Altiplano Provides 2017 Exploration Update For Its Maria Luisa and Farellon Projects, Chile APN: TSXV The ALTPF: OTCQB 9AJ1: FWB

Exploration Programs

Altiplano Provides 2017 Exploration Update For Its Maria

Luisa and Farellon Projects, Chile

APN: TSXV

The ALTPF: OTCQB

9AJ1: FWB

EDMONTON

,

Nov. 10, 2017

/CNW/ - Altiplano Minerals Ltd. (TSX-V: APN) (OTCQB:ALTPF) (FWB: 9AJ1) ("

APN

" or the "

Company

")

is pleased to provide a summary of exploration and development work completed to date during 2017 at its Maria Luisa and Farellon Cu (Cu-Au)

Projects located approximately 130 km apart in northern

Chile

. This document summarizes all work that has been completed at Altiplano's Chilean

Projects since the effective date of the most recent NI 43-101 Technical Report for these Projects, which was

February 10, 2017

(

Dufresne

,

2017).

1.

Maria Luisa Project

The Maria Luisa project hosts Au-Cu mineralization in two major NW and NS trending strike-slip structural systems. Historical mining has been

largely from the main NW-trending system, the Maria Luisa vein. The Maria Luisa vein is an anastomosing set of structures (traceable for ~500m

long; Fig 2) that range 1–5 m in width and includes veins, faults, magmatic-hydrothermal breccias, and tectonic breccias. This mineralization was

emplaced in two different stages. The stage I (Au-rich) mineralization consists of specular hematite-quartz banded veins with epithermal textures

including open spaces, crustiform quartz, and bladed calcite indicative of boiling. Grades up to 25 g/t Au across 1.6 m obtained from a vein of

massive hematite suggest an association between Au and hematite, although supergene enrichment is suspected due to the presence of jarosite.

This stage is brecciated and cut by a second stage of mineralization. The Stage II (Cu-rich) mineralization consists of magmatic-hydrothermal

breccia with abundant angular fragments of stage I mineralization and andesitic rock either clast supported or cemented by siderite and iron-copper

oxides (hematite, goethite, malachite) at upper levels. At lower levels (below the 841m level), the breccia fragments are dominantly andesite with

lesser fragments of stage I mineralization and is cemented by quartz-chalcopyrite with minor bornite and traces of pyrite.

The

February 2017

Technical Report on Altiplano's Chilean projects (

Dufresne

, 2017) recommended a significant program of work at the Maria

Luisa Project that included drilling, underground sampling, surface surveying (including a UAV survey), underground surveying, geophysical

surveying, underground development and bulk sampling, all of which was to be incorporated into a possible maiden mineral resource estimation

effort for the Project. Altiplano has not yet initiated geophysical surveying or any significant underground drilling or bulk sampling work at the

Maria Luisa Project. As a result, additional work designed to come up with a possible resource estimation has also not yet been initiated at the

Project.

During 2017, Altiplano completed surface surveying at the Maria Luisa project that allowed for the accurate geospatial location of the project's

key geographic and infrastructure, along with numerous features resulting from historical work. The 2017 surveying program included the

completion of a 115 ha photogrammetric drone (UAV) survey that was completed in August of 2017 (Figure 1).

The 2017 exploration program at the Maria Luisa project included the completion of a limited 4-hole (495m) drill program that was intended to

test both styles of mineralization below the main historic workings of the Maria Luisa main structure. The holes were drilled with a NQ diameter,

and the core samples were split to send one half for ICP-MS multi-element analysis at Actlabs laboratories in Coquimbo,

Chile

. Samples were

also analyzed for Au by a standard 30g fire assay method with a gravimetric finish. Additionally, with respect to QC sampling, two (2) different

certified reference materials (standards), and blank pulp samples, were sent to the labat an overall frequency of 1 QC sample in every 10 total

samples. No issues have been found with the results of any of the QC samples received to date. The full set of results is still pending and only

preliminary results are reported here. Core recovery within the mineralized structures ranged between 45 and 60%. The drill hole collar information

and assay data are summarized in Tables 1 and 2 below, and the holes are illustrated in Figure 2.

The drill program intersected both the hematite Au-rich mineralization with hole 17MLD001 (1 m @ 6.95 g/t Au and 0.03% Cu), and Cu-rich

mineralization with hole MLD003 (0.6m @ 5.90% Cu and 0.22 g/t Au). Disseminations of Cu and Au were also identified within holes MLD003

and MLD004. As a result, these holes were recently resampled in their entirety and these results are pending at this time.

Table 1. 2017 Maria Luisa Drill Collars.

Hole ID

Easting (m)

Northing (m)

Elevation (m)

Azimuth

Dip

Depth (m)

17MLD001

306232

6767010

906

45

-60

137.5

17MLD002

306232

6767010

906

45

-50

84.7

17MLD003

306264

6766987

903

15

-70

155.0

17MLD004

306209

6767079

924

60

-55

117.5

Table 2. 2017 Maria Luisa Drill Program Intersection Summary.

