Arizona Metals Intersects 44.5 m @ 4.0 g/t AuEq, 18.6 m @ 2.1% CuEq,
and 32.0 m @5.3 g/t AuEq in Kay2 Zone
Toronto, May 27, 2025 – Arizona Metals Corp. (TSX:AMC, OTCQX:AZMCF) (the “Company”
or “Arizona Metals”) is pleased to announce assay results from five drill holes in the Kay2 Zone
at the Kay project in Arizona.
• Drill hole KM -25-180 intersected 44.5 m @ 4.0 g/t AuEq, including 9.5 m @ 9.2 g/t AuEq
and 0.9 m @ 21.7 g/t AuEq. (Figure 1, Table 1). The hole is located approximately 40 m south
of hole KM-24-166, the discovery hole in the Kay2 Zone.
• Drill hole KM-25-178 intersected three intervals: 18.6 m @ 2.1% CuEq, 8.4 m @ 1.9% Cueq,
and 1.8 m @ 2.4 g/t AuEq (Figure 1, Table 1). This hole is located about 45 m above hole KM-
24-166.
• Drill hole KM-25-179 also returned three intervals: 32.0 m @ 5.3 g/t AuEq (including 6.1 m
@ 10.9 g/t AuEq), 1.5 m @ 6.2%CuEq, and 7.6 m @ 1.0% CuEq (Figure 1, Table 1). Hole
179 is located 70 m above and south of hole 166, and 70 m above hole 180.
To date, drilling in the Kay2 Zone has demonstrated dimensions of 100 m along strike and 140 m
vertically. Drilling shows good continuity in mineralization in the Kay2 Zone and adjacent
mineralization in the main Kay deposit to the south. The Kay2 Zone is located approximately 100
m north of previously drilled mineralization in the Kay deposit.
Duncan Middlemiss, President and CEO of Arizona Metals, comment s: “We are encouraged by
the latest drill results from the Kay2 Zone, which continue to demonstrate significant expansion
potential. The intercepts show substantial thicknesses, consistent grades, and strong continuity —
key indicators of a robust mineralized system. These results reinforce our confidence in th e Kay2
Zone and support our view that the se results will contribute to the overall tonnage of the Kay
deposit. We believe this will be clearly reflected in the updated mineral resource estimate, which
remains on track for release in the second quarter of 2025.”
The Company has also received approval for one additional drill pad from the Bureau of Land
Management under the existing Notice of Intent to Explore permit. This drill pad provides
additional opportunities to test the Kay North Extension target where the Kay mineralized horizon
continues north from the Kay deposit. One drill hole in the Kay2 Zone, KM-25-176, encountered
no significant assays (Table 1). Deep drill hole KM-25-177, targeted at the depth extension of the
main Kay deposit, was lost before reach ing the target depth due to difficult drilling . With the
completion of recent drill holes, Arizona Metals has drilled a total of 133,000 meters on the
property.
Table 1. Results of Phase 3 Drill Program at the Kay Project, Yavapai County, Arizona announced in this news release.
Analyzed Grade
Analyzed Metal
Equivalent
Metal Equivalent
Hole ID
From
m To m
Length
m
Cu
%
Au
g/t
Zn
%
Ag
g/t
Pb
%
CuEq
%
AuEq
g/t
ZnEq
%
CuEq
%
AuEq
g/t
ZnEq
%
KM-25-176 no significant assays
KM-25-177 lost before reaching target depth
KM-25-178 605.9 607.8 1.8 0.01 2.21 0.57 26.0 0.66 1.93 3.17 5.02 1.44 2.35 3.74
KM-25-178 614.2 632.8 18.6 1.15 1.23 1.40 4.8 0.10 2.49 4.09 6.49 2.13 3.50 5.55
including 623.6 626.5 2.9 0.28 3.29 6.42 7.4 0.50 4.93 8.08 12.82 4.08 6.69 10.61
KM-25-178 685.7 694.0 8.4 1.67 0.65 0.05 6.9 0.02 2.15 3.52 5.58 1.89 3.10 4.92
including 686.9 688.1 1.2 5.08 2.88 0.07 21.6 0.02 7.04 11.54 18.31 6.11 10.01 15.88
KM-25-179 607.2 639.2 32.0 0.94 1.37 4.25 27.2 0.56 3.75 6.14 9.75 3.23 5.29 8.40
including 609.5 611.7 2.3 0.43 5.44 12.10 41.1 0.30 8.79 14.41 22.87 7.30 11.96 18.98
including 619.8 625.9 6.1 0.65 2.73 12.19 35.9 1.86 7.70 12.62 20.03 6.66 10.91 17.32
KM-25-179 664.5 666.0 1.5 6.60 0.14 0.04 4.0 0.04 6.74 11.04 17.52 6.24 10.23 16.23
KM-25-179 687.9 695.6 7.6 0.81 0.13 0.22 9.4 0.05 1.06 1.74 2.75 0.95 1.56 2.47
KM-25-180 657.6 702.1 44.5 0.67 1.68 2.78 18.7 0.12 2.94 4.82 7.66 2.46 4.03 6.39
including 663.2 672.7 9.5 0.43 5.37 7.14 59.2 0.35 7.00 11.47 18.20 5.63 9.22 14.63
including 671.5 672.4 0.9 0.99 18.85 8.20 191.0 1.40 17.47 28.63 45.43 13.24 21.70 34.44
