Hudson Provides Update ON Engineering and Construction Activities at the White Mountain Anorthosite Project IN Greenland

Mine Development & Operations

Suite 420– 1639 2nd Ave. W. Tel: (604) 628-5002

Vancouver, B.C. V6J 1H3 Fax: (604) 688-3452

FOR IMMEDIATE RELEASE TSX-V: HUD

June 29, 2017 OTC: HUDRF

NR2017-10

HUDSON PROVIDES UPDATE ON ENGINEERING AND CONSTRUCTION ACTIVITIES

AT THE WHITE MOUNTAIN ANORTHOSITE PROJECT IN GREENLAND

Vancouver, BC - HUDSON RESOURCES INC. (the “Company”) – (TSX Venture Exchange “HUD”;

OTC “HUDRF”) is pleased to provide an update on engineering and construction activities at the

company’s White Mountain Anorthosite project in western Greenland. So far this year, activities have

focused on completing the civil works in the field, finalizing detailed engineering, and the procurement

of all of the major project components for the process plant and infrastructure.

With respect to civil works, RTS Greenland A/S, is currently finishing the drill and blast operations to

prepare for foundations for the process plant, product storage building and ancillary infrastructure.

Civil works will continue through to the fall to support the project infrastructure. Concrete foundation

work will commence shortly upon finalization of an agreement with a contractor. Building erection and

mechanical installation are planned to commence in the fall.

With regard to engineering, CWA Engineers Inc. have completed all but a few remaining detailed

engineering drawings. Hudson has also engaged Ramboll Group A/S and Automatic Syd A/S, both out

of Denmark, for the electrical engineering and motor control center (MCC) facilities.

Major on site accomplishments so far this year include:

• Completion of a new access road from the port;

• Completion of blasting for the warehouse, which is a 90m by 45m building for storing 30,000

tonnes of final product;

• Completion of the access roads for the bollards at the dock;

• Completion of the process plant site which is a 40m by 40m pad;

• Preparation of the site for the accommodation complex; and

• Receipt of materials for preparation of the concrete foundation work.

“We are very pleased to be undertaking these activities on site as we advance the project towards

commercial production” commented James Tuer, Hudson’s president. “This next phase in our

company’s history is to transform from explorer to producer and bring a unique resource to market. We

believe this will generate a number of exciting new business lines for the company including supplying

feed product to the E-Glass fiberglass market, the paints and coatings business and the alumina

industry”.

“Construction activities are proceeding well, however a late revision in the process plant design will

result in the delayed delivery of some of the conveyors. This, along with a few other delays, will push

our ambitious goal of commissioning the plant by late 2017 to the middle of next year when we expect

to commence shipping product. In the meantime, potential customers continue to test our anorthosite

for E-Glass and coatings applications with positive results and Hudson is working towards additional

off-take agreements.”

Procurement of all major project components is now complete. The following have now been

purchased and are expected to be ready for shipment over the next couple of months:

• Product storage building and Process building (Norsteel Buildings);

• Truck maintenance building (Vertical Building Structures);

Suite 420– 1639 2nd Ave. W. Tel: (604) 628-5002

Vancouver, B.C. V6J 1H3 Fax: (604) 688-3452

• Maxtrak 1000 SR Mobile cone crusher to feed the plant (Powerscreen);

• Two High Pressure Grinding Rolls installed in the plant (Weir Minerals);

• Six high intensity magnetic separators (Eriez Manufacturing);

• Three coarse and two quad deck fine screens for sorting product (Derrick Corporation);

• Twenty-three process conveyors (Continental Conveyor – a number of which will be delayed)

• 1,200 stph shiploader and conveying system from the warehouse (Thor Global);

• Five 100,000 litre fuel tanks for the fuel farm (CGH Nordic);

• Used 44 bed accommodation complex (subject to Greenland government approval);

• Various mobile equipment including a 35-tonne and two 90-tonne cranes, Telehandler, 30-tonne

excavator, trucks and concrete batch plant; and

• The 300’ by 100’ barge that will deliver a significant portion of the equipment sourced in North

America and then be moored as the floating wharf this fall.

Hudson owns 100 percent of the White Mountain project. The company was granted a 50-year mining

license in 2016, and the deposit has resources defined for more than 100 years of production. Hudson

will provide photos of the construction progress on a regular basis on its website.

ON BEHALF OF THE BOARD OF DIRECTORS

“James Tuer”

James Tuer, President

For further information:

James Tuer, President

Ph: 604-628-5002 or 604-688-3415

[email protected]

Forward-Looking Statements

This news release includes certain forward-looking statements or information. All statements other than statements of

historical fact included in this news release, including, without limitation, statements regarding the use of proceeds from t he

private placement, and other future plans and objectives of the Company are forward-looking statements that involve various

risks and uncertainties. There can be no assurance that such statements will prove to be accurate and actual results and

future events could differ materially from those anticipated in such statements. Important factors that could cause actual

results to differ materially from the Company's plans or expectations include market prices, general economic, market or

business conditions, regulatory changes, timeliness of government or regulatory approvals and other risks detailed herein and

from time to time in the filings made by the Company with securities regulators. The Company expressly disclaims any

intention or obligation to update or revise any forward-looking statements whether as a result of new information, future events

or otherwise except as otherwise required by applicable securities legislation.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is de fined in the policies of the TSX

Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.