Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

AIR.V ·

Clean Air Metals PEA Delivers C$219.4 M pre-tax NPV, 39% IRR for the Thunder Bay North Project

Economic Studies

1

Clean Air Metals PEA Delivers

C$219.4 M pre-tax NPV, 39% IRR

for the Thunder Bay North Project

THUNDER BAY, ON, October 9, 2025 - Clean Air Metals Inc. ("Clean Air

Metals" or the "Company") (TSXV: AIR) (FRA: CKU) (OTCQB: CLRMF) is pleased

to announce results from an independent Preliminary Economic Assessment

(PEA) and updated resource that was completed for its Thunder Bay PGE-Cu-Ni

Project near Thunder Bay, Ontario, Canada. The PEA outlines an 11-year mine

life (+ 2 years of pre-production activities) producing 2,500 tonnes per day from

a near-surface, ramp-access underground operation.

All figures are in Canadian Dollars, unless specified otherwise.

Highlights

• The project has a $219.4M1 pre-tax NPV8 against a project capital cost of $89.5M.

After-tax NPV of $157.5M

• The pre-tax internal rate of return (IRR) is 39%, and the after-tax IRR is 32%

• At spot pricing1, pre-tax NPV8 totals $316M with pre-tax IRR of 52%

• The asset is designed from the ground up as a low-cost, high-margin producer

with access to the first seven months from collaring the ramp portal. The project

maximizes the use of temporary infrastructure and utilizes toll milling at a nearby

facility

• The capital payback is 2.5 years from the start of production through healthy

operating margins of 45%

• Baseline environmental studies are primarily completed to support future

permitting of the project

• The Project is near the City of Thunder Bay, Canada, where key highway and

electrical infrastructure and support are located

• The Company has positive relationships and is working closely with nearby

Indigenous communities to allow full and meaningful participation in the project

• The resource has been updated with additional drilling and new pricing,

highlighting a 14.9M tonne indicated resource grading 2.66 g/t 2PGE2, 0.40%

Cu and 0.24% Ni

• Additionally, there are 2.49M tonnes of inferred resource grading 1.62 g/t

2PGE2, 0.31% Cu and 0.19% Ni. There are no reserves

Notes:

1. Study pricing and Spot pricing are outlined in Table 7

2. 2 PGE = Platinum + Palladium

3. Resource table which shows indicated and inferred material is outlined in Table 9

2

CEO Mike Garbutt P.Eng, MBA stated that "The PEA is a critical step in advancing

the Thunder Bay North Project and more importantly, it adds to the list of

significant critical mineral opportunities in this province and has the potential to

provide long-term economic opportunities for Northwestern Ontario. We intend

to move this project forward and continue exploration efforts on the Escape

down-plunge through a follow-up to the successful resource expansion hole

recently drilled within this area.”

The PEA was independently prepared by Mr. Denis Decharte, P. Eng of SLR, Mr.

Michael Selby, P. Eng of Technica Mining, Mr. Charlie Buck, P. Eng of XPS and

Mrs. Maria Story of Story Environmental, who are considered independent

"Qualified Persons" under National Instrument 43-101 Standards of Disclosure

for Mineral Projects. The technical disclosure in this news release is based upon

the information in the PEA prepared by or under the supervision of Mr.

Decharte, Mr. Selby, Mr. Buck, and Mrs. Story. The Company will file the

complete PEA report on Sedar+ at www.sedarplus.ca within 45 days of this press

release.

Table 1. PEA Summary of Key Project Metrics

Project Metric Units Value

Pre-tax NPV 8% $ M 219.4

After-tax NPV 8% $ M 157.5

Pre-tax IRR % 39

After-tax IRR % 32

Payback period from production

start

years 2.5

Initial CAPEX $ M 89.5

Sustaining CAPEX $ M 162.7

Maximum Production Rate Mtpa 0.91

Mine Life years 11

Total Mill Feed ktonnes 8,705

LOM Feed Grade Pt (g/t) eq1 4.92

Total Revenue (net of royalties) $ M 1,584

Total Operating Costs $ M 874

Pre-Tax Operating Cashflow $ M 453

Net Smelter Return (NSR) $ / tonne feed 189

Operating Margin % 45

3

Operating Costs

Mine Operating Cost $ / tonne feed 66.80

Transportation and Toll-Milling $ / tonne feed 33.60

Total Site Operating $ / tonne feed 100.40

Royalties $ / tonne feed 6.80

Note: Values have been rounded

1. Pt..eq Platinum equivalent are calculated as follows: Pt.eq = (Pt grade/31.1035 x $1425 + Pd grade x 31.1035

x 86.0% x $1,225 + Cu grade x 2204 x 94% x $4.80 + Ni grade x 2204 x 57% x $6.60 + Au grade/31.1035 x

85% x $2,800 + Ag grade/31.1035 x 65% x $30) / $1225

The project cash flows were modelled using a simple discounted cash flow model, with

an 8% discount rate. The project cash flow is scheduled annually and uses an exchange

rate of 1.37 CAD to USD. Taxes were evaluated for federal and provincial corporate tax

rates, as well as the Ontario Mining tax rates, subject to appropriate deductions for CEE,

CDE, and depreciation allowances.