The true width of mineralization is estimated to be 50% to 99% of reported core width, with an average of 76%. (2) Assumptions used in USD for
the copper and gold metal equivalent calculations were metal prices of $4.63/lb Copper, $1937/oz Gold, $25 .20/oz Silver, $1.78/lb Zinc, and
$1.02/lb Pb. Metal Equivalent calculations used assumed metal recoveries, based on a preliminary review of historic data by SRK and ProcessIQ,
were 93% for copper, 92% for zinc, 90% for lead, 72% silver, and 70% for gold. The following equation was used to calculate copper equivalence:
CuEq = Copper (%) (93% rec.) + (Gold (g/t) x 0.61)(70% rec.) + (Silver (g/t) x 0.0079)(72% rec.) + (Zinc (%) x 0.3844)(92% rec.) + (Lead (%) x
0.2203)(90% rec.). The following equation was used to calculate gold equivalence: AuEq = Gold (g/t)(70% rec.) + (Copper (%) x 1.638)(93% rec.)
+ (Silver (g/t) x 0.01291)(72% rec.) + (Zinc (%) x 0.6299)(92% rec.) +(Lead (%) x 0.3609)(90% rec.). Analyzed metal equivalent calculations are
reported for illustrative purposes only. The metal chosen for reporting on an equivalent basis is the one that contributes the most dollar value after
accounting for assumed recoveries.
Figure 1. Oblique section looking northeast, displaying new drill holes reported in this release. See Table 1 for
additional details. The true width of mineralization in this area is yet to be determined. See Table 1 for constituent
elements, grades, metals prices and recovery assumptions used for Au Eq g/t and CuEq % calculations. Analyzed
Metal Equivalent calculations are reported for illustrative purposes only.
About Arizona Metals Corp
Arizona Metals Corp owns 100% of the Kay Project in Yavapai County, which is located on 1669
acres of patented and BLM mining claims and 193 acres of private land that are not subject to any
royalties. An historic estimate by Exxon Minerals in 1982 reported a “proven and probable reserve
of 6.4 million short tons at a grade of 2.2% copper, 2.8 g/t gold, 3.03% zinc, and 55 g/t silver.” The
historic estimate at the Kay Mine Project was reported by Exxon Minerals in 1982. (Fellows, M.L.,
1982, Kay Mine massive sulphide deposit: Internal report prepared for Exxon Minerals Company)
The Kay Project’s historic estimate has not been verified as a current mineral resource. None of
the key assumptions, parameters, and methods used to prepare the historic estimate were reported,
and no resource categories were used. Significant data compilation, re -drilling and data
verification may be required by a Qualified Person before the historic estimate can be verified and
upgraded to be a current mineral resource . A Qualified Person has not done sufficient work to
classify it as a current mineral resource, and Arizona Metals is not treating the historic estimate as
a current mineral resource.
The Kay Project is a steeply dipping VMS deposit that has been defined from a depth of 60 m to
at least 900 m. It is open for expansion on strike and at depth.
The Company also owns 100% of the Sugarloaf Peak Project, in La Paz County, which is located
on 4,400 acres of BLM claims. The Sugarloaf Peak Project is a heap-leach, open-pit target and has a
historic estimate of “100 million tons containing 1.5 million ounces gold” at a grade of 0.5 g/t
(Dausinger, N.E., 1983, Phase 1 Drill Program and Evaluation of Gold-Silver Potential, Sugarloaf
Peak Project, Quartzsite, Arizona: Report for Westworld Inc.)
The historic estimate at the Sugarloaf Peak Project was reported by Westworld Resources in 1983.
The historic estimate has not been verified as a current mineral resource. None of the key
assumptions, parameters, and methods used to prepare the historic estimate were reported, and no
resource categories were used. Significant data compilation, re-drilling and data verification may
be required by a Qualified Person before the historic estimate can be verified and upgraded to a
current mineral resource. A Qualified Person has not done sufficient work to classify it as a current
mineral resource, and Arizona Metals is not treating the historic estimate as a current mineral
resource.
