FR Frankfurt – FMV First Majestic Produces 5.5M Silver Eqv. Oz in Q4 2020 (3.5M Silver Oz and 26K Gold Oz); Provides 2021 Outlook and Conference Call Details

Financials

FIRST MAJESTIC SILVER CORP.

Suite 1800 – 925 West Georgia Street

Vancouver, B.C., Canada V6C 3L2

Telephone: (604) 688-3033 Fax: (604) 639-8873

Toll Free: 1-866-529-2807

Web site: www.firstmajestic.com; E-mail: [email protected]

NEWS RELEASE

New York – AG                     January 20, 2021 

Toronto – FR 

Frankfurt – FMV  

First Majestic Produces 5.5M Silver Eqv. Oz in Q4 2020 (3.5M Silver Oz and 26K Gold

Oz); Provides 2021 Outlook and Conference Call Details

Vancouver, BC, Canada ‐ First Majestic Silver Corp. ("First Majestic" or the "Company") is pleased to announce 

the Company’s fourth quarter and full year 2020 production results, as well as production and cost guidance for 

2021.  The  Company’s  fourth  quarter  and  full  year  2020  financial  results  are  scheduled  to  be  released  on 

February 18, 2021.  

Q4 2020 HIGHLIGHTS 

 Total production reached 5.5 million silver equivalent ounces, representing a 5% increase over the prior 

quarter. 

 Silver production reached 3.5 million ounces, representing a 9% increase over the prior quarter and the 

Company’s second highest quarterly silver production. 

 Gold production reached 26,343 ounces, representing a 2% increase from the prior quarter. 

 San Dimas produced 1.9 million ounces of silver and 19,980 ounces of gold, representing an increase of 

16%  and  9%,  respectively,  from  the  prior  quarter  and  the  highest  quarterly  silver  production  since 

acquiring the mine in May 2018.   

 La Encantada produced 1.1 million silver ounces, representing a 12% increase from the prior quarter and 

the highest quarterly production since Q2 2013.   

 At the end of the fourth quarter, 25 exploration drill rigs were active across the Company’s mines and 

projects consisting of 12 rigs at San Dimas, seven rigs at Santa Elena, four rigs at La Encantada and two 

rigs at La Parrilla.  

FY 2020 HIGHLIGHTS 

 Silver production of 11.6 million ounces achieved the top‐end of the Company’s revised guidance range 

of producing between 11.0 to 11.7 million ounces of silver. Strong silver production from La Encantada 

and San Dimas in the second half of 2020 helped to offset some of the production losses resulting from 

the national COVID‐19 shutdowns which occurred in the second quarter of 2020. 

2 

 Gold production in 2020 reached 100,081 ounces and slightly below the Company’s guidance range of 

producing between 106,000 to 112,000 ounces.  The slight miss was primarily due to lower production 

rates at Santa Elena and lower gold grades at San Dimas in the second half of 2020.  

 La Encantada produced 3.5 million silver ounces, representing a 14% increase from the prior year and 

beating  the  Company’s  revised  production  guidance  of  between  3.1  to  3.3  million  silver  ounces.  In 

addition, La Encantada recorded its highest annual silver production since 2014.  

 Achieved record consolidated average silver recoveries of 88%, the highest in the Company’s 18‐year 

history due to the continued success with fine grinding technologies and mill modifications.  

 La Encantada achieved average silver recoveries of 78% in 2020 marking its highest annual recovery rate 

in the Company’s history.   

 Completed  2,292  metres  of  underground  development  at  the  Ermitaño  project  near  Santa  Elena  in 

advance of production ramp up scheduled for early 2022. 

 Construction of the liquid natural gas (“LNG”) facility at Santa Elena was approximately 90% complete at 

year end and remains on schedule to begin commissioning in February 2021 with initial power delivery 

expected in Q2 2021.    

 Completed 156,244 metres of exploration drilling in 2020. 

 Ended the year with record cash and cash equivalents balance of US$238.6 million. 

“First  Majestic  posted  another  strong  year  in  2020  despite  the  many  challenges  brought  on  by  the  COVID‐19 

pandemic and Mexico’s two‐month national shutdown,” said Keith Neumeyer, President & CEO. “Nevertheless, 

our team quickly adapted to the new normal and outperformed in the second half of the year. During the fourth 

quarter, silver production at La Encantada and San Dimas again exceeded our expectations. At La Encantada, 

silver production hit a six year high due to continued improvements in recoveries and underground production 

from the caving areas. San Dimas had a strong close to 2020 by producing 3.5 million silver equivalent ounces in 

the fourth quarter and the highest quarterly silver production while under our ownership.”  

Mr. Neumeyer continues, “In 2021, we expect an increase of up to 20% in consolidated silver production across 

the three operating mines. In addition, our investment in underground development at the Ermitaño project near 

Santa Elena will kick into high gear in order to prepare the area for production ramp up in early 2022. Along with 

a few other projects currently being advanced, we now have a clear path to achieving our goal of producing 30 

million silver equivalent ounces by 2023.”       

FY2020 Mine by Mine Production Table: 

*Certain amounts shown may not add exactly to the total amount due to rounding differences. 

