HUDSON RESOURCES PROVIDES FALL CONSTRUCTION UPDATE
FOR THE WHITE MOUNTAIN ANORTHOSITE PROJECT, GREENLAND
Vancouver, BC - HUDSON RESOURCES INC. (the “Company”) – (TSX Venture Exchange “HUD”;
OTC “HUDRF”) is pleased to provide the following update on construction activities completed this fall
at the White Mountain anorthosite project in Greenland.
Since the Company’s last update on construction activities (NR2017-13 dated September 25, 2017),
Hudson has met a number of important milestones as it moves towards production by the second half
of 2018. Key activities included:
• Completion of the concrete foundations for the process plant, fuel farm and 95% of the product
warehouse building;
• Completion of the installation of the 500,000 litre diesel fuel farm which is comprised of five 100,000
litre double walled tanks. In November, Hudson received 270,000 litres of arctic grade diesel by fuel
ship – enough to complete project construction;
• Successfully barged 1,100 tonnes of goods to site from Canada. Cargo included the project
buildings, major components of the process equipment, the shiploader, three mobile cranes and 6
man lifts;
• Completion of the shipping and erection of the 44 room accommodation complex. This
accommodation complex will house the construction team and will then be used for operations;
• Completion of the port including the mooring of Hudson’s 90m x 30m barge, which will be the
permanent wharf for the mine. Three ships have already called on the Hudson port, including Royal
Arctic’s largest container ship, the Naja Acrtica;
• Completion of the structural components of the truck shop which will be finished early next year;
• Extending the road to within 4km of the mine site; and
• Completion of the US$9.5 million drawdown of subordinated debt (after satisfying the conditions of
the loan) and a portion of the senior loan with Cordiant Capital.
James Tuer, Hudson’s President, stated, “We are very pleased with the progress that we’ve made this
year. We have now completed almost all of the infrastruct ure for the mine which makes up a large
portion of the construction activities. We are now focused on working towards next years activities with
the goal of shipping product to customers by the second half of 2018. We are in advanced discussions
with additional customers for E-Glass and for paints and coatings applications and we are developing
additional applications for this unique material which we hope to be able to announce early next year.”
On October 15, Hudson’s barge arrived at the White Mountain project from Sydney Nova Scotia with
1,100 tonnes of cargo including 52 shipping containers and several pieces of mobile construction
equipment. Major cargo components included the process plant building, product warehouse building,
Suite 420 – 1639 2nd Ave W. Tel: (604) 628-5002
Vancouver, B.C. V6J 1H3 Fax: (604) 688-3452
truck shop building, 3 mobile cranes, 6 man lifts, the ship loader and associated conveyors, screening
equipment for the process plant, structural steel and construction equipment. The barge was unloaded
and the cargo stored around the project area in preparation for construction.
Prior to unloading, the barge was secured to the shoreline by a unique and robust mooring system
designed by Hudson which includes a number of forward and aft chain lines, spring lines and stiff legs
to keep the barge 10m off shore. This provides a minimum of 20m draft which will allow any size ship to
dock at the port, providing Hudson with more flexibility in the future for shipping of product.
The Company purchased a 44-man camp, which was located in Nuuk, the capital of Greenland. The
facility was dismantled, moved and erected on site in October and November. The facility will be
instrumental in providing high quality accommodation to construction and operating staff.
A large majority of the process equipment and buildings have been delivered and are safely stored at
site ready for erection to commence in April 2018. Additional equipment is in transit with the remaining
equipment to be delivered over the next few months. The objective is to begin plant commissioning next
summer with product shipping to customers in the second half of 2018. With this in mind, Hudson
continues to work with the Greenland government to encourage local employment and ensure all
operating conditions under the mining licence and impact benefits agreement (IBA) are met.
At the end of July, the Company completed the 7-year debt funding arrangement with Cordiant Capital
for a Senior Loan of US$13 million and a Subordinated Loan of US$9.5 million, for a total of US$22.5M
through Hudson’s 100% owned Greenland subsidiary, Hudson Greenland A/S.
Hudson currently holds cash and cash equivalents of approximately $10.4 million, of which $1.3 million
has been set aside as a reclamation bond, $1.3 million in a debt service reserve account as part of the
loan financing agreement and $6.1 million has been drawn down and available for current and future
expenditures. Another US$4.5 million remains undrawn and available to the Company in the form of
senior debt.
Photos of the 2017 activities have been updated on Hudson’s website: hudsonresources.ca/gallery.asp
ON BEHALF OF THE BOARD OF DIRECTORS
“James Tuer”
James Tuer, President
For further information:
James Tuer, President
Ph: 604-628-5002 or 604-688-3415
Forward-Looking Statements
This news release includes certain forward-looking statements or information. All statements other than statements of historical fact included
in this news release, including, without limitation, statements regarding the use of proceeds from the private placement, and other future plans
and objectives of the Company are forward-looking statements that involve various risks and uncertainties. There can be no assurance that
such statements will prove to be accurate and actual results and future events could differ materially from those anticipated in such
statements. Important factors that could cause actual results to differ materially from the Company's plans or expectations include market
prices, general economic, market or business conditions, regulatory changes, timeliness of government or regulatory approvals and other risks
detailed herein and from time to time in the filings made by the Company with securities regulators. The Company expressly disclaims any
intention or obligation to update or revise any forward-looking statements whether as a result of new information, future events or otherwise
except as otherwise required by applicable securities legislation.
Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange)
accepts responsibility for the adequacy or accuracy of this release.