Monday, September 14, 2026
MiningNewsTerminal
Monday, September 14, 2026 Admin

AGLD.V ·

Austral delivered another quarter of operational progress and a stronger balance sheet, with Guanaco production up 17% and unit costs lower following commissioning of additional crushing capacity, toll proc essing at Casposo generating US$5.9 million in fee revenue at

Corporate Updates

1

Austral Gold Limited (ASX:AGD | TSXV: AGLD | OTCQB:AGLDF) (Austral or the Company), which

owns and operates the Casposo (Argentina) and Guanaco (Chile) gold and silver producing mines, is

pleased to provide its Quarterly Activities Report for the three-month period ended 30 June 2026.

Austral delivered another quarter of operational progress and a stronger balance sheet, with

Guanaco production up 17% and unit costs lower following commissioning of additional

crushing capacity, toll proc essing at Casposo generating US$5.9 million in fee revenue at

recoveries above the 85% incentive threshold, exploration advancing in both countries, and

further financial debt reduction alongside a solid cash position of US$20.3 million. Subsequent

to quarter-end, the Company filed an updated Guanaco Technical Report supporting a 14 -year

mine life and US$192.1 million after-tax NPV (10% discount rate). (note 1 on page 2)

Highlights

• Guanaco (Chile): production up 17% quarter-on-quarter to 3,381 gold equivalent ounces (GEO) (Q1

2026: 2,879 GEO), reflecting commissioning of an additional secondary crusher and higher grades

and recoveries. Operating cash cost (C1) and all-in sustaining cost (AISC) decreased 9.6% and

2.6%, respectively, from Q1 2026 to US$2,542/oz and US$2,954/oz.

• Casposo (Argentina): following the commencement of toll processing on 1 May 2026, production

from Company-owned material totalled 932 GEO during April (Q1 2026: 4,456 GEO). During May

and June, an additional 1,651 GEO was produced from 39,342 tonnes of third-party toll material with

GEO recovery rates exceeding 85%. The toll processing counterparty elected not to supply material

in July 2026, and the processing of Company-owned material resumed during the month.

• Combined revenue: US$31.8 million (Q1 2026: US$34.1 million), comprising US$25.9 million from

gold and silver sales (81%) with 5,664 GEO sold at US$4,569/GEO (Q1 2026: US$4,846) and

US$5.9 million (19%) from toll processing (Q1 2026: nil). The decrease reflects lower realised prices

and sales volumes during Casposo's two-month toll processing period, when revenue was generated

from processing fees rather than metal sales.

• Balance sheet: financial debt reduced to US$22.0 million at 30 June 2026, down US$4.6 million

since the 31 December 2025 audited year-end, while cash and cash equivalents increased to

US$20.3 million (31 December 2025: US$10.5 million). Net financial debt was US$1.7 million (31

December 2025: US$16.1 million), and net current assets improved to US$20.8 million (31

December 2025: net current liabilities of US$6.4 million). A further US$2.5 million of related party

debt was repaid in July 2026.

Austral Gold Limited ABN30 075 860 472

ASX: AGD TSXV: AGLD OTCBQ: AGLDF

Quarterly

Activities Report

For the three-month period ended 30 June 2026 (Q2 2026)

www.australgold.com

PRODUCTION | EXPLORATION | EQUITY INVESTMENTS

2

• Updated Guanaco Technical Report: filed subsequent to quarter-end under NI 43-101, extending

life of mine to 14 years (Jan 2026 – Feb 2040) with an after-tax NPV of US$192.1 million (10%

discount rate; LOM gold price US$3,135/oz).¹

PRODUCTION FROM AUSTRAL GOLD MATERIAL

Owned Production (Casposo + Guanaco)

Gold and Silver Revenue

4,313 GEO

US$25.9m

Combined Cash Cost (“C1”) of

US$2,478/oz and all-in-sustaining cost

(“AISC”) of US$2,996/oz *

Sales Volume: 5,664 GEO.

Average selling price of US$4,569/GEO*

Revenue mix: 83% gold | 17% silver

* Weighted average

• Cash flow and capital investment: Sales of 5,664 GEO exceeded production of 4,313 GEO,

reflecting the timing of export shipments at quarter -end. Both operations continued to generate

consistent operating cash flow, with an average cash margin of ~45% (average selling price less C1).

AISC included ongoing sustaining capital. At Guanaco, sustaining capital included the installation of

an additional secondary crusher and continued expansion of the leach pads (strips 5 and 6), with

commissioning expected in August 2026. At Casposo, sustaining capital mainly included plant

equipment purchases, while engineering studies progressed and vendor selection commenced for a

classification plant to support the reprocessing of dry-tailings material.

