Artemis GOLD Executes Credit-Approved Commitment Letter FOR $385 Million Project Debt Financing to Develop Blackwater

Financings Debt & Credit Facilities

3083 Three Bentall Centre, 595 Burrard Street, Vancouver, BC, V7X 1L3

Telephone: 604.558.1107 Fax: 604.566.9050 [email protected]

www.artemisgoldinc.com

NEWS RELEASE

February 24, 2022 Trading Symbol: TSX-V: ARTG

ARTEMIS GOLD EXECUTES CREDIT-APPROVED COMMITMENT LETTER FOR $385 MILLION PROJECT

DEBT FINANCING TO DEVELOP BLACKWATER

• FACILITY PROVIDES AN ADDITIONAL $40 MILLION STANDBY COST OVERRUN FACILITY:

• BLACKWATER PROJECT UPDATE

All figures presented in Canadian Dollars, unless specified otherwise

Vancouver, British Columbia – Artemis Gold Inc. – February 24, 2022 (TSX-V: ARTG) ("Artemis" or the

"Company") is pleased to announce that it has executed a credit-approved commitment letter and term

sheet (“Commitment Letter”) from Macquarie Bank Limited (“Macquarie”) and National Bank of Canada

(“National Bank”) to jointly underwrite a $360 million Project Loan Facility (“ PLF”), to fund a significant

component of the estimated construction costs of the Company’s Blackwater Gold Project (“Blackwater”,

or the “Project”) in central British Columbia. The PLF also provides for up to $25 million in capitalized

interest and a $40 million standby cost overrun facility (“Standby COF”). The Standby COF is an addition

to the terms previously announced on April 9, 2021, and represents a further enhancement of these

financing facilities to de-risk development in the current economic environment.

The execution of the Commitment Letter represents a strong statement of support of the technical and

economic merits of Blackwater by Macquarie and National Bank , and achieves another important

milestone towards de-risking the development of Blackwater.

Currently Artemis remains confident in the $645 million initial capital cost estimate outlined in the 2021

Feasibility Study technical report entitled “Blackwater Gold Project NI 43 -101 Technical Report on

Updated Feasibility Study” dated September 10, 2021 (“FS”). Potential future inflationary pressures

remain a risk for development projects and accordingly the Standby COF provides another important risk

management tool at management’s disposal at a competitive cost of capital . The PLF remains subject to

customary conditions precedent, including but not limited to the finalization of definitive documentation.

Highlights of the PLF

Key Terms of the PLF include the following:

• Facility Amount - $360 million , plus up to $25 million for capitalized interest prior to Project

completion, plus a Standby COF in the amount of $40 million . The Company may cancel the

Standby COF once Project development reaches completion.

3083 Three Bentall Centre, 595 Burrard Street, Vancouver, BC, V7X 1L3

Telephone: 604.558.1107 Fax: 604.566.9050 [email protected]

www.artemisgoldinc.com

• Interest Rate –Canadian Dealer Offered Rate (“CDOR”), plus a margin of 4. 5% pre -project

completion, reducing to 4.0% post-completion. Any amounts drawn on the Standby COF will carry

the above pricing plus an additional 2%.

• Fees – Customary Upfront and standby fees for a facility of this nature.

• Repayment and Maturity – Principal and capitalized interest will be repayable in quarterly

installments over six years, with reduced repayments during the period when the Company

expects to undertake its expansion of the Project from phase 1 to phase 2. The PLF can be prepaid

at anytime without penalty.

• Liquidity – Minimum required proceeds of $10 million, Debt Service Reserve of principal and

interest owing in the upcoming quarter.

• Hedging - A hedging program is expected to be put in place following the execution of a definitive

credit agreement pending certain conditions being met. In order to limit the Company’s exposure

to lower gold price s early in the mine life including during pay -back and in support of overall

project economics, the extent of the hedge program may range from 185,000 gold ounces (at a

hedge price of C$2,632 per gold ounce1) to 250,000 gold ounces (at a hedge price of C$2,369 per

gold ounce1).

Closing of the PLF will be subject to completion of final due diligence, definitive documentation and other

typical conditions precedent for a financing of this nature. The Company is targeting the execution of a

definitive credit agreement during Q2 2022.

Steven Dean, Chairman and CEO commented, “The committed underwriting of the PLF by two renowned

global banks is another important step towards de-risking the development of Blackwater. This underlines

the robust economics and debt carrying capacity of the Project, further evidenced by the addition of the

standby cost overrun facility to the original PLF proposal.

