Silver Mountain Granted Environmental Impact Assessment (Eia) Permit Extension FOR the Reliquias MINE, Caudalosa MINE and Plant Until 2034
SILVER MOUNTAIN GRANTED ENVIRONMENTAL IMPACT ASSESSMENT
(EIA) PERMIT EXTENSION FOR THE RELIQUIAS MINE, CAUDALOSA MINE
AND PLANT UNTIL 2034
TORONTO
,
June 18, 2024
/CNW/ -
Silver Mountain Resources Inc.
("Silver Mountain" or the "Company") (TSXV: AGMR) (OTCQB: AGMRF) is pleased to
announce that
Peru's
National Authority for Environmental Certification (SENASE) has approved the extension of the main environmental permit (or EIA-d) for its
100% owned Reliquias Mine, Caudalosa Mine and all their components in central
Peru
. This authorization extends the environmental certification for the
Company's future mining operations until 2034.
Alvaro Espinoza
, CEO of Silver Mountain, stated, "
We continue to hit the key milestones for our Reliquias Mine as planned. Extending the Reliquias EIA is part
of the permitting process which will allow us to start operations, certain that the main environmental certification covers the initial years of production and any
resources that may be incorporated through our planned resource expansion programs. Furthermore, the timely approval of this extension confirms that the
Peruvian government is proactively helping advance modern and responsible new mine operations in the country, taking full advantage of high metal prices
and high demand for metals around the world.
"
On Behalf of the Board of Directors of Silver Mountain Resources Inc.
Alvaro Espinoza
, Chief Executive Officer
About Silver Mountain
Silver Mountain Resources Inc. is a silver explorer and mine developer planning to restart production at the Reliquias underground mine and undertake exploration
activities at its prospective silver camps at the Castrovirreyna Project in Huancavelica,
Peru
.
For additional information regarding the Project, please refer to the Company's news release dated
May 15
th
, 2024 (
https://agmr.ca/silver-mountain-delivers-positive-preliminary-economic-assessment-for-its-reliquias-project-peru-pre-tax-npv-5-of-c107-million-pre-tax-irr-of-57-and-payback-of-1-8-years/
). A new technical report is being prepared and will be filed within 45 days of
May 15, 2024
. The current technical report, titled "NI 43-101 Technical Report:
Mineral Resource Update, Reliquias Mine", Huancavelica-
Peru
, dated
March 8, 2024
, effective date
January 1, 2024
, is available at
https://sedarplus.ca
.
For further information about our drill program, including cross sections of the main veins with drill hole locations, please refer to our corporate presentation,
available on our website at
www.agmr.ca
Silver Mountain's subsidiary Sociedad Minera Reliquias S.A.C. owns 100% of its concessions and holds more than 60,000 hectares in the district of
Castrovirreyna, Huancavelica,
Peru
.
Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in policies of the TSX Venture Exchange) accepts responsibility for the
adequacy or accuracy of this release.
Forward Looking Statements
This news release contains forward-looking statements and forward-looking information within the meaning of Canadian securities legislation (collectively,
"
forward-looking statements
") that relate to Silver Mountain's current expectations and views of future events. Any statements that express, or involve
discussions as to, expectations, beliefs, plans, objectives, assumptions or future events or performance (often, but not always, through the use of words or
phrases such as "will likely result", "are expected to", "expects", "will continue", "is anticipated", "anticipates", "believes", "estimated", "intends", "plans", "forecast",
"projection", "strategy", "objective" and "outlook") are not historical facts and may be forward-looking statements and may involve estimates, assumptions and
uncertainties which could cause actual results or outcomes to differ materially from those expressed in such forward-looking statements. No assurance can be
given that these expectations will prove to be correct and such forward-looking statements included in this news release should not be unduly relied upon. These
statements speak only as of the date of this news release.
Forward-looking statements are based on a number of assumptions and are subject to a number of risks and uncertainties, many of which are beyond Silver
Mountain's control, which could cause actual results and events to differ materially from those that are disclosed in or implied by such forward-looking statements.
Such risks and uncertainties include, but are not limited to, the factors set forth under "
Caution Regarding Forward-Looking Statements"
and "
Risk Factors
" in the
Company's Annual Information Form dated
April 26, 2024
, and other disclosure documents available on the Company's profile on SEDAR+ at
www.sedarplus.ca
.
Silver Mountain undertakes no obligation to update or revise any forward-looking statements, whether as a result of new information, future events or otherwise,
except as may be required by law. New factors emerge from time to time, and it is not possible for Silver Mountain to predict all of them or assess the impact of
each such factor or the extent to which any factor, or combination of factors, may cause results to differ materially from those contained in any forward-looking
statement. Any forward-looking statements contained in this news release are expressly qualified in their entirety by this cautionary statement.
SOURCE
Silver Mountain Resources Inc.
View original content to download multimedia:
http://www.newswire.ca/en/releases/archive/June2024/18/c8975.html
%SEDAR: 00052252E
For further information:
For Further Information Contact: Alvaro Espinoza, Chief Executive Officer, Silver Mountain Resources Inc, 82 Richmond Street , East,
Toronto, ON M5C 1P1, +51954 475 319, [email protected], www.agmr.ca
CO: Silver Mountain Resources Inc.
CNW 07:00e 18-JUN-24