Hole ID

From (m)

To (m)

Core

Interval

(m)

Au

(ppm)

Cu

(%)

17MLD001

101.30

102.28

0.98

6.95

0.03

17MLD002

81.70

83.20

1.50

0.66

1.28

17MLD003

94.15

96.70

2.55

0.16

1.68

including

94.75

95.35

0.60

0.22

5.09

and

100.00

102.00

2.00

1.53

0.38

and

115.00

116.40

1.40

1.62

2.53

17MLD004

42.90

44.40

1.50

1.32

0.52

(note: there is insufficient information available to determine true widths at this time)

2.

Farellon Project

The Farellon Project is being explored for Copper (Cu) bearing, +/- gold (Au), magnetite veins that have seen historical production at shallow

levels. The

February 2017

Technical Report on Altiplano's Chilean projects (

Dufresne

, 2017) also recommended a significant program of work at

the Farellon Project that included drilling, underground sampling, surface surveying (including a UAV survey), underground surveying, geophysical

surveying, underground development and bulk sampling, all of which was to be incorporated into a possible maiden mineral resource estimation

effort for the Project. Results of the UAV are shown on Figure 3. Altiplano has not yet initiated geophysical surveying and is currently planning a

bulk sampling effort intended to evaluate Cu mineralization that has recently been encountered adjacent to the new (2017) Farellon decline, which

has been advanced 341m thus far in 2017. A possible mineral resource estimation has not yet been initiated for the Farellon vein structure.

The primary focus of Altiplano's work in 2017 has been the advancement of the new decline at the Farellon Project and subsequent underground

drilling from drill stations cut along the decline. The Farellon decline is being excavated as a 3m x 3m tunnel that is intended to drop at a rate of

approximately 15% in the immediate footwall approximately 10-15m away from the Farellon structure, which strikes roughly 065

o

and dips

approximately 72

o

to the southeast. In total, 26 underground core holes were initiated during 2017 along the Farellon decline, 25 of which

reached their planned length. The program currently comprises 334.13m of drilling. Of the 25 holes that reached their intended length, only 6

failed to intersect the Farellon structure and instead intersected mafic dykes. The remaining holes intersected the magnetite-chalcopyrite Farellon

vein hosted within a diorite intrusion. Core recovery within the intersected mineralized zones ranged between 90 and 100%. The 2017 Farellon

drill holes were drilled with a BQ diameter and the core samples were generally split to send one half for CuT (total Cu) and Au analyses at

Actlabs laboratories in Coquimbo, Chile. The analytical methods applied to the Farellon samples were the same as those discussed above for the

Maria Luisa drilling samples. Although the current procedure is to split the Farellon core, whole core was sent for analysis from the first 6 holes of

the program. For QC sampling, blank pulp and two (2) different certified reference materials (standards) were inserted by the company into the

regular drill sample stream at an overall frequence of 1 in 10 samples. To date, no significant issues with the Farellon QC sample analyses have

been identified.

The 2017 Farellon drill program collar information and significant intersections are summarized in Tables 3 and 4 below and the drillholes are

illustrated in Figures 4 and 5. The most significant result of the 2017 underground drilling, apart from the continuity of the Farellon structure, was

the apparent increase in copper grades in the more recent drilling at the current extent of the decline, which is located immediately beneath the

historically mined (shallow) portion of the structure. As a result, a bulk sampling program in this portion of the Farellon vein is currently being

planned. Further development of the Farellon decline and additional underground drilling is ongoing.

Table 3. 2017 Farellon Project Underground Drill Collars.

Hole ID

Easting (m)

Northing (m)

Elevation (m)

Aimuth

Dip

Depth (m)

