lhoosk’uz Dené Nation Council commented, “The Blackwater Mine represents a significant opportunity

for Lhoosk’uz Dené Nation and we are pleased that it has received its BC Mines Act Permit. The Mine is

located in our traditional territory, and we have been active participants at every stage of the project from

mineral exploration to the Environmental Assessment and the BC Mines Act Permit. We look forward to

ongoing engagement with Artemis Gold as the project progresses to major works construction.”

“Ulkatcho First Nation has been involved in the development of the Blackwater Gold Project in earnest

since 2015 throughout the environmental assessment process. Today we continue to work in

collaboration with Artemis Gold Inc., Lhoosk’uz Dené Nation, and both the federal and provincial

governments to achieve the best mitigation results for all Canadians. We are pleased to hea r the major

mines permit has been approved. A lot of hard work has been done by all parties involved,” said Chief

Lynda Price of the Ulkatcho First Nation.

In preparation for the start of construction, Artemis has:

• significantly advanced site preparation works on the process plant area footprint, along with

progressive upgrades to selected infrastructure

• practically completed expansion works associated with a 477-room construction camp, with only

minor service tie-ins outstanding, which are scheduled to be completed prior to the commencement

of major works

Artemis Gold Inc. | 595 Burrard St., Suite 3083, Vancouver, BC V7X 1L3

Phone: 604.558.1107 [email protected] www.artemisgoldinc.com

• ordered the initial construction equipment fleet from Finning; due to commence delivery next month

• selected preferred partners to provide on-site security services, on-site fuel supply/storage along

with explosives supply

• closed its bank financing agreements

Further updates will be provided.

-30-

ARTEMIS GOLD INC.

On behalf of the Board of Directors

“Steven Dean”

Chairman and Chief Executive Officer

+1 604 558 1107

For further information

Investor Relations contact

Gerrie van der Westhuizen

Chief Financial Officer and Corporate Secretary

+1 (604) 558-1107

Media relations contact

[email protected]

Neither the TSX Venture Exchange nor its Regulation Services P rovider (as that term is defined in the

policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this

release.

Cautionary Note Regarding Forward-Looking Information

This news release contains certain “forward looking statements” and certain “forward-looking information”

as defined under applicable Canadian and U.S. securities laws. Forward -looking statements and

information can generally be identified by the use of fo rward-looking terminology such as “may”, “will”,

“expect”, “intend”, “estimate”, “anticipate”, “believe”, “continue”, “plans”, “potential” or similar terminology.

Forward-looking statements and information are not historical facts, are made as of the date of this news

release, and include, but are not limited to, statements regarding the potential of the Project; the jobs to

be created in connection with the Project; the contribution of the Project to the economy; opinions of the

Province of British Columbi a regarding the Project and the region; agreements and relationships with

Indigenous partners; the future of mining in British Columbia; the plans of the Company with respect to

the Project, including construction, site preparation, clearing, consultation with indigenous groups ;; and

other plans and expectations of the Company with respect to the Project. These forward -looking

statements involve numerous risks and uncertainties and actual results may vary. Important factors that

may cause actual results to vary include without limitation, risks related to the ability of the Company to

accomplish its plans and objectives with respect to the development of the Project within the expected

timing or at all, the timing and receipt of certain required approval s, changes in commodity prices,

changes in interest and currency exchange rates, risks inherent in exploration and development activities,

changes in development or mining plans due to changes in logistical, technical or other factors,

unanticipated operational difficulties (including failure of plant, equipment or processes to operate in

Artemis Gold Inc. | 595 Burrard St., Suite 3083, Vancouver, BC V7X 1L3

Phone: 604.558.1107 [email protected] www.artemisgoldinc.com

accordance with specifications, cost escalation, unavailability of materials, equipment or third party

contractors, delays in the receipt of government approvals, industri al disturbances, job action, and

unanticipated events related to heath, safety and environmental matters), the COVID -19 pandemic,

political risk, social unrest, changes in general economic conditions or conditions in the financial markets,

and other risks related to the ability of the Company to proceed with its plans for the Project and other

risks set out in the Company’s most recent MD&A. In making the forward-looking statements in this news

release, the Company has applied several material assumptions, including without limitation, the

assumptions that: (1) market fundamentals will result in sustained mineral demand and prices; (2) the

receipt of any necessary approvals and consents in connection with the development of the Project; (3)

the availability of financing on suitable terms for the development, construction and continued operation

of the Project; (4) sustained commodity prices such that the Project remains economically viable; and (5)

that the COVID-19 pandemic and restrictions related thereto will not materially impact the Company or

prevent the Company from operating its business as planned. The actual results or performance by the

Company could differ materially from those expressed in, or implied by, any forward-looking statements.

Accordingly, no assurances can be given that any of the events anticipated by the forward -looking

statements will transpire or occur, or if any of them do so, what impact they will have on the results of

operations or financial condition of the Company. Except as r equired by law, the Company is under no

obligation, and expressly disclaim any obligation, to update, alter or otherwise revise any forward-looking

statement, whether written or oral, that may be made from time to time, whether as a result of new

information, future events or otherwise, except as may be required under applicable securities laws.