Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

ARIC.V ·

Awalé Hits 24.9 g/t Gold over 2 Metres Within 5.1 g/t Gold over 10 Metres at Empire

Drill Results

Awalé Hits 24.9 g/t Gold over 2 Metres Within

5.1 g/t Gold over 10 Metres at Empire

Highlights:

Step-down drilling at Empire confirms broad, multi-zone gold mineralization to 280m vertical depth.

5.1 g/t gold over 10m from 224m, including 24.9 g/t gold over 2m (EMDD-11)

1.3 g/t gold over 11m from 198m, including 7.8 g/t gold over 1m (EMDD-11)

Near-surface resource drilling:

2.9 g/t gold over 10m from 116m (EMDD-07)

1.1 g/t gold over 19m from 23m (EMDD-03)

Mineralization open along strike and at depth across Empire's 20 km corridor, with drilling to date

covering only 5 km.

All resource drilling results now reported; initial MRE targeted for Q2 2026.

Toronto, Ontario--(Newsfile Corp. - April 21, 2026) -

Awalé Resources Limited (TSXV: ARIC)

(OTCQX: AWLRF) (FSE: 2F60)

("

Awalé

" or the "

Company

") is pleased to report drill results from the

Empire target at its Odienné Project ("

Odienné

" or the "

Project

") in Côte d'Ivoire. These results

complete the Company's 12-hole drill program at Empire with 9 of these 12 holes to be incorporated into

the initial Mineral Resource Estimate ("MRE"), targeted for release in Q2 2026.

Drill hole EMDD-11 follows-up on the previously released deep hole OEDD-127, which returned 5.2 g/t

Au over 15m from 215m downhole, including 7.5 g/t Au over 10m (

see news release dated May 12,

2025

), extending the high-grade zone down-plunge to 150m vertical depth. The Empire target will form

part of Awale's first MRE alongside BBM and Charger and is expected to contribute a potential near-

surface, open-pit component with upside expansion potential.

"This is an important result for Empire because it confirms growth beyond the current resource drilling

area. High-grade mineralization in the deepest hole drilled to date shows the system continues at depth

and potentially remains open along strike. With drilling now reported across Empire, Charger, and BBM,

we have significantly advanced the data that supports a first resource estimate for the Project in the

coming weeks. Drilling continues to test additional upside at the Charger and BBM targets, and Sienso

permit," stated Andrew Chubb, President and CEO of Awalé Resources.

Link to All Figures

Watch Video of CEO Andrew Chubb Discussing New Results from Empire

About Empire

Step-back hole EMDD-11 has not only intercepted down-plunge mineralization from previously reported

hole OEDD-127, returning a high-grade result of 2m at 24.9 g/t Au within a broader minreralized vein

and alteration zone of 10m at 5.1 g/t Au, but also intercepted hanging wall mineralization. This returned

11m at 1.3 g/t Au from 198m, including 1m at 7.8 g/t Au. This mineralization is significant and is

interpreted to represent a new zone (see cross section in Figure 4) and may be related to step south and

southeast en echelon mineralization previously reported at Empire as 'Empire Gap' (

see news release

dated September 1, 2021

).

Empire is Awalé's first discovery from the first drill program on the Odienné Project in 2019. It is a high-

grade gold discovery that sits within a 20 km WNW (west-northwest) trending structure corridor, and 2.5

km south of the Charger discovery. The Company has now demonstrated that the Odienné Project lies

within a large plumbing system where multiple discoveries have been made. Taken together, these

discoveries form the potential for a mining camp where multiple sites would feed a central processing

facility, Empire is a high-grade discovery that is part of this vision.