Strategic Intent

The Thunder Bay North project contains several critical minerals and therefore

is ideally positioned to meet the priority goals of both the Federal and Provincial

governments including advancing meaningful economic reconciliation with

several Indigenous communities.

The toll milling scenario contemplated in the Thunder Bay North PEA looks to

take advantage of the significant processing capability in the region, specifically

the Lac-des-Iles (LDI) Mine and Mill situated 65 km north of the Thunder Bay

North project. The recent announcement from Impala Canada about the

pending closure of the LDI mine presents a potential new opportunity. Clean Air

Metals has a significant interest in working through unexplored options to utilize

infrastructure at LDI, up to and including the possible acquisition of the assets

and continued operation LDI with supplementary higher-grade feed from

Thunder Bay North. There can be no certainty that any business arrangement

with Impala Canada can be reached for the processing of ores from the Thunder

Bay North Project.

Path Forward for the Project

Based on the strong initial economics and the current dynamic metals market,

the Board of Clean Air Metals has given management approval to fast-track the

project towards a final production decision. The key steps to reaching this

milestone are as follows:

• Advancing appropriate NI 43-101 studies, engineering, environmental and

permitting activities

• Continued consultation with local Indigenous communities

4

• Exploring all available processing opportunities

• Raising capital to fund the above work

• Begin assembling the construction financing plan, including support from the

federal and provincial governments as well as the private sector

Clean Air Metals Chair Jim Gallagher, P.Eng. stated: "The Board is quite pleased

with the results of the study. The project features high-grade material very close

to the surface with minimal infrastructure requirements, given its proximity to

Thunder Bay. This results in a low-risk, quick-payback project. Recent drill results

demonstrate the continuation of the mineral zones at depth, suggesting the

potential for a significantly longer mine life. Given the very strong government

support for critical mineral projects and the recent improvement in metal prices,

there has never been a better time to move this project forward.”

Capital and Operating Costs Summary

The initial project capital cost is estimated at $89.5M, including a 25%

contingency allowance for all capital items. The duration of the construction

phase of the project is estimated at 24 months. The capital cost estimates are

detailed in Table 2. Operating costs average $100.40 per tonne, driven by

maximizing stope size and efficient operating development designs for near-

surface, underground bulk mining. The operating cost summary is shown in

Table 3.

Table 2: Project and Sustaining Capital Cost Estimates

Category Unit Initial

Project

Sustainin

g

Total

Capital Development $ M 19.8 64.1 83.9

Underground Infrastructure $ M 2.0 19.1 21.1

Mobile Equipment Lease $ M 4.8 72.0 76.8

Sample Tower and Pads $ M 2.3 - 2.3

Access Road / Prep /

Ditching

$ M 3.5 - 3.5

Site Power $ M 3.4 2.3 5.7

Ventilation Fans and

Heating

$ M 2.5 4.5 7.0

Other Surface Infrastructure $ M 9.8 0.7 10.5

Pre-Production Indirect $ M 18.7 - 20.8

Mine Closure $ M 5.0 5.0

Engineering and

Procurement

$ M 4.8 - 4.8

Project Contingency $ M 17.9 - 17.9

5

Table 3: Operating Cost Summary

Category LoM Cost

($M)

Average

($/t prod)

Mine Production 110.0 12.60

Operating Development 61.1 7.00

Haulage 65.7 7.50

Indirect Costs 280.1 32.20

Transportation and

Processing

292.4 33.60

General and Administration 64.5 7.40

Total 874.7 100.40

Note: values have been rounded

Sensitivity

The sensitivity analysis identified that project economics are most sensitive to

changes in operating costs and metal pricing. Results are shown in Tables 4

through 6.

