Altiplano Provides Activity Update at the El Penon Processing Facility and Reports on First Shipments of Copper-Gold-Iron Material
Altiplano Provides Activity Update at the El
Penon Processing Facility and Reports on
First Shipments of Copper-Gold-Iron Material
Edmonton, Alberta--(Newsfile Corp. - April 4, 2022) -
Altiplano Metals Inc
. (TSXV: APN) (WKN:
A2JNFG) ("
Altiplano
" or the "Company") is pleased to report on the ongoing construction activity at the
El Peñón processing facility being built to support copper-gold-iron production from the Farellon mine
located near La Serena, Chile.
Highlights
The first shipments of the stock-piled material from the Farellon Mine have begun, in anticipation of
the completion of the El Peñón processing facility.
A total of 1,440 tonnes will be moved to the new processing site over a two week period. To date
400 tonnes have been received at the plant site.
This material contains an estimated 1.1% copper and 40% iron which will be used as a test feed to
begin the processing circuit.
Further updates on the construction progresses at the facility include:
Ongoing testing of the crushing, milling and copper-gold flotation concentrate circuit.
Installation of the magnetic separation equipment has began following the completed civil
work (cement pads).
Construction of the analytical laboratory is at near completion.
Installation of the Cu concentrate dewatering equipment has begun with the assembly of the
thickener tanks.
The Cu and Fe concentrate and dry stack tails storage areas have been completed in
anticipation of receiving the final concentrate and tails.
Next steps include:
Test run of the Cu-Au flotation circuit with the stock-piled low grade recently shipped to the
site.
Installation and connection of the control room (early April).
Final installation of dewatering equipment (early April).
Connection of electrical to the main grid expected in late April/early May. A generator with
adequate capacity will be used until the utility company completes this work.
First test Cu - Au concentrate produced (early May)
Testing and completion of the magnetic separation and drying processes in May
President and CEO Alastair McIntyre comments, "It is exciting to see the final stages of the processing
facility coming together with most of the major engineering tasks completed. The final connections and
test runs soon to be completed prepares us for full operation this quarter. El Peñón output will be well
timed to leverage the current strong metals price environment."
Figure 1. Views of the Processing Plant
To view an enhanced version of Figure 1, please visit:
https://orders.newsfilecorp.com/files/4303/119116_a9f6580e74f0aa97_001full.jpg
Altiplano has generated over US$7.98 million from the recovery and sale of 3.86 million pounds of
copper with an average grade of 1.74% Cu (2018 Q1-2021 Q4). Cash flow has been re-invested into
equipment, underground drilling, expanding underground development at Farellon, enhancing ventilation
to increase productivity and capacity, new underground development and exploration at Maria Luisa,
and the commencement of the permitted El Peñón fit-for-purpose mill and flotation plant located 15 km
from the Farellon site.
About Altiplano
Altiplano Metals is a growing gold, silver, and copper company focused on the Americas. The Company
has a diversified portfolio of assets that include an operating copper/gold/iron mine, development near
term producing gold/copper projects, and exploration land packages with district-scale potential.
Altiplano is focused on creating long-term stakeholder value through developing safe and sustainable
production, reinvesting into exploration, and pursuing acquisition opportunities to complement its
existing portfolio. Management has a substantial record of success in capitalizing on opportunity,
overcoming challenges and building shareholder value. Altiplano trades on the Toronto Venture
Exchange trading under the symbol APN and the Frankfurt Exchange under the symbol A2JNFG.
John Williamson, B.Sc., P.Geol., a Qualified Person as defined by NI 43-101, has reviewed, and
approved the technical contents of this document.
Altiplano is part of the Metals Group of companies, managed by an award-winning team of professionals
who stand for technical excellence, painstaking project selection and uncompromising corporate
governance, with a proven ability to capitalize on investment opportunities and deliver shareholder
returns.
www.metalsgroup.com
ON BEHALF OF THE BOARD
/s/ "John Williamson"
Chairman
For further information, please contact:
Alastair McIntyre, President and CEO
Tel: (416) 434-3799
For further information, please contact:
Jeremy Yaseniuk, Director
Tel: (604) 773-1467
Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the
policies of the (TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this
release.
This release includes certain statements that may be deemed "forward-looking statements". All
statements in this release, other than statements of historical facts, that address exploration drilling,
exploitation activities and events or developments that the Company expects are forward-looking
statements. A qualified person has not done sufficient work to classify any historical estimates as
current mineral resources or mineral reserves and the issuer is not treating the historical estimates as
current mineral resources or mineral reserves. The Farellon mine was previously in production dating
back to the 1970's with a reported historical production (to a depth of 70 m) yielding approximately
300,000 tonnes at an average grade of 2.5% copper and 0.5g/t gold. This material was processed
locally and sold to ENAMI. Altiplano is relying upon past production records, underground sampling
and related activities and current diamond drilling to estimate grade and widths of the mineralization
to reactivate production. The decision to commence production on the Farellon deposit is not based
on a feasibility study of mineral reserves demonstrating economic and technical viability and there is
increased uncertainty and economic and technical risks of failure associated with any production
decision. Although the Company believes the expectations expressed in such forward-looking
statements are based on reasonable assumptions, such statements are not guarantees of future
performance and actual results or developments may differ materially from those in the forward-
looking statements. Factors that could cause actual results to differ materially from those in forward-
looking statements include market prices, exploitation and exploration successes, continuity of
mineralization, uncertainties related to the ability to obtain necessary permits, licenses and title and
delays due to third party opposition, changes in government policies regarding mining and natural
resource exploration and exploitation, and continued availability of capital and financing, and general
economic, market or business conditions. Investors are cautioned that any such statements are not
guarantees of future performance and actual results or developments may differ materially from those
projected in the forward-looking statements. For more information on the Company, investors should
review the Company's continuous disclosure filings that are available at
www.sedar.com
.
To view the source version of this press release, please visit
https://www.newsfilecorp.com/release/119116