Altiplano Announces Q1 2021 Results at Farellon

Financials

Altiplano Announces Q1 2021 Results at

Farellon

Edmonton, Alberta--(Newsfile Corp. - May 10, 2021) -

Altiplano Metals Inc

. (TSXV: APN) (WKN:

A2JNFG) ("

Altiplano

" or the "Company") is pleased to report on the Q1 2021 results from the Farellon

Copper-Gold (Cu-Au) mine located near La Serena, Chile.

During Q1, 2021, the Company extracted a total 9,770 tonnes of mineralized Cu/Au material at Farellon

and processed 8,055 tonnes at an average copper grade of approximately 1.53%. Sales of 257,500

pounds of copper generated approximately US$544,000 in revenue. Total revenue since Q1 2018

generated at the Farellon operation now represents more than US$6,000,000 from the sale of

approximately 2.96 mm pounds of copper.

Total extracted tonnes in Q1 declined by 19.5% from the previous record quarterly set in Q4 2020.

Processed material was also lower in Q1 representing a 11.5% decrease from the previously strong

quarter. Overall grade declined by 8.9% from Q4 2020. Grade and extraction declines are attributed to

development work in non-productive areas and reduction in grade control as the benching process of

removing ceilings between drift levels has begun. The grade is expected to improve in April as new

headings are developed and with access to higher grade zones.

At the end of March 2021, the

Company had 1,600 tonnes in stockpiles at the Farellon site and an additional 1,428 tonnes in process.

CEO Alastair McIntyre comments "the work in Q1 2021 reflects our ongoing focus on development and

sustainability. As we advance to additional headings at depth, and begin to mine within existing levels,

this provides us the opportunity to improve output and increase efficiencies. Our next steps are to begin

mining on the 369 m level in the NE and SW directions, following up with an extension to the 360 m

level."

Figure 1. Mined, Processed and Cu Grade

To view an enhanced version of Figure 1, please visit:

https://orders.newsfilecorp.com/files/4303/83337_77735d69a47f48cb_001full.jpg

Figure 2. Processed Material, income vs. Mining Costs

To view an enhanced version of this graphic, please visit:

https://orders.newsfilecorp.com/files/4303/83337_altiplano2.jpg

Period

USD Revenue

Cu Pounds Sold

Q1 2020

$320,960

188,670

Q2 2020

$477,805

310,255

Q3 2020

$827,298

460,385

Q4 2020

$579,276

322,130

Q1 2021

$544,019

277,520

Total

$2,749,500

1,558,950

Figure 3.

Quarterly Review of US$ Revenue and Copper Pounds Sold

Figure 4. Farellon Mine Section

To view an enhanced version of Figure 4, please visit:

https://orders.newsfilecorp.com/files/4303/83337_77735d69a47f48cb_003full.jpg

The decision to commence production on the Farellon deposit is not based on a feasibility study of

mineral reserves demonstrating economic and technical viability and there is increased uncertainty

and economic and technical risks of failure associated with the production decision

Mining activity in Q1 2021 involved completing the advance on the 376 m NE and 382 m NE levels

where work has also begun to remove the ceilings between these drifts. This benching method is used to

extract the mineralized material remaining between the drift levels, which is removed to the surface. This

work also creates additional ventilation as the spaces between these levels open up. Two chimneys

were created to open two additional air flow channels by connecting the 382 m SW with 389 m SW

levels and also connecting the 389 m SW with 395 m SW levels. Finally, the extension of the Hugo

Decline to the 369 m level began at the end of March. This approximately 80 m extension is expected to

be completed in May (News Release 4 April 2021).

About Altiplano

Altiplano Metals Inc. (TSXV: APN) is a Canadian mining company focused on the acquisition and

development of near-term cash flowing assets and exploration projects of significant scale. Altiplano's

goal is to grow into a mid-tier producer of copper, gold and silver with immediate plans of generating

profits from three cash flowing projects in 2021. Management has a substantial record of success in

capitalizing on opportunity, overcoming challenges and building shareholder value.

John Williamson, B.Sc., P.Geol., a Qualified Person as defined by NI 43-101, has reviewed and

approved the technical contents of this document

Altiplano is part of the Metals Group of companies.

Metals Group is an award-winning team of

professionals who stand for technical excellence, painstaking project selection and uncompromising

corporate governance, with a proven ability to capitalize on investment opportunities and deliver

shareholder returns.

www.metalsgroup.com

ON BEHALF OF THE BOARD

/s/ "John Williamson"

Chairman

For further information, please contact:

Alastair McIntyre, CEO

[email protected]

Tel: (416) 434-3799

Jeremy Yaseniuk, Director

[email protected]

Tel: (604) 773-1467

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the

policies of the (TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this

release.

This release includes certain statements that may be deemed "forward-looking statements". All

statements in this release, other than statements of historical facts, that address exploration drilling,

exploitation activities and events or developments that the Company expects are forward-looking

statements. A qualified person has not done sufficient work to classify any historical estimates as

current mineral resources or mineral reserves and the issuer is not treating the historical estimates as

current mineral resources or mineral reserves. The Farellon mine was previously in production dating

back to the 1970's with a reported historical production (to a depth of 70 m) yielding approximately

300,000 tonnes at an average grade of 2.5% copper and 0.5g/t gold. This material was processed

locally and sold to ENAMI. Altiplano is relying upon past production records, underground sampling

and related activities and current diamond drilling to estimate grade and widths of the mineralization

to reactivate production. The decision to commence production on the Farellon deposit is not based

on a feasibility study of mineral reserves demonstrating economic and technical viability and there is

increased uncertainty and economic and technical risks of failure associated with any production

decision. Although the Company believes the expectations expressed in such forward-looking

statements are based on reasonable assumptions, such statements are not guarantees of future

performance and actual results or developments may differ materially from those in the forward-

looking statements. Factors that could cause actual results to differ materially from those in forward-

looking statements include market prices, exploitation and exploration successes, continuity of

mineralization, uncertainties related to the ability to obtain necessary permits, licenses and title and

delays due to third party opposition, changes in government policies

regarding mining and natural resource exploration and exploitation, and continued availability of

capital and financing, and general economic, market or business conditions. Investors are cautioned

that any such statements are not guarantees of future performance and actual results or

developments may differ materially from those projected in the forward-looking statements. For more

information on the Company, investors should review the Company's continuous disclosure filings

that are available at

www.sedar.com

.

To view the source version of this press release, please visit

https://www.newsfilecorp.com/release/83337