Abacus provides update on environmental review process at Ajax Project

Corporate Updates

TSX.V Symbol: AME

Abacus provides update on environmental review process at Ajax Project

Vancouver, BC – May 15, 2017. Abacus Mining & Exploration Corporation (“ Abacus”

or the “ Company”) (TSXV:AME) wishes to provide an update on the Ajax Project’s

Environmental Assessment (“EA”) review process within the context of a joint and

coordinated federal and provincial review effort towards a streamlined process and timeline

alignment.

Resumption of EA Review Process

On March 29, 2017, the operator of the Ajax Project, KGHM International (“KGHMI”),

was notified by the British Columbia Environmental Assessment office (“EAO”) that, as a

result of the satisfactory completion of information and materials in r esponse to issues

raised by multiple stakeholders, and in fulfilment of the requirements related to Aboriginal

and public consultation, it ha d lifted its suspension of the 180 -day time limit for the

application review. This suspension was originally requested by KGHMI to fulfill the

requirements to the EAO’s satisfaction.

The resumption of the review process occurs at day 108 of the 180-day timeframe and is a

positive development toward the feasibility of a final decision later this fall.

EA Process next steps

The EAO also informed that, going forward, the Ca nadian Environmental Assessment

Agency (“Agency”) and the EAO have agreed to see k a greater level of coordination and

to prepare a joint assessment report. This coordinated approach is expected to streamline

the process and provide greater certainty of process through the alignment of timelines,

ensuring that both jurisdictions consid er the same information and avoid duplication .

Throughout the period, t he Agency and the EAO have acted in coordination on the Ajax

Project, co -chairing a technical working group, participating in consultation with

Aboriginal groups and coordinating public comment periods.

To provide the process certainty for the remainder of the EA and to ensure federal-

provincial timeline alignment consistent with a coordinated process, the provincial review

period will be extended by an additional 110 days. Inclusive of the extension will be a 30-

day public comment period on the joint assessment report and any draft provincial EA

Certificate conditions , as well as a 45 -day period for provincial Ministers to make a

decision as to whether to issue an EA Certifi cate for the Ajax Project. Hence the

Application review phase is expected to conclude around late September 2017, and

decisions from the provincial and federal governments are expected later in the fall.

Suite 615-800 West Pender Street

Vancouver, B.C. V6C 2V6 Canada

Tel: 604.682.0301 Fax: 604.682.0307

email: [email protected]

website: www.amemining.com

TSX Venture Exchange Symbol: AME

Community and First Nations Consultations

The goal of the Ajax Project is to be an integral member of the community through an

open-door policy of continuous consultation and providing solutions which have resulted

in numerous technical enhancements and design changes through the Application/EIS

process that has improved the Project. One such major change is the new mine plan which

concentrates mining activities in a central footprint to reduce emissions and dust. This has

necessitated the relocation of the tailings storage facility to more than 5 kms southeast and

no longer within Kamloops City limits; the facility has been redesigned from a dry stack

tailings to a thickened tailings storage facility; t he north rock storage facility has been

relocated, including the mine processing plant and ore stockpiles more than 2 kms south of

their formerly proposed locations; and the primary crusher will also move south of the pit,

and approximately 3.5 kms from the closest city neighbourhood.

Another recent example is in response to the Tk’emlups and Skeetchestn bands (“SSN”)

concerns over the preservation of a historic fish habitat. A new plan involves construction

of a dam and connector channel, preservation of a spillway, and restoration of fish habitat

by adding spawning gravel , in addition to creating a new access road, boat launch and

recreational area for local fishers.

Negotiations are ongoing with the City of Kamloops and the SSN towards a lasting

partnership which the Ajax team views as an essential opportunity to invest in the future

of Kamloops and nearby communities.

For further information, please contact Investor Relations at (604) 682-0301.

On Behalf of the Board,

ABACUS MINING & EXPLORATION CORPORATION

Michael McInnis

Chairman, President & CEO

About Abacus

Abacus is a mineral exploration and mine development company with a 20% interest in the

Ajax Project located at the historic Ajax -Afton site southwest of Kamloops, B.C., and an

option to acquire up to a 75% undivided interest in the Willow porphyry copper -gold

property located in Nevada. The Ajax Project is a proposed copper -gold open-pit mine

currently undergoing a provincial and federal environmental assessment process. Through

KGHM Ajax Mining Inc., a joint venture company between Abacus (20%) and KGHM

Polska Miedz S.A. (KGHM) (80%), the Ajax Mine is being funded in large part by KGHM

and operated by its wholly -owned subsidiary, KGHM International Ltd. For the latest

reports and information on Abacus’ projects, please refer to the Company’s website at

www.amemining.com.

Forward-Looking Information

This release includes certain statements that are deemed “forward-looking statements”. All statements in this

release, other than statements of historical facts, that address events or developments that Abacus expects to

occur, are forward-looking statements. Forward-looking statements are statements that are not historical facts

and are generally, but not always, identified by the words “expects”, “plans”, “antici pates”, “believes”,

“intends”, “estimates”, “projects”, “potential” and similar expressions, or that events or conditions “will”,

“would”, “may”, “could” or “should” occur. Although the Company believes the expectations expressed in

such forward-looking statements are based on reasonable assumptions, such statements are not guarantees of

future performance and actual results may differ materially from those in the forward -looking statements.

Factors that could cause the actual results to differ materially f rom those in forward -looking statements

include changes to commodity prices, mine and metallurgical recovery, operating and capital costs, foreign

exchange rates, ability to obtain required permits on a timely basis, exploitation and exploration successes,

continued availability of capital and financing, and general economic, market or business conditions.

Investors are cautioned that any such statements are not guarantees of future performance and actual results

or developments may differ materially from t hose projected in the forward -looking statements. Forward -

looking statements are based on the beliefs, estimates and opinions of the Company's management on the

date the statements are made. Except as required by applicable securities laws, the Company und ertakes no

obligation to update these forward -looking statements in the event that management's beliefs, estimates or

opinions, or other factors, should change.