Ongoing Drilling and Results Pending

The Company continues to advance multiple drill programs across the Project, with results pending from:

Four exploration holes at Charger 2

Seven diamond drill holes and aircore drilling at Fremen target on the 100%-owned Sienso permit

Ongoing diamond drilling at BBM and Charger NE

Regional aircore drilling across the Odienné East and Odienné West permits

About Awalé Resources

Awalé is a diligent and systematic mineral exploration company focused on discovering large high-

grade gold and copper-gold deposits. Exploration activities are currently underway in the underexplored

regions of Côte d'Ivoire, where the Company is exploring the Odienné Copper-Gold Project ("

Odienné

"

or the "

Project

"), covering 2,346 km

2

across seven permits-five granted and two applications. This

includes 797 km

2

in two permits held under the Awalé-Newmont Joint Venture ("OJV"). Awalé currently

manages all exploration activities over the OJV, with funding currently provided by Newmont Ventures

Limited ("Newmont") under an Exploration Agreement signed in May 2022.

Awalé has discovered four gold, gold-copper, and gold-copper-silver-molybdenum mineralized systems

within the OJV and has recently commenced exploration on its 100%-owned properties.

The Odienné Project is underexplored and has multiple pipeline prospects with similar geochemical

signatures to Iron Oxide Copper Gold (

IOCG

) and intrusive-related mineral systems with substantial

upside potential. The Company benefits from a skilled and well-seasoned technical team that allows it to

continue exploring in a pro-mining jurisdiction that offers significant potential for district-scale

discoveries.

Table 1: Significant Intercepts from Diamond Drilling - (from this release)

Hole ID

From

(m)

To

(m)

Length

(m)

Au

(g/t)

Ag

(g/t)

Cu

(ppm)

Mo

(ppm)

Composite

Trigger

(Aug/t)