TOLL PRODUCTION FROM CHALLENGER GOLD MATERIAL

Casposo Tolling (Hualilan Project)

Tolling Fee Revenues

39,342 tonnes

US$5.9m

An average GEO recovery rate of 85.9%

(gold 87.9% | silver 65.1%)

Including variable incentive fee based on

recovery rates

• Toll processing of Challenger Gold's Hualilan ore: during the quarter, Casposo processed 39,342

tonnes of ore from ASX-listed Challenger Gold Limited’s Hualilan Project during May and June. GEO

recovery rates exceeded 85%, resulting in the maximum 30% variable incentive fee under the toll

processing agreement, and generating US$5.9 million in toll processing revenue. Under the

agreement, Challenger Gold was to supply material for up to three months in the first batch cycle ;

however, it elected not to supply material for processing in July . The Company accordingly returned

to processing its own material at Casposo, which it expects to continue pending Challenger Gold's

confirmation of any subsequent batch cycle in accordance with the agreement.

¹ “Technical Report on the Guanaco Mine, An tofagasta Region, Chile” with an effective date of 31 May 2026 is available under the

Company's profile on SEDAR+ at www.sedarplus.ca and on the ASX website at (www.asx.com.au). Austral Gold Limited is not aware of

any new information or data that materially affects the original market announcement.

3

EXPLORATION

• Exploration advanced across both jurisdictions during the quarter, targeting near -mine resource

growth (brownfield) and new discoveries (greenfield) in Chile and Argentina.

• Brownfield exploration at Guanaco (Chile): commenced infill and step -out drilling at Los Nanos,

Dumbo Sur, Dumbo–Defensa and Cerro Estrella near the Guanaco processing facility.

• Brownfield exploration at the Casposo District (Argentina): launched an 8,500m drilling program

(announced on 18 May 2026), initially focused on Casposo Norte, with results expected in early

August 2026. Follow-up drilling is planned at Amanda in Q3 2026.

• Greenfield exploration at Juncal, Guanaco (Chile): channel sampling announced on 22 June

2026 returned significant silver -gold results, with continuous surface mineralisation identified across

seven of eleven mapped veins. Magnetic surveys and geological mapping are complete, supporting

IP surveys in Q3 2026 and a planned maiden drilling campaign in Q4 2026.

• Greenfield exploration at the Casposo District (Argentina): geophysical surveys at Cerro

Amarillo (Manantiales) are scheduled for Q3 2026 to prioritise targets ahead of a plann ed maiden

drilling campaign in Q4 2026.

EQUITY INVESTMENTS

• The Company maintained its holding in ASX -listed Unico Silver Limited ("Unico"), comprising

15.7 million shares valued at US$6.2 million at 30 June 2026 (31 March 2026: US$6.6 million). The

holding remains a liquid asset that provides additional financial flexibility and exposure to the silver

sector.

FINANCIAL POSITION

• Cash and liquidity: cash and cash equivalents

of US$20.3 million as at 30 June 2026 (31 March

2026: US$24.3 million), the movem ent mainly

reflecting debt repayment and capital investment

during the quarter (see cash flow section on page

7). Toll-processing receivables of US$5.9 million

further support near-term liquidity.

• Working capital: net current assets increased to

US$20.8 million as at 30 June 2026, up US$6.4

million in the quarter (31 March 2026: US$14.4

million), continuing a sustained improvement

from net current liabilities of US$6.4 million at 31

December 2025.

• Financial debt: reduced to US$22.0 million as at

30 June 20 26, down US$1.7 million on the

quarter and US$4.6 million since 31 December

2025. Of this, US$10.7 million (49%) was owed

to related parties. Net financial debt was US$1.7

million (debt less cash and cash equivalents).

Subsequent to quarter -end, the Company repaid

US$2.5 million of related party loans.

