Edmonton, Alberta--(Newsfile Corp. - August 26, 2021) -

Altiplano Metals Inc

. (TSXV: APN) (WKN:

A2JNFG) ("

Altiplano

" or the "Company") is pleased to report on the July 2021 results from the Farellon

Copper-Gold (Cu-Au) mine located near La Serena, Chile.

During July 2021, Farellon extracted approximately 4,020 tonnes of mineralized Cu/Au material at an

approximate grade of 1.52% copper with shipments for processing totaling 2,831 tonnes. These figures

represent a 11.5% improvement from June in tonnes extracted and a 2% increase in the copper grade.

Revenue generated in July was approximately US$243,900 (after processing costs). Waste removal

increased in July, reflecting the ongoing development work of the Hugo decline extension and

preparation work for bench mining practices. At July month end, an additional 1,280 tonnes were

stockpiled at site and will be shipped in August for processing.

CEO Alastair McIntyre commented, "I am pleased to see that our positive July results highlight our focus

on continuation of the upward trend in improved grade and increasing output while working in tandem

with the ongoing development of our decline extension and sustainability work, such as the ventilation

improvements."

Figure 1. Comparative 2021 Monthly Review of Farellon Output

To view an enhanced version of Figure 1, please visit:

https://orders.newsfilecorp.com/files/4303/94388_ce1e495804c5e80f_001full.jpg

Figure 2. Monthly Processed Material, Income and Mining Cost at Farellon

To view an enhanced version of Figure 2, please visit:

https://orders.newsfilecorp.com/files/4303/94388_ce1e495804c5e80f_002full.jpg

Figure 3. Comparative 2021 Income, Copper Contained and Grade

Month 2021

USD Income*

Copper Pounds

Cu grade %

January

$218,695

104,741

1.77%

February

$137,990

68,806

1.38%

March

$184,028

83,974

1.43%

April

$230,655

88,053

1.64%

May

$99,614

39,330

1.23%

June

$269,442

93,277

1.49%

July

$243,853

90,654

1.52%

*

After processing costs

Figure 4. Illustration of Underground Operations at Farellon

To view an enhanced version of Figure 4, please visit:

https://orders.newsfilecorp.com/files/4303/94388_ce1e495804c5e80f_003full.jpg

The decision to re-commence production on the Farellon deposit is not based on a feasibility study of mineral reserves demonstrating economic

and technical viability and there is increased uncertainty and economic and technical risks of failure associated with the production decision.

During July, extraction of Cu/Au mineralized material focused on advancing the 376 SW and the 368 NE

levels. Bench mining continued on the ceiling of level 389 SW and preparation for benching has begun

on the 382 SW ceiling (Figure 4). Development work on the Hugo Decline continues with the advance to

the next access point at the 360 m level where to date, 70.5 m of the total 90 m required to reach the 360

m level have been completed. The decline advance is expected to be completed at the end of August

where an additional advance of 22 m will be required to reach to the vein intersection. This additional

work is expected be completed in September. The civil works for the new ventilation plan started with the

closure of selected areas of the Almendro Tunnel to support the improved airflow through the Hugo

Decline. In addition, the 125 HP fan platform has been installed with test phase preparation underway.

About Altiplano

Altiplano Metals Inc. (TSXV: APN) is a Canadian mining company focused on developing and acquiring

near term cash flowing assets and exploring for projects of significant scale. Altiplano's goal is to grow

into a mid-tier mining company through developing a portfolio of near-term production projects, cash

flowing assets, and exploration projects focusing on copper, gold and silver. Management has a

substantial record of success in capitalizing on opportunity, overcoming challenges and building

shareholder value.

John Williamson, B.Sc., P.Geol., a Qualified Person as defined by NI 43-101, has reviewed and

approved the technical contents of this document.

Altiplano is part of the Metals Group portfolio of companies. Metals Group is an award-winning team of

professionals who stand for technical excellence, painstaking project selection, uncompromising

corporate governance and a unique ability to pan through the rubble to discover and develop golden

opportunities.

www.metalsgroup.com

ON BEHALF OF THE BOARD

/s/ "John Williamson"

Chairman

For further information, please contact:

Alastair McIntyre, CEO

[email protected]

Tel: (416) 434 3799

Jeremy Yaseniuk, Director

[email protected]

Tel: (604) 773-1467

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the

policies of the (TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this

release.

This release includes certain statements that may be deemed "forward-looking statements". All

statements in this release, other than statements of historical facts, that address exploration drilling,

exploitation activities and events or developments that the Company expects are forward-looking

statements. A qualified person has not done sufficient work to classify any historical estimates as

current mineral resources or mineral reserves and the issuer is not treating the historical estimates as

current mineral resources or mineral reserves. The Farellon mine was previously in production dating

back to the 1970's with a reported historical production (to a depth of 70 m) yielding approximately

300,000 tonnes at an average grade of 2.5% copper and 0.5g/t gold. This material was processed

locally and sold to ENAMI. Altiplano is relying upon past production records, underground sampling

and related activities and current diamond drilling to estimate grade and widths of the mineralization

to reactivate production. The decision to commence production on the Farellon deposit is not based

on a feasibility study of mineral reserves demonstrating economic and technical viability and there is

increased uncertainty and economic and technical risks of failure associated with any production

decision. Although the Company believes the expectations expressed in such forward-looking

statements are based on reasonable assumptions, such statements are not guarantees of future

performance and actual results or developments may differ materially from those in the forward-

looking statements. Factors that could cause actual results to differ materially from those in forward-

looking statements include market prices, exploitation and exploration successes, continuity of

mineralization, uncertainties related to the ability to obtain necessary permits, licenses and title and

delays due to third party opposition, changes in government policies regarding mining and natural

resource exploration and exploitation, and continued availability of capital and financing, and general

economic, market or business conditions. Investors are cautioned that any such statements are not

guarantees of future performance and actual results or developments may differ materially from those

projected in the forward-looking statements. For more information on the Company, investors should

review the Company's continuous disclosure filings that are available at

www.sedar.com

.

To view the source version of this press release, please visit

https://www.newsfilecorp.com/release/94388