Table 4: Cost Sensitivities for Post-Tax NPV8

Variables

Change Unit Initial Capital Sustaining

Capital

Operating

Cost

20% $ M 144 141 77

10% $ M 151 149 118

5% $ M 154 153 138

-0% $ M 158 158 158

-5% $ M 161 162 177

-10% $ M 164 166 197

-20% $ M 171 174 235

Note: Values have been rounded

Total $ M 89.5 167.7 257.2

Note: Values have been rounded

6

Table 5: Metal Price Sensitivities for Pre-Tax NPV8

Variable

s

Change Unit All

Metals

10% $ M 320

SPOT $ M 316

5% $ M 270

-0% $ M 219

-5% $ M 169

-10% $ M 118

Note: Values have been rounded

Table 6: Metal Payable Sensitivities for Pre-Tax NPV8

Variables

Change Unit Platinum

Payable

Palladium

Payable

Copper

Payable

10% $ M 250 251 246

5% $ M 235 235 233

-0% $ M 219 219 219

-5% $ M 204 204 206

-10% $ M 189 188 193

Note: Values have been rounded

Ramp-up of Market Interest in Platinum and Palladium

The Company is also encouraged by recent market dynamics, particularly with

platinum and palladium pricing. The fundamentals for platinum, in particular,

have been steadily improving, with increased deficits expected to continue for

the next 5-10 years. Key market drivers that are fueling this price recovery

include:

• Despite recent improvements, spot prices for PGEs continue below the marginal

cost of supply for many primary PGE operations worldwide and thus are

operating at a loss. This is resulting in production curtailments worldwide

• A significant volume of the world supply of PGEs originates in Russia and South

Africa, which have aging infrastructure that is prone to disruptions, and have

been generally heavily undercapitalized during this recent downturn

• Supply deficits have existed for 10 of the last 11 years

• Future growth in demand for PGEs will be driven in part by slowing battery

electric vehicle growth, that is taken up by hybrid and plug-in hybrids that have

7

significant PGE loadings. This is further supported by recent US policy changes

regarding EVs

• Recycling has not picked up and is plagued by a lack of interest and investment

• Platinum is increasingly seen as a lower-cost store of value in the face of rising

gold prices

Following nearly four years of a declining outlook for PGEs, the Company

believes that the strong results and timing of this study, in conjunction with

recent exploration success in the Escape down-plunge, provide a solid platform

for the Company to move forward. Table 7 shows the price deck for the study

in comparison to the spot price on October 7th, 2025. Table 8 illustrates the

potential impact on project metrics resulting from the increased interest in the

platinum and palladium markets and associated changes in spot prices.

Table 7: Study Price Deck and Spot Pricing

Metal Unit Study Price1 Spot Price

(October 7, 2025)

Platinum $ US/oz 1425 1629

Palladium $ US/oz 1225 1323

Gold $ US/oz 2800 3692

Silver $ US/oz 30 48.47

Copper $ US/lb 4.80 5.04

Nickel $ US/lb 6.60 7.02

1. Study prices are based on a combination of recent information from various financial institutions and long-term

metal forecasts.

8

Table 8: Impact of Recent Improvement to PGE Markets

Project Metric Study Price

Deck

Spot

(Oct 7, 2025)

Pre-tax NPV - 8% $ M

219 316

After-tax NPV 8% $ M 158 225

Pre-tax IRR % 39 52

After-tax IRR % 32 44

Payback period from production start years 2.5 2.0

Operating Margin % 45 50

Note: subject to rounding

Note on Mineral Reserves, Mineral Resources and PEA

There are no Mineral Reserves for the Thunder Bay North Project currently. The

information reported in the PEA for the Project is preliminary in nature. It

includes Inferred Mineral Resources that are considered too speculative

geologically to have economic considerations applied to them that would

enable them to be categorized as Mineral Reserves. Inferred Mineral Resources

are based on limited geological evidence and sampling. The tonnage and grade

of Inferred Mineral Resources are subject to significant uncertainty regarding

their existence and whether they can be mined economically. There is no

certainty that the results for the PEA for the Project will be realized.

Updated Mineral Resource

The Updated Mineral Resource Estimate was prepared by SLR Consulting Ltd.

("SLR") and is based on an underground constrained resource model using a

Net Smelter Return (NSR) cut-off value of US$46/tonne and consensus metal

pricing.

The Current Deposit contains an Indicated Mineral Resource of 8.8 million

tonnes grading 2.7 g/t 2PGE ("Pt + Pd"), 0.32% copper and 0.22% nickel and

an Inferred Mineral Resource of 1.7 million tonnes grading 1.7 g/tonne 2PGE,

0.32% copper, 0.21% nickel.

The Escape Deposit contains an Indicated Mineral Resource of 6.0 million

tonnes grading 2.6 g/t 2PGE, 0.52% copper, 0.28% nickel and an Inferred

Mineral Resource of 0.8 million tonnes grading 1.4 g/tonne 2PGE, 0.27%

copper, 0.17% nickel.

Summaries of resource grades and contained metals are presented in Tables 9

and 10 below.