Financial Position

Summary

(US$ million)

Q2 2026

(June)

Q1 2026

(March)

Q4 2025

(Dec)

Cash & Cash

equivalents

20.3 24.3 10.5

Financial Debt 22.0 23.7 26.6

(Net Financial

Debt) / Net Cash

(1.7) 0.6 (16.1)

Net Current

Assets / (Net

Current

Liabilities)

20.8 14.4 (6.4)

Unico Silver

Investment 6.2 6.6 10.4

4

Q2 2026 Production Overview

Guanaco Operations

Gold and Silver Production Operating Cash Costs (C1)

3,381 GEO US$2,542/oz

17.4% increase from Q1 2026

(2,879 GEO)

16.9% increase from Q2 2025

(2,891 GEO)

9.6% decrease from Q1 2026 (US$2,811)

0.2% decrease from Q2 2025 (US$2,548)

All-In-Sustaining Costs (AISC)

US$2,954/oz

2.6% decrease from Q1 2026 (US$3,034/oz)

7.5% increase from Q2 2025 (US$2,749/oz)

Quarterly Production and Costs

Key Operating Metrics

Q2 2026

(June)

Q1 2026

(March)

Q2 2025

(June)

Milled Ore (t) 68,808 65,327 68,148

Gold (Oz) (2) 3,221 2,707 2,818

Silver (Oz) (2) 9,823 9,780 7,123

GEO (2) (3) 3,381 2,879 2,891

C1 Cost of Production

(US$/GEO) (4) 2,542 2,811 2,548

All-in Sustaining Cost

(US$/GEO) (4) 2,954 3,034 2,749

Gold Selling Price (US$/Oz) 4,491 4,805 3,280

Silver Selling Price (US$/Oz) 74 81 34

(1) Tonnes processed through the agitation leaching process.

(2) Reported production also includes material processed through the heap leaching circuit, with a breakdown provided on page 11

(3) Average Ag:Au ratio was 61.4:1 for Q2 2026, 56.9:1 for Q1 2026 (5); and 97.6:1 Ag:Au for Q2 2025

(4) Composition of the operating cash cost (C1) and all-in sustaining cost (AISC) are provided on page 11

(5) *Reported as 57.0:1 in the Q1 2026 Quarterly Activities Report

5

Casposo Operations

During Q2 2026, the Casposo plant processed the Company's own material for one month (April) and

ore from Challenger Gold's Hualilan Project on a toll basis during May and June.

Quarterly Production from Casposo Material

Key Operating Metrics

Q2 2026

(June) (**)

Q1 2026

(March)

Q2 2025

(June)

Milled Ore (t) (1) 22,135 80,342 (*)

Gold (Oz) 567 2,765 (*)

Silver (Oz) 22,588 97,488 (*)

GEO (2) 932 4,456 (*)

C1 Cost of Production

(US$/GEO) (3)

2,245 1,456 (*)

All-in Sustaining Cost

(US$/GEO) (3)

3,148 1,609 (*)

Gold Selling Price (US$/Oz) 4,651 4,930 (*)

Silver Selling Price (US$/Oz) 77 84 (*)

(1) Tonnes processed through agitation leaching process

(2) Average Ag:Au ratio was 61.9:1 for Q2 2026 and 57.7:1 for Q1 2026

(3) Composition of the cash cost (C1) and All-in Sustaining Cost (AISC) are provided on page 20

(*) Care and maintenance and refurbishment phase of the Casposo plant.

(**) Q2 2026 includes only one month of production.

Quarterly Production from Hualilan Material

Key Operating Metrics

Q2 2026

(June) (*)

Q1 2026

(March)

Q2 2025

(June)

Processed (t) 39,342 (*) (*)

Plant Grade (g/t Au) 1.39 (*) (*)

Plant Grade (g/t Ag) 8.10 (*) (*)

Gold recovery rate (%) 87.9 (*) (*)

Silver recovery rate (%)

65.1 (*) (*)

GEO recovery rate (%) 85.9 (*) (*)

Gold (Oz)

1,543 (*) (*)

Silver (Oz) 6,670 (*) (*)

GEO (Oz) 1,651 (*) (*)

Tolling Fee (US$ million) (1) 5.9 (*) (*)

(1) The Tolling Fee comprises: (i) a Basic Tolling Fee, covering processing costs and G&A; (ii) a Variable Incentive Fee, set as a

percentage of the Basic Tolling Fee based on metallurgical recovery (20% for recovery from 70% to 80%, 25% from +80% to 85%, and

30% above 85%), being the maximum tier, which the Company achieved in Q2 2026; and (iii) a Fixed Monthly Fee.

(*) The first production batch cycle with Hualilan material commenced on 1 May 2026 (Q2 2026).

6

Forecast Calendar Year (CY) 2026 Production and Costs

Guanaco's production guidance remains unchanged, although full -year output is expected to be at the

lower end of the range, reflecting lower than forecast production in Q1 2026 with a gradual improvement

throughout Q2 2026. At Casposo, the Company maintains its initial guidance for production from owned

material, which remains dependent on the timing of the next Hualilan batch cycle under the toll

processing agreement.

Guanaco Mine

• Production: 16,000–20,000 GEO1

• Operating Costs: C1 annual average of US$2,400-2,700/oz and AISC of US$2,600-2,900/oz.