EMDD0001

34.0

35.0

1.0

0.8

0.2

145.5

1.3

0.5

EMDD0002

4.6

9.6

5.0

3.5

0.3

108.0

2.6

0.2

including

7.6

9.1

1.5

10.2

0.4

89.6

2.0

5

13.0

14.0

1.0

5.0

0.2

71.2

2.6

0.2

23.0

29.0

6.0

1.4

0.3

120.2

3.4

0.2

including

23.0

24.0

1.0

6.9

1.0

161.9

4.3

0.5

75.0

78.0

3.0

0.6

0.2

142.5

2.3

0.2

EMDD0003

0.0

4.6

4.6

0.6

0.1

157.8

1.9

0.2

0.6

1.6

1.0

2.2

0.1

134.3

2.4

0.5

9.1

13.5

4.4

4.0

0.3

154.6

1.9

0.5

including

9.1

10.6

1.5

7.4

0.3

187.5

2.5

5

23.0

42.0

19.0

1.1

0.2

98.8

5.0

0.5

including

38.0

39.0

1.0

7.8

0.4

27.9

3.2

5

46.0

48.0

2.0

1.0

0.2

76.2

4.3

0.5

52.0

58.0

6.0

0.8

0.2

61.3

3.1

0.5

EMDD0004

19.0

23.0

4.0

5.2

0.7

135.5

3.0

0.5

including

19.0

20.0

1.0

18.8

2.0

183.1

2.3

5

EMDD0005

0.0

29.0

29.0

0.7

0.1

82.9

2.5

0.2

including

13.6

23.0

9.4

1.5

0.2

74.2

2.3

0.5

and

22.0

22.5

0.5

9.8

0.5

66.0

5.4

5

45.0

46.0

1.0

0.5

0.1

66.1

6.2

0.5

77.0

82.0

5.0

0.6

0.2

161.7

5.4

0.5

89.0

90.0

1.0

0.8

0.1

77.1

6.1

0.5

EMDD0006

66.0

67.0

1.0

0.9

0.2

89.6

1.3

0.5

77.0

78.0

1.0

2.1

0.2

83.0

4.1

0.5

102.0

121.0

19.0

0.4

0.1

88.3

4.2

0.2

including

114.0

117.0

3.0

1.0

0.2

82.3

4.0

0.5

125.0

133.0

8.0

0.5

0.1

104.4

2.2

0.2

including

132.0

133.0

1.0

1.5

0.1

92.9

3.5

0.5

137.0

140.0

3.0

1.8

0.3

114.9

4.3

0.2

including

138.0

139.0

1.0

4.9

0.7

177.2

3.8

0.5

148.0

160.0

12.0

1.3

0.2

126.3

2.7

0.2

including

159.0

160.0

1.0

5.3

0.2

102.9

2.4

5

167.0

178.0

11.0

0.8

0.1

98.1

5.1

0.5

182.0

183.0

1.0

1.2

0.3

53.6

2.9

0.5

EMDD0007

77.0

78.0

1.0

0.8

0.2

256.2

1.7

0.5

EMDD0007

92.0

93.0

1.0

0.8

0.1

78.5

6.9

0.5

EMDD0007

116.0

126.0

10.0

2.9

0.3

87.5

2.5

0.2

including

116.0

119.0

3.0

8.9

0.6

71.2

4.7

0.5

including

116.0

117.0

1.0

23.9

1.5

55.7

5.0

5

EMDD0007

137.0

150.0

13.0

0.5

0.1

72.6

1.7

0.2

including

137.0

138.0

1.0

2.0

0.2

103.1

0.9

0.5

186.0

187.0

1.0

0.8

0.0

67.6

0.9

0.5

190.0

191.0

1.0

0.7

0.2

210.5

1.0

0.5

194.0

195.0

1.0

0.7

0.1

65.1

6.2

0.5

201.0

205.0

4.0

0.5

0.1

58.2

5.5

0.5

209.0

213.0

4.0

1.6

0.1

52.0

3.8

0.5

220.0

221.0

1.0

2.3

0.2

71.7

2.9

0.5

EMDD0008

1.6

3.5

1.9

0.7

0.2

194.4

4.9

0.5

24.0

28.0

4.0

0.8

0.1

84.0

6.7

0.5

56.0

57.0

1.0

0.6

0.1

119.5

16.5

0.5

60.0

61.0

1.0

0.5

0.1

116.6

3.1

0.5

62.0

63.0

1.0

0.5

0.1

71.5

2.0

0.5

85.0

88.0

3.0

0.9

0.1

87.0

0.9

0.5

97.0

105.0

8.0

0.8

0.1

79.9

1.3

0.2

115.0

140.0

25.0

0.5

0.2

91.4

6.9

0.2

including

125.0

127.0

2.0

3.8

0.7

117.6

1.9

0.5

including

125.0

126.0

1.0

7.1

1.2

123.1

0.6

5

131.0

132.0

1.0

1.7

0.3

67.2

3.1

0.5

137.0

139.0

2.0

0.6

0.1

139.7

37.7

0.5

153.0

158.0

5.0

0.4

0.1

46.7

4.1

0.2

including

153.0

154.0

1.0

1.6

0.1

54.3

8.3

0.5

174.0

175.0

1.0

0.8

0.1

126.3

5.7

0.5

EMDD0010

3.5

5.0

1.5

1.5

0.3

116.3

4.4

0.5

66.0

66.5

0.5

1.0

1.2

92.0

3.5

0.5

88.0

100.0

12.0

0.6

0.1

132.5

8.1

0.2

including

90.0

95.0

5.0

0.9

0.2

173.1

11.4

0.5

and

99.0

100.0

1.0

2.1

0.1

126.7

1.8

0.5

137.0

158.0

21.0

0.5

0.1

71.9

2.6

0.2

including

137.0

138.0

1.0

1.4

0.1

62.7

4.6

0.5

and

143.0

145.0

2.0

1.2

0.1

90.1

1.6

0.5

and

151.0

158.0

7.0

0.8

0.1

68.9

2.7

0.5

184.0

195.0

11.0

0.5

0.1

73.2

2.7

0.2

184.0

188.0

4.0

1.0

0.1

66.7

2.7

0.5

207.0

209.0

2.0

1.3

0.2