We remain confident in the current initial capital cost estimate of $645 million in the Feasibility Study as

at September 2021 , but without the benefit of a crystal ball the risk of the impact of future inflationary

pressures on our capital estimates is not entirely within our control. The standby cost overrun facility gives

management another important risk management tool at a very competitive cost of capital during a period

of variable inflation and supply chain challenges.

The Company is looking forward to continuing to work with Macquarie and National Bank to finalize

conditions precedent to a definitive credit agreement in parallel with the execution of fixed price EPC

Contracts, and securing final major permits while continuing to target breaking ground on major

construction in the summer of 2022”.

Further updates regarding the development of the Project include:

1 The hedge prices assume gold prices ranging from US$1,800 per gold ounce to US$2,000 per gold ounce, translated to

Canadian dollar equivalent at a CAD/USD rate of 0.76.

3083 Three Bentall Centre, 595 Burrard Street, Vancouver, BC, V7X 1L3

Telephone: 604.558.1107 Fax: 604.566.9050 [email protected]

www.artemisgoldinc.com

• The early works program at Blackwater is expected to commence in Spring 2022 to prepare the

site in order to accommodate the start of major works construction activities.

• Expected award of fixed price engineering, procurement and construction (“ EPC”) contracts for

the process plant and power transmission lines in Spring 2022.

• Artemis continues to target receipt of the BC Mines Act permit in the summer of 2022 with major

construction activities commencing thereafter.

On behalf of the Board of Directors,

ARTEMIS GOLD INC.

On behalf of the Board of Directors

“Steven Dean”

Chairman and Chief Executive Officer

For further information: Chris Batalha, CFO, +1 (604) 558-1107.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the

policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Cautionary Note Regarding Forward-Looking Information

This news release contains certain "forward looking statements" and certain "forward -looking

information" as defined under applicable Canadian and U.S. securities laws (together, “ forward-looking

statements”). Forward -looking statements can generally be identi fied by the use of forward -looking

terminology such as "may", "will", "expect", "intend", "estimate", "anticipate", "believe", "continue",

"plans", "potential" or similar terminology. Forward -looking statements in this news release include, but

are not limited to, statements and information related to the plans of the Company regarding the Project

and other statements regarding future plans, expectations, guidance, projections, objectives, estimates

and forecasts, as well as statements as to management's expectations with respect to such matters.

Forward-looking statements and information are not historical facts and are made as of the date of this

news release. These forward -looking statements involve numerous risks and uncertainties and act ual

results may vary. Important factors that may cause actual results to vary include without limitation, risks

related to the ability of the Company to accomplish its plans and objectives with respect to the Project

within the expected timing or at all; the timing of the finalization of definitive documents related to the

PLF and the satisfaction of other conditions precedent; the timing and receipt of certain approvals, changes

in commodity and power prices, changes in interest and currency exchange rate s, risks inherent in

exploration estimates and results, timing and success, inaccurate geological and metallurgical

assumptions (including with respect to the size, grade and recoverability of mineral reserves and

resources), changes in development or mining plans due to changes in logistical, technical or other factors,

unanticipated operational difficulties (including failure of plant, equipment or processes to operate in

accordance with specifications, cost escalation, unavailability of materials, equipm ent and third party

contractors, delays in the receipt of government approvals, industrial disturbances or other job action, and

unanticipated events related to health, safety and environmental matters), political risk, social unrest, and

changes in genera l economic conditions or conditions in the financial markets. In making the forward -

looking statements in this news release, the Company has applied several material assumptions, including

3083 Three Bentall Centre, 595 Burrard Street, Vancouver, BC, V7X 1L3

Telephone: 604.558.1107 Fax: 604.566.9050 [email protected]

www.artemisgoldinc.com

without limitation, the assumptions that: (1) market fundamentals will result in sustained mineral demand

and prices; (2) the receipt of any necessary approvals and consents in connection with the development of

any properties; ( 3) the availability of financing on suitable terms for the development, construction and

continued operation of any mineral properties; and ( 4) sustained commodity prices such that any

properties put into operation remain economically viable. The actual results or performance by the

Company could differ materially from those expressed in, or implie d by, any forward -looking statements

relating to those matters. Accordingly, no assurances can be given that any of the events anticipated by

the forward-looking statements will transpire or occur, or if any of them do so, what impact they will have

on the results of operations or financial condition of the Company. Except as required by law, the Company

is under no obligation, and expressly disclaims any obligation, to update, alter or otherwise revise any

forward-looking statement, whether written or oral , that may be made from time to time, whether as a

result of new information, future events or otherwise, except as may be required under applicable

securities laws.