Casposo Mine

• Production: 11,000–13,000 GEO. This guidance has been prepared on the basis that Casposo

would process both Company -owned ore and Hualilan toll material during 2026 for approximately

six months each. Two months of toll processing were completed during the first half of the year.

• Operating Costs: C1 annual average of US$2,200-2,400/oz and AISC of US$2,400-2,600/oz.

1 Notes

• Gold equivalent ounces (GEO), for budgeting purposes, are calculated using a silver-to-gold ratio of 95:1, per the formula AuEq (g/t) = (g/t

Au) + (g/t Ag) ÷ 95, where the factor of 95 reflects assumed metal prices of US$3,800/oz gold and US$40/oz silver.

• Gold and silver are expected to account for 97% and 3% of revenue at Guanaco, and 78% and 22% at Casposo.

• Forecast metallurgical recoveries are 85.0% gold and 50.0% silver at Guanaco, and 90.0% gold and 79.0% silver at Casposo.

• Forecast average head grades are 0.58–0.85 g/t gold and 3.00 g/t silver at Guanaco (heap and agitation leaching circuits, sourced from

heaps 2 and 3), and 1.33–3.86 g/t gold and 50.22–65.68 g/t silver at Casposo.

Casposo Mining Operations

7

Q2 2026 Financials Overview

As at 30 June 2026, the Company ended the quarter with US$20.3 million in cash and cash

equivalents and net financial debt of US$1.7 million (debt less cash and cash equivalents). This

position reflects the improvements achieved in liquidity since the reopening of Casposo in Q4

2025 with t he Company operat ing two cash -generating mining operations (Casposo and

Guanaco). Liquidity was maintained despite continued capital investments in both operations,

including exploration, the repayment of financial debt, and outstanding toll receivables.

Cash Flow

The table below provides a summary of cash flow for the June 2026 quarter, compared to the March 2026

quarter and the corresponding quarter in the prior year ended June 2025.

Cash Flow (US$ million) Q2 2026

(June)

Q1 2026

(March)

Q2 2025

(June)

Operating Cash flow before changes in working capital 12.2 18.9 0.4

Changes in working capital (11.5) (8.5) (0.9)

Operating (deficiency) cash flow after changes in

working capital 0.7 10.4 (0.5)

Net cash (used in) from investing activities (2.4) 1.3 (1.8)

Net cash (used in) from financing activities (2.3) 2.1 (0.3)

Net (decrease) increase in cash (4.0) 13.8 (2.6)

Cash beginning of period 24.3 10.5 3.6

Cash end of period 20.3 24.3 1.0

• Operating cash flow (after working capital movements) totalled US$0.7 million in Q2 2026,

down US$9.7 million from Q1 2026 and up US$1.2 million from Q2 2025. The quarte r-on-quarter

decrease from Q1 2026 primarily reflected lower cash generated during the two -month Hualilan toll

campaign, with the associated tolling fees still outstanding at quarter -end, together with a build -up of

ore inventory as Casposo's open -pit operations continued while the plant processed toll material.

Accordingly, working capital movements mainly comprised increases in receivables and inventory.

• Net cash used in investing activities totalled US$2.4 million during the quarter , primarily

comprising US$2.1 million in capital expenditures on plant and equipment and US$0.3 million

invested in exploration and evaluation activities, partially offset by proceeds of US$0.1 million from the

sale of equipment.

• Net cash used in financing activities totalled US$2.3 million during the quarter, primarily

reflecting repayments of borrowings, interest and lease liabilities.

8

Net Cash Position/ Financial Debt

Net Financial Debt Position (US$ million)(1) Q2 2026

(June)

Q1 2026

(March)

Q2 2025

(June)

Cash & Cash Equivalents 20.3 24.3 1.0

Financial Debt (2) 22.0 23.7 28.5

(Net Financial Debt) / Net Cash (1.7) 0.6 (27.5)

(1) Consolidated unaudited figures

(2) Includes US$0.1 million of financial leases as of 30 June 2026, US$0.2 million as of 31 March 2026, and US$0.7 million

as of 30 June 2025

• Financial debt totalled US$22.0 million as of 30 June 2026, of which US$10.7 million (49%) was

owed to related parties. This represented a decrease of US$1.7 million from 31 March 2026 and a

reduction of US$6.5 million from 30 June 2025.

The decrease in total debt reflects continued debt reduction during the period. Subsequent to the end

of the quarter, the Company repaid overdue related party loans totalling US$2.5 million.

Guanaco Processing Facilities (Chile)