*The following prices were used in the calculation of silver equivalent ounces: Silver: $20.55 per ounce; Gold: $1,770 per ounce.  

Mine

 Ore 

Processed 

 Tonnes 

per Day 

 Ag Grade 

(g/t) 

 Au Grade 

(g/t) 

 Ag 

Recovery  

 Au    

Recovery  

 Ag Oz 

Produced  

 Au Oz 

Produced  

 Equivalent  

Ag Ounces 

San Dimas 713,064      1,954        297           3.24          94% 96% 6,399,667      71,598       12,670,526  

Santa Elena 640,276      1,754        88             1.43          93% 96% 1,692,761      28,242       4,181,708    

La Encantada 860,613      2,358        162           0.01          78% 90% 3,505,953      241            3,526,776    

Total 2,213,953   6,066        184           1.46          88% 96% 11,598,380    100,081     20,379,010  

3 

Production Details Table: 

QUARTERLY REVIEW 

Total ore processed during the quarter at the Company's mines amounted to 625,332 tonnes, representing a 5% 

decrease  compared  to  the  previous  quarter.  The  decrease  in  tonnes  processed  was  primarily  due  to  lower 

production at Santa Elena’s Main Vein partially offset by higher production rates at San Dimas.  

Consolidated silver and gold grades in the quarter averaged 194 g/t and 1.37 g/t, respectively, compared to 170 

g/t and 1.27 g/t, respectively, in the previous quarter. The increase in consolidated grades were primarily due to 

the increased tonnage of higher grade material at San Dimas and La Encantada.     

Consolidated silver and gold recoveries were fairly consistent averaging 89% and 96%, respectively, during the 

quarter. La Encantada continues to achieve higher recoveries as a result of improved blending procedures of 

stockpiles and processing ore with low manganese content.  

Quarterly Mine by Mine Production Table: 

*Certain amounts shown may not add exactly to the total amount due to rounding differences. 

*The following prices were used in the calculation of silver equivalent ounces: Silver: $24.39 per ounce; Gold: $1,874 per ounce.  

At the San Dimas Silver/Gold Mine: 

 San Dimas recorded its highest quarterly silver production under First Majestic’s ownership during the 

fourth  quarter.  The  operation  produced  1,941,286  ounces  of  silver  and  19,980  ounces  of  gold 

representing  an  increase  of  16%  and  9%,  respectively,  compared  to  the  prior  quarter  for  a  total 

production of 3,477,062 silver equivalent ounces.    

 The mill processed a total of 208,648 tonnes with average silver and gold grades of 309 g/t and 3.10 g/t, 

respectively.  

 Silver and gold recoveries during the quarter averaged 94% and 96%, respectively.  

 The Central Block and Sinaloa Graben areas contributed approximately 72% and 24%, respectively, of 

the  total  production  during  the  quarter.  In  addition,  the  Tayoltita  and  El  Cristo  areas  contributed 

approximately 4% of total production in the quarter.   

Q4 Q3 Q/Q FY FY Y/Y

2020 2020 Change Consolidated  Production Results 2020 2019 Change

625,332 655,920 ‐5% Ore  processed/tonnes  milled 2,213,953 2,831,999 ‐22%

5,477,492 5,201,085 5% Total  production ‐ Silver  equivalent  ounces 20,379,010 25,554,288 ‐20%

3,452,959 3,158,866 9% Silver  ounces produced 11,598,380 13,241,118 ‐12%

26,343 25,771 2% Gold  ounces produced 100,081 134,580 ‐26%

Mine

 Ore 

Processed 

 Tonnes 

per Day 

 Ag Grade 

(g/t) 

 Au Grade 

(g/t) 

 Ag 

Recovery  

 Au    

Recovery  

 Ag Oz 

Produced  

 Au Oz 

Produced  

 Equivalent  

Ag Ounces 

San Dimas 208,648      2,268        309           3.10          94% 96% 1,941,286      19,980       3,477,062    

Santa Elena 168,276      1,829        83             1.22          93% 96% 418,153         6,294         901,630       

La Encantada 248,408      2,700        172           0.01          80% 90% 1,093,521      69              1,098,800    

Total 625,332      6,797        194           1.37          89% 96% 3,452,959      26,343       5,477,492    

4 

 A total of 12 drill rigs, consisting of three surface rigs and nine underground rigs, were active at the end 

of the quarter.  

 The Company is expecting to release an updated NI 43‐101 Technical Report on San Dimas by the end of 

the first quarter of 2021. 

At the Santa Elena Silver/Gold Mine: 

 During the quarter, Santa Elena produced 418,153 ounces of silver and 6,294 ounces of gold representing 

a decrease of 17% and 15%, respectively, compared to the prior quarter for a total production of 901,630 

silver equivalent ounces.  

 The  mill  processed  a  total  of  168,276  tonnes,  consisting  of  105,591  tonnes  of  underground  ore  and 

62,685  tonnes  from  the  above  ground  heap  leach  pad.  The  decrease  in  tonnes  was  primarily  due  to 

having limited contractor and equipment availability during the quarter. The Company expects mine and 

plant  production  to  return  to  normal  operating  rates  by  the  second  quarter  of  2021  following 

improvements in underground ore haulage and increased production at the Main, Alejandra Bajo and 

America veins. 