Drill Station

17FND001

287617.6

6657770.9

421.5

152.45

-0.30

5.60

110

17FND002

287708.8

6657818.6

407.5

183.02

0.00

12.60

210

17FND003

287729.9

6657823.2

405.2

129.84

2.84

6.02

230

17FND004

287729.9

6657823.2

405.1

143.80

-28.52

9.66

230

17FND005

287729.9

6657823.2

405.3

126.84

28.79

11.44

230

17FND006

287754.4

6657839.0

401.2

144.54

-0.18

5.54

260

17FND007

287754.6

6657839.1

401.2

103.68

-1.16

7.78

260

17FND008

287754.2

6657838.9

401.2

200.00

0.00

5.60

260

17FND009

287730.0

6657823.4

405.2

101.40

-1.83

6.81

230

17FND010

287729.7

6657823.0

405.2

170.53

0.18

7.10

230

17FND011

287729.7

6657823.0

405.0

180.00

-30.00

10.50

230

17FND012

287768.7

6657852.0

400.0

148.00

0.00

21.25

280

17FND013

287778.2

6657855.2

399.6

115.40

0.26

24.74

290

17FND014

287778.4

6657855.4

399.5

99.53

-2.43

12.68

290

17FND015

not drilled

17FND016

287730.6

6657824.6

405.3

88.92

-1.96

12.99

230

17FND017

287730.6

6657824.6

405.3

89.04

-32.64

15.02

230

17FND018

287777.5

6657854.5

399.5

159.36

-0.71

11.70

290

17FND019

287778.5

6657856.4

399.5

101.79

-31.70

15.50

290

17FND020

287810.0

6657880.6

397.5

119.42

-2.17

19.82

330

17FND021

287778.9

6657855.4

399.5

144.23

-29.93

18.70

290

17FND022

287775.9

6657855.3

399.5

210.29

-0.46

13.85

290

17FND023

287786.3

6657865.0

398.8

85.25

-4.80

23.50

300

17FND024

287810.0

6657880.7

397.7

157.16

-1.06

16.54

330

17FND025

287810.2

6657880.9

397.7

133.63

-0.42

18.00

330

17FND026

terminated short of target

17FND027

287810.2

6657880.9

397.7

155.36

-31.54

21.19

3300

Table 4. 2017 Farellon Drill Program Intersection Summary.

DDH

From

(m)

To

(m)

Core

Interval

(m)

True

Width*

(m)

Cu (%)

17FND001

3.10

4.90

1.80

1.60

1.21

17FND002

10.00

11.60

1.60

1.25

1.17

17FND003

2.34

3.63

1.29

1.15

1.54

17FND004

4.01

6.98

2.97

1.70

1.18

17FND005

no vein intersection (dyke)

17FND006

1.07

2.57

1.50

1.35

0.88

17FND007

2.15

6.72

4.57

3.05

1.59

including

2.15

3.72

1.57

1.05

2.88

17FND008

1.57

3.85

2.28

1.15

1.12

including

2.67

3.17

0.50

0.25

2.31

17FND009

3.12

4.50

1.38

0.85

1.26

17FND010

3.29

4.87

1.58

1.30

0.99

17FND011

no significant intersection (vein)

17FND012

no vein intersection (dyke)

17FND013

no vein intersection (dyke)

17FND014

no vein intersection (dyke)

17FND015

not drilled

17FND016

5.80

7.20

1.40

0.65

1.50

17FND017

10.59

11.79

1.20

0.40

1.75

17FND018

6.20

7.70

1.50

1.30

2.02

17FND019

6.60

8.65

2.05

0.90

2.33

17FND020

13.56

18.35

4.79

3.80

4.14

including

14.70

17.80

3.10

2.45

6.11

including

14.70

15.46

0.76

0.60

10.29

17FND021

no vein intersection (dyke)

17FND022

no vein intersection (dyke)

17FND023

20.65

22.90

2.25

0.75

0.55

17FND024

8.82

11.28

2.46

2.20

1.18

including

10.38

11.28

0.90

0.80

2.41

17FND025

11.11

15.14

4.03

3.40

1.29

including

11.51

12.51

1.00

0.85

3.17

17FND026

terminated short of target

17FND027

14.27

17.45

3.18

1.95

2.10

including

15.82

17.45

1.63

1.00

3.74

including

15.82

16.56

0.74

0.45

5.11

* True Widths are approximate based upon the apparent dip of the Farellon structure.

John Williamson

, P.Geol., President and CEO of Altiplano, is the Qualified Person as defined in National Instrument 43-101 who has

reviewed and approved the technical contents of this press release.

About Altiplano

Altiplano Minerals Ltd. (APN: TSX

V)

is a mineral exploration company focused on evaluating and acquiring projects with significant potential

for advancement from discovery through to production, in

Canada

and abroad. Management has a substantial record of success in capitalizing

opportunity, overcoming challenges and building shareholder value. Additional information concerning Altiplano can be found on its website at

www.altiplanominerals.com

.

ON BEHALF OF THE BOARD

/s/ "John Williamson"

President and CEO

Tel: (780) 437-6624

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the (TSX Venture

Exchange) accepts responsibility for the adequacy or accuracy of this release.

This release includes certain statements that may be deemed "forward-looking statements". All statements in this release, other than

statements of historical facts, that address exploration drilling, exploitation activities and events or developments that the Company

expects are forward-looking statements. Although the Company believes the expectations expressed in such forward-looking statements

are based on reasonable assumptions, such statements are not guarantees of future performance and actual results or developments may

differ materially from those in the forward-looking statements. Factors that could cause actual results to differ materially from those in

forward-looking statements include market prices, exploitation and exploration successes, continuity of mineralization, uncertainties

related to the ability to obtain necessary permits, licenses and title and delays due to third party opposition, changes in government

policies regarding mining and natural resource exploration and exploitation, and continued availability of capital and financing, and

general economic, market or business conditions. Investors are cautioned that any such statements are not guarantees of future

performance and actual results or developments may differ materially from those projected in the forward-looking statements. For more

information on the Company, investors should review the Company's continuous disclosure filings that are available at

www.sedar.com

.

SOURCE

Altiplano Minerals

View original content with multimedia: http://www.newswire.ca/en/releases/archive/November2017/10/c7340.html

%SEDAR: 00030745E

For further information:

Jeremy Yaseniuk, Director, [email protected], Tel: (604) 773-1467; Renmark Financial

Communications Inc., Laura Welsh: [email protected], Tel.: (416) 644-2020 or (514) 939-3989, www.renmarkfinancial.com

CO: Altiplano Minerals