Ares Strategic Mining Contracts Provo Mining for Mine Preparation Activities and Mining

Mine Development & Operations

Ares Strategic Mining Contracts Provo Mining

for Mine Preparation Activities and Mining

• Ares and Provo will commence drilling at Ares’ permitted mine site to provide the data

for the mineworks design and installations.

• A ramp installation is being planned, with offshoot adits, to intersect several fluorspar

pipes.

• The mined product will provide feed for the lumps plant currently under construction at

Ares’ processing site.

• Provo Mining will provide mining services to extract fluorspar mineralization for the

Ares processing facility.

• The completion of the mineworks is planned to coincide with the completion of the

lump’s construction.

Vancouver, B.C., January 9th, 2024 — Ares Strategic Mining Inc. (“Ares” or the “Company”) (CSE:

ARS) (OTC:ARSMF) (FRA: N8I1), is pleased to announce the Company has entered into an

agreement with Provo Mining & Construction, Inc. (“Provo”) to prepare Ares’ permitted mine site

for producing fluorspar feed for its anticipated fluorspar production operation.

Provo is a Utah based mining contracting company, that utilizes innovative engineering for

project and construction management to deliver safe, well-executed mining projects. Provo

specializes in EPCM, feasibility assessments, design, build and the commissioning of mining

projects. Provo has begun planning work on the Ares mine site and is looking to start physical

work at the site imminently. Drilling work will commence to inform the mine installation works,

with an aim to retrieve fluorspar mineralization for processing as inexpensively and efficiently as

possible.

Ares is undertaking simultaneous activity across its mine site and processing facility to expedite

its Utah operation’s development. In addition to the mine preparation, the Company is currently

constructing its lumps plant at its 50-acre industrial site. The Company recently closed a State of

Utah backed financing (see Press Release dated December 22, 2023) and is in the process of

ordering a flotation plant capable of delivering the highest grade fluorspar products needed by

industry, enabling the Company to have multiple product lines.

James Walker, CEO and President of the Company, said, “All the components to launch our

operation are lining up. The project is now well financed, has professional and experienced teams

working on both the mine and the processing site, while we also scale up our manufacturing

capability with new and advanced equipment . We are looking forward to keeping our

shareholders updated with our progress during this very busy period of development for our

Company and project.”

In 2018 the U.S. government classified fluorspar as a Critical Mineral, “deemed critical to U.S.

national security and the economy.” Fluorspar remains the only non-metallic Critical Mineral,

which is 100% imported in the entire country. Fluorspar’s classification as a Critical Mineral in the

United States translates to a faster permitting period, enabling mining operations to initiate more

quickly than operations for conventional minerals.

Lost Sheep Fluorspar Project – Delta, Utah

• 100% owned – 5,982 acres – 353 Claims.

• Located in the Spor Mountain area, Juab County, Utah, approximately 214 km south-

west of Salt Lake City.

• Fully Permitted – including mining permits.

• NI 43-101 Technical Report identified extensive high-grade fluorspar with low levels

of impurities.

• Mining plan approved by BLM1

First approved by Rex Rowley – Area Manager, Bureau of Land Management – 24th August 1992.

1 Renewed by Mike Gates – Minerals Program Manager, Bureau of Land Management – 12th December 2016.

ON BEHALF OF THE BOARD OF DIRECTORS OF

ARES STRATEGIC MINING INC.

James Walker

Chief Executive Officer and President

For further information, please contact James Walker by email at [email protected]

DISCLOSURE AND FORWARD-LOOKING STATEMENTS:

Companies typically rely on comprehensive feasibility reports on mineral reserve estimates to reduce the

risks and uncertainties associated with a production decision. Historically, situations where the issuer

decides to put a mineral project into production without first establishing mineral reserves supported by a

technical report and completing a feasibility study have a higher risk of economic or technical failure,

though some industrial mineral ventures are relatively simple operations with low levels of investment and

risk, where the operating entity has determined that a formal prefeasibility or feasibility study in

conformance with NI 43-101 and 43-101 CP is not required for a production decision. Based on historical

engineering work, geological reports, historical production data and current engineering work completed

or in the process by Ares, the Company intends to move forward with the development of its Utah asset.

Certain information in this news release may contain forward-looking statements that involve substantial

known and unknown risks and uncertainties. Forward-looking statements are often identified by terms

such as “will”, “may”, “should”, “anticipate”, “expects” and similar expressions. All statements other than

statements of historical fact included in this news release are forward-looking statements that involve risks

and uncertainties. There can be no assurance that such statements will prove to be accurate and actual

results and future events could differ materially from those anticipated in such statements. Important

factors that could cause actual results to differ materially from the Company’s expectations include the

failure to satisfy the conditions of the relevant securities exchange(s) and other risks detailed from time to

time in the filings made by the Company with securities regulations. The reader is cautioned that

assumptions used in the preparation of any forward-looking information may prove to be incorrect. Events

or circumstances may cause actual results to differ materially from those predicted, as a result of numerous

known and unknown risks, uncertainties, and other factors, many of which are beyond the control of the

Company. The reader is cautioned not to place undue reliance on any forward-looking information. Such

information, although considered reasonable by management at the time of preparation, may prove to be

incorrect and actual results may differ materially from those anticipated. Forward-looking statements

contained in this news release are expressly qualified by this cautionary statement. The forward-looking

statements contained in this news release are made as of the date of this news release and the Company

disclaims any intention or obligation to update or revise such information, except as required by applicable

law.