HIGHLIGHTS
Casposo Plant refurbishment advancing safely and efficiently across all core workstreams
Crushing Area completed refurbishment with initial unloaded tests underway
Commercial operations on track for start-up in the second half of 2025
Sydney, Australia--(Newsfile Corp. - April 29, 2025) -
Established gold producer Austral Gold
Limited
(ASX: AGD) (TSXV: AGLD) (OTCQB: AGLDF) (
"Austral"
or the
"Company"
) is pleased to
provide an update on the refurbishment of its 100% owned Casposo Plant, as previously announced on
30 December 2024, following the execution of a Toll Agreement with ASX-listed Challenger Gold
Limited.
Austral Gold's Chief Executive Officer, Stabro Kasaneva said:
"We are pleased with the continued
progress on the refurbishment of the Casposo Plant in Argentina. We expect this will enable us to
diversify our revenue streams by bringing our second mine complex into operation alongside our
flagship Chilean operational cluster. We will continue to keep our stakeholders informed and expect to
provide a further update during the second quarter of 2025."
Processing Plant Overview
The Casposo Gold-Silver Processing Plant, which has been in care and maintenance since 2019
following nearly a decade of operations, has traditionally been divided into nine key areas as follows:
Area 100:
Crushing
Area 200:
Grinding, gravitational concentration, thickening, and intensive leaching
Area 300:
Leaching
Area 400:
Counter current decantation and tailings filtration
Area 500:
Clarification and Merrill-Crowe process
Area 600:
Refinery 1-2 and smelting
Area 700:
Cyanide destruction
Area 800:
Reagents 1 and Reagents 2
Area 900:
Water and air supply
The plant has a capacity of 1,300 tonnes per day (tpd), as shown by previous production rates from
operations, covering the full process from crushing to agitation leaching and the Merrill-Crowe
processing stages. Since commencing operations in 2010, the Casposo Plant has processed more
than 530,000 gold equivalent ounces.
Refurbishment Plant Overview
Key activities completed to date as part of the Casposo Plant refurbishment include:
Inspection Phase Finalised:
Completion of the inspection stage to identify procurement needs
and align them with existing warehouse inventory.
Longer Lead items for Plant equipment:
Major equipment dismantled and sent for evaluation
and repair, including leaching tank reducers, mill motor, hydrocyclones, and impeller blades.
Crushing Circuit Works Completed (Area 100):
Mechanical, electrical, and fabrication works
finalised and ready for commissioning.
Leaching Tank Reducers Repaired (Area 300):
100% of leaching tank reducers refurbished
and ready for installation.
Leaching Tank Cleaning Progress (Area 300 and 400):
80% of accumulated solids removed
from leaching tanks.
Thickeners and Counter-Current Decantation (CCD) repaired (Area 400):
Milling thickeners
and counter current decantation systems are repaired and ready for commissioning.
Belt Filter Refurbishment Underway (Area 400):
Sandblasting and painting of belt filters 80%
complete.
Process Water System Ready (Area 900):
Refurbishment of the process water pumping system
completed.
Electrical Cabling Organised (Area 400 and 500):
Reorganisation and cleaning works finalised
in the electrical rooms supporting CCD, Filtration, and Merrill Crowe areas.
Electric Motor Maintenance Advancing:
80% of testing and servicing is completed for the
Plant's electric motors.
Valve Replacement Progress (Area 400):
40% of valves replaced across the CCD and
Filtration areas.
General View of the Crushing Circuit Area (Area 100)
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/690/250255_f028e76714c72b2d_002full.jpg
Main works planned for Q2 2025 include:
Primary crusher refurbishment
SAG mill relining and SAG engine repair
Installation of new hydrocyclones.
Engines and reducers for leaching tanks and CCD's repair
Filter band refurbishment
Modifications and improvement of piping and ducts
The Company also intends to prepare a technical report on the feasibility of processing Casposo's own
mineralised material prior to completing the refurbishment of the Casposo Plant.
About Austral Gold
Austral Gold is a growing gold and silver mining producer building a portfolio of quality assets in the
Americas based on three strategic pillars: production, exploration and equity investments. Austral
continues to lay the foundation for its growth strategy by advancing its attractive portfolio of producing
and exploration assets.
For more information, please visit the Company's website at
www.australgold.com
.
Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the
policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this
release.
Release approved by the Company's Chief Executive Officer of Austral Gold, Stabro Kasaneva.
For additional information please contact:
David Hwang
Jose Bordogna
Joint Company Secretary
Chief Financial Officer and Joint Company
Secretary
Austral Gold Limited
Austral Gold Limited
+61 433 292 290
+61 466 892 307
Forward-Looking Statements
Statements in this announcement that are not historical facts are forward-looking statements. Forward-
looking statements are statements that are not historical, and consist primarily of projections -
statements regarding future plans, expectations and developments. Words such as "expects", "intends",
"plans", "may", "could", "potential", "should", "anticipates", "likely", "believes" and words of similar
import tend to identify forward-looking statements. Forward-looking statements in this announcement
include statements regarding our expectations for the refurbishment of the Casposo Plant in Argentina,
the diversification of our revenue streams, and the operation of our second mine complex alongside our
flagship Chilean operational cluster. Additionally, forward-looking statements include our plans to
provide updates during the second quarter of 2025 and to prepare a technical report on the feasibility of
processing Casposo's own mineralised material, the main works planned for Q2 2025, and our
expectation that we can continue to lay the foundation for our growth strategy by advancing our attractive
portfolio of producing and exploration assets.
All of these forward-looking statements are subject to a variety of known and unknown risks,
uncertainties and other factors that could cause actual events or results to differ from those expressed or
implied, including, without limitation, uncertainty of exploration programs, development plans and cost
estimates, commodity price fluctuations; political or economic instability and regulatory changes;
currency fluctuations, the state of the capital markets, uncertainty in the measurement of mineral
resources and reserves and other risks and hazards related to the exploration of a mineral property, and
the availability of capital and a skilled workforce. You are cautioned that the foregoing list is not
exhaustive of all factors and assumptions which may have been used. Austral cannot assure you that
actual events, performance or results will be consistent with these forward-looking statements, and
management's assumptions may prove to be incorrect. Austral's forward-looking statements reflect
current expectations regarding future events and operating performance and speak only as of the date
hereof and Austral does not assume any obligation to update forward-looking statements if
circumstances or management's beliefs, expectations or opinions should change other than as required
by applicable law. For the reasons set forth above, you should not place undue reliance on forward-
looking statements.
To view the source version of this press release, please visit
https://www.newsfilecorp.com/release/250255