107.5

11.8

0.5

229.0

236.0

7.0

1.0

0.3

104.9

3.4

0.5

EMDD0011

138.0

141.0

3.0

1.0

0.3

178.9

2.2

0.5

174.0

175.0

1.0

0.9

0.2

103.5

9.3

0.5

198.0

209.0

11.0

1.3

0.2

80.5

2.5

0.2

including

199.0

200.0

1.0

7.8

0.6

70.6

2.4

5

213.0

214.0

1.0

1.6

0.1

92.3

3.4

0.5

224.0

234.0

10.0

5.1

0.2

114.1

3.8

0.2

including

224.0

226.0

2.0

24.9

0.6

46.2

5.0

0.5

including

225.0

226.0

1.0

47.6

1.1

75.3

5.7

5

249.0

270.0

21.0

0.3

0.1

109.7

6.3

0.2

including

256.0

257.0

1.0

0.6

0.1

110.6

17.6

0.5

and

261.0

262.0

1.0

0.7

0.2

77.5

1.6

0.5

and

269.0

270.0

1.0

2.2

0.5

133.8

4.8

0.5

298.0

308.0

10.0

1.0

0.1

57.7

3.0

0.2

including

298.0

305.0

7.0

1.3

0.1

70.4

3.9

0.5

and

321.0

322.0

1.0

4.6

0.1

46.9

1.8

0.5

328.0

333.0

5.0

1.2

0.3

67.5

2.0

0.2

including

330.0

333.0

3.0

1.9

0.5

80.3

1.8

0.5

EMDD0012

209.0

213.0

4.0

0.6

0.0

0.0

0.0

0.5

275.0

290.0

15.0

0.6

0.1

36.5

1.3

0.2

including

283.0

290.0

7.0

1.0

0.1

71.5

2.4

0.5

294.0

350.0

56.0

0.8

0.2

68.9

38.8

0.2

including

322.0

323.0

1.0

6.6

0.3

65.4

16.4

5

and

345.0

350.0

5.0

1.9

0.2

65.3

20.7

0.5

including

349.0

350.0

1.0

8.8

0.5

64.7

23.3

5

EMDD0013

19.5

20.5

1.0

1.2

0.1

98.4

2.0

0.5

171.0

172.0

1.0

1.0

0.3

141.8

7.4

0.5

183.0

184.0

1.0

5.4

1.0

62.8

2.5

0.5

190.0

193.0

3.0

2.7

0.1

47.2

5.5

0.2

including

192.0

193.0

1.0

7.1

0.3

84.2

7.7

5

Table 2: Empire Drill Collar Details - (all collars from this release)

Hole ID

Easting

Northing

RL_M

Azimuth_True

Dip

EOH_M

Comments

EMDD0001

647575.3

1030224.5

476.7

360

-60

87.32

EMDD0002

647320.8

1030241.0

469.1

359

-60

84.37

EMDD0003

647543.0

1030233.2

474.6

359

-60

93.4

EMDD0004

647341.1

1030254.7

469.9

2

-60

64.4

EMDD0005

647423.9

1030247.1

471.0

359

-59

95.4

EMDD0006

647506.8

1030155.3

475.1

356

-62

252.35

EMDD0007

647447.5

1030153.2

473.8

355

-62

264.35

EMDD0008

647414.7

1030181.1

472.2

356

-62

224.3

EMDD0009

647414.2

1030151.2

472.7

356

-62

45.5

Failed Hole

EMDD0010

647414.1

1030146.0

472.6

356

-62

290.2

EMDD0011

647479.8

1030089.0

474.6

354

-63

449.27

EMDD0012

647413.9

1030075.4

472.3

354

-62

455.8

EMDD0013

647520.9

1029980.5

476.9

360

-52

261.3

Quality Control and Assurance

Analytical work for drill samples is being carried out at the independent Intertek Laboratories in Ghana

and Australia, an ISO 17025 Certified Laboratory. Samples are prepared and stored at the Company's

field camps and put into sealed bags until collected by Intertek from the Company's secure Odienné

office and transported by Intertek to their preparation laboratory in Yamoussoukro, Côte d'Ivoire, for

preparation. Samples are logged in the tracking system, weighed, dried, and pulverized to greater than

85%, passing a 75-micron screen. Two pulps are prepared from each sample with one stream to

Intertek Ghana for fire assay and a second to Australia where the sample is analyzed by 52 element

ICP/MS with a 4-Acid digest. Blanks, duplicates, and certified reference material (standards) are being

used to monitor laboratory performance during the analysis. Where visible gold is observed in drill core,

a quartz wash is applied between every sample to reduce or eliminate any contamination. Once fire

assay results are received, samples over 5 g/t gold are routinely screen fire assayed, samples lower

than 5 g/t gold continued within a high-grade interval are also screen fire assayed.