Qualified Person and Quality Assurance/Quality Control
All of Arizona Metals’ drill sample assay results have been independently monitored through a
quality assurance/quality control (“QA/QC”) protocol which includes the insertion of blind
standard reference materials and blanks at regular intervals. Logging and sampling were completed
at Arizona Metals’ core handling facilities located in Phoenix and Black Canyon City, Arizona.
Drill core was diamond sawn on site and half drill-core samples were securely transported to ALS
Laboratories’ (“ALS”) sample preparation facility in Tucson, Arizona. Sample pulps were sent to
ALS’s labs in Vancouver, Canada, and Reno, Nevada, for analysis.
Gold content was determined by fire assay of a 30 -gram charge with ICP finish (ALS method
Au-AA23). Silver and 32 other elements were analyzed by ICP methods with four -acid digestion
(ALS method ME-ICP61a). Over-limit samples for Au, Ag, Cu, and Zn were d etermined by ore-
grade analyses Au-GRA21, Ag-OG62, Cu-OG62, and Zn-OG62, respectively.
ALS Laboratories is independent of Arizona Metals Corp. and its Vancouver and Reno facilities
are ISO 17025 accredited. ALS also performed its own internal QA/QC procedures to assure the
accuracy and integrity of results. Parameters for ALS’ internal and Arizona Metals’ external blind
quality control samples were acceptable for the samples analyzed. Arizona Metals is not aware of
any drilling, sampling, recovery, or other factors that could materially affect the accuracy or
reliability of the data referred to herein.
The qualified person who reviewed and approved the technical disclosure in this release is David
Smith, CPG, a qualified person as defined in National Instrument43-101 – Standards of Disclosure
for Mineral Projects . Mr. Smith supervised the preparation of the scientific and technical
information that forms the basis for this news release and has reviewed and approved the disclosure
herein. Mr. Smith is the Vice -President, Exploration of the Company. Mr. Smith supervised the
drill program and verified the d ata disclosed, including sampling, analytical and QA/QC data,
underlying the technical information in this news release, including reviewing the reports of ALS,
methodologies, results, and all procedures undertaken for quality assurance and quality control in
a manner consistent with industry practice, and all matters were consistent and accurate according
to his professional judgement. There were no limitations on the verification process.
Disclaimer
This press release contains statements that constitute “forward-looking information” (collectively,
“forward-looking statements”) within the meaning of the applicable Canadian securities
legislation. All statements, other than statements of historical fact, are forward-looking statements
and are based on expectations, estimates and projections as at the date of this news release. Any
statement that discusses predictions, expectations, beliefs, plans, projections, objectives,
assumptions, future events or performance (often but not always using phrases such as “expects”,
or “does not expect”, “is expected”, “anticipates” or “does not anticipate”, “plans”, “budget”,
“scheduled”, “forecasts”, “estimates”, “believes” or “intends” or variations of such words and
phrases or stating that certain actions, events or results “may” or “could”, “would”, “might” or
“will” be taken to occur or be achieved) are not statements of historical fact and may be forward-
looking statements. Forward-looking statements contained in this press release include, without
limitation, statements regarding the expansion potential of the Kay Project, statements regarding
drill results and future drilling of the Kay2 Zone and the main Kay deposit, statements regarding
Kay2 Zone mineralization, statements regarding Kay2 Zone mineralization and the contribution
of the Kay2 Zone mineralization to the mineral resource estimate for the Kay deposit, and th e
mineral resource estimate being completed in Q2 2025 or at all. In making the forward- looking
statements contained in this press release, the Company has made certain assumptions. Although
the Company believes that the expectations reflected in forward -looking statements are
reasonable, it can give no assurance that the expectations of any forward-looking statements will
prove to be correct. Known and unknown risks, uncertainties, and other factors which may cause
the actual results and future events to differ materially from those expressed or implied by such
forward-looking statements. Such factors include, but are not limited to: availability of the
Company to stay well funded; delay or failure to receive required permits or regulatory approvals;
and general business, economic, competitive, political and social uncertainties. Accordingly,
readers sh ould not place undue reliance on the forward -looking statements and information
contained in this press release. Exce pt as required by law, the Company disclaims any intention
and assumes no obligation to update or revise any forward -looking statements to reflect actual
results, whether as a result of new information, future events, changes in assumptions, changes in
factors affecting such forward- looking statements or otherwise.
THE TORONTO STOCK EXCHANGE HAS NEITHER REVIEWED NOR ACCEPTS RESPONSIBILITY
FOR THE ADEQUACY OR ACCURACY OF THIS RELEASE
Not for distribution to US newswire services or for release, publication, distribution or dissemination
directly, or indirectly, in whole or in part, in or into the United States
For further information, please contact:
Morgan Knowles
Vice President of Investor Relations
(647) 202-3904
or
Duncan Middlemiss
President and CEO
www.arizonametalscorp.com
https://x.com/ArizonaCorp