Mineralized Interval Calculations

Significant intervals reported in this news release are calculated as downhole length-weighted

intercepts. For the Empire target, initial mineralized zones are calculated at a 0.2 g/t Au trigger and

include up to 3 metres of internal waste for delineating mineralized zones. Included intervals are

calculated at 0.5 g/t Au, 1 g/t Au, and 5 g/t Au trigger values, with up to 3 metres of internal waste. Table

1 and 2 contains a list of all holes reported in this release. True widths are estimated to be 75% of the

downhole widths. Holes not reported do not make the 0.2 g/t Au grade trigger.

Qualified Person

The technical and scientific information contained in this news release has been reviewed and approved

for release by Andrew Chubb, the Company's Qualified Person as defined by National Instrument 43-

101. Mr. Chubb is the Company's Chief Executive Officer and holds an Economic Geology degree, is a

Member of the Australian Institute of Geoscientists (AIG), and is a Member of the Society of Economic

Geoscientists (SEG). Mr. Chubb has over 25 years of experience in international mineral exploration and

mining project evaluation.

Abbreviations Used in this Release

Ag

Silver

Au

Gold

Cu

Copper

g/t

Grams per tonne

km

Kilometres

m

Metres

MRE

Mineral Resource

Estimate

Mo

Molybdenum

ppm

Parts per million

AWALÉ Resources Limited

On behalf of the Board of Directors

"Andrew Chubb"

Chief Executive Officer

FOR FURTHER INFORMATION, PLEASE CONTACT:

Andrew Chubb, CEO

(+356) 99139117

[email protected]

Ardem Keshishian, VP Corporate Development

+1 (416) 471-5463

[email protected]

The Company's public documents may be accessed at

www.sedarplus.ca

. For further information on the

Company, please visit our website at

www.awaleresources.com

.

Forward-Looking Information

This news release contains forward-looking information within the meaning of Canadian securities

laws (collectively "forward-looking statements"). Forward-looking statements are typically identified by

words such as: believe, expect, anticipate, intend, estimate, plans, propose, potential, postulate and

similar expressions, or are those, which, by their nature, refer to future events. All statements that are

not statements of historical fact are forward-looking statements. Forward-looking statements in this

news release include but are not limited to statements regarding the Company's presence in Côte

d'Ivoire and ability to achieve results, creation of value for Company shareholders, achievements

under the Newmont JV, works on other properties, timing and extent of planned drilling, expectations

to achieve a first mineral resource estimate and preliminary economic assessment, advancing

towards a pre-feasibility study, potential for new discoveries, timing for providing assay results,

commencement of operations. Although the Company believes any forward-looking statements in this

news release are reasonable, it can give no assurance that the expectations and assumptions in such

statements will prove to be correct. Factors that could cause actual results to differ materially from

such forward-looking information include, but are not limited to, the results of the proposed drilling

programs, the number of drilling rigs on site, changes in the state of equity and debt markets,

fluctuations in commodity prices, delays in obtaining required regulatory or governmental approvals,

and other risks involved in the mineral exploration and development industry, including those risks

set out in the Company's management's discussion and analysis as filed under the Company's

profile at

www.sedarplus.ca

. Forward-looking information in this news release is based on the opinions

and assumptions of management considered reasonable as of the date hereof, including that all

necessary governmental and regulatory approvals will be received as and when expected and that the

proposed drilling program will proceed as planned. Although the Company believes that the

assumptions and factors used in preparing the forward-looking information in this news release are

reasonable, undue reliance should not be placed on such information. The Company disclaims any

intention or obligation to update or revise any forward-looking information, other than as required by

applicable securities laws.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the

policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this

release.

To view the source version of this press release, please visit

https://www.newsfilecorp.com/release/293495