 Silver and gold grades from underground ore averaged 113 g/t and 1.58 g/t, respectively, while silver 

and gold grades from the above ground heap leach pad averaged 33 g/t and 0.61 g/t, respectively.  

 Silver  and  gold  recoveries  averaged  93%  and  96%,  respectively,  during  the  quarter.  The  Company 

continues  to  advance  the  SAG  mill  circuit  conversion  at  Santa  Elena  and  anticipates  the  mill  to  be 

commissioned in the third quarter of 2021. Lower operating costs are expected to be achieved once the 

mill is fully commissioned due to having lower power requirements compared to a standard ball mill as 

well as a reduction in chemical reagents and steel balls.    

 The  LNG  generators  were  successfully  installed  at  Santa  Elena’s  new  LNG  power  facility  during  the 

quarter and the project was approximately 90% complete at year end. Electromechanical activities such 

as the installation of the natural gas pipelines, cooling system, instrumentation and controls, plant safety 

infrastructure and connection of the main electric cables continued throughout the quarter. Dry‐testing 

and commissioning activities are scheduled to start in February. The power generation plant is expected 

to be fully operational in the second quarter after completing the commissioning and ramp‐up period.  

 At  the  Ermitaño  project  near  Santa  Elena,  the  Company  completed  approximately  923  metres  of 

underground development during the quarter. The underground ventilation circuit, which ties together 

the West and East ramps, was completed at the end of November. On surface, the construction of the 

transmission power line and housing for the temporary diesel generators were completed. The diesel 

generators were delivered to site in early January and are currently undergoing installation.      

 A total of seven drill rigs, consisting of five surface rigs and two underground rigs, were active at the end 

of the quarter.  

 The Company is expecting to release an updated NI 43‐101 Technical Report on Santa Elena by the end 

of the first quarter of 2021. 

At the La Encantada Silver Mine: 

 During the quarter, La Encantada processed 248,408 tonnes of ore and produced 1,093,521 ounces of 

silver, or approximately 12% above the previous quarter and the highest quarterly production since Q2 

2013. 

5 

 Silver grades and recoveries during the quarter averaged 172 g/t and 80%, respectively. 

 Strong production from the San Javier and La Prieta caving areas contributed approximately 81% of the 

total  silver  production  during  the  quarter.  Caving  production  benefited  from  higher  than  expected 

grades and tonnage during the quarter.  

 The mill modernization project designed to improve processing efficiencies had some installation delays 

throughout  2020  due  to  the  impacts  caused  by  the  COVID‐19  pandemic.  As  a  result,  the  project  is 

expected  to  continue  into  2021  with  the  installation  of  new  scrubbers  for  the  foundry,  main  gear 

replacement and new impellers for two thickener tanks, filter press upgrades and improvements to the 

electrical control room. 

 A total of four drill rigs, consisting of one surface rig and three underground rigs, were active at the end 

of the quarter.  

 The Company is expecting to release an updated NI 43‐101 Technical Report on La Encantada by the end 

of the first quarter of 2021. 

2021 GUIDANCE 

The Company expects 2021 production from its three operating mines to range between 12.5 to 13.9 million 

ounces of silver and 100,000 to 112,000 ounces of gold for total production (with gold credits converted to silver 

ounces) of between 20.6 to 22.9 million silver equivalent ounces. Based on the midpoint of the guidance range 

the Company expects a 14% increase in silver production and a 7% increase in total production when compared 

to 2020. The increases are primarily due to higher throughputs and silver grades at San Dimas and having a full 

year of production following Mexico’s two month national shutdown in 2020, offset by a lower silver to gold 

ratio which impacts the calculation of conversion to silver equivalent ounces.  

A mine‐by‐mine breakdown of the 2021 production guidance is included in the table below. Effective 2021, the 

Company is adjusting its cost guidance and future reporting to reflect cash costs and all‐in sustaining cost per 

ounce (“AISC”) on a per silver equivalent payable ounces compared to previous disclosure of only silver payable 

ounces. For 2021, the Company is using an 80:1 silver to gold ratio compared to a 100:1 silver to gold ratio in its 

revised  2020  guidance.  Metal  price  and  foreign  currency  assumptions  for  calculating  equivalents  are  silver: 

$22.50/oz, gold: $1,800/oz, MXN:USD 20:1.  

6 

Mine  Silver Oz (M)    Gold Oz (k)  Silver Eqv Oz (M)  Cash Costs per 

AgEq Oz ($) 

AISC per  

AgEq Oz ($) 

San Dimas  7.1 – 8.0  72 – 80  12.9 – 14.4  7.94 – 8.43  11.36 – 12.23 

Santa Elena  2.0 – 2.2  29 – 32  4.3 – 4.8  12.93 – 13.71  16.49 – 17.68 

La Encantada  3.4 – 3.7  –  3.4 – 3.7  11.20 – 11.89  13.72 – 14.70 

Totals:  12.5 – 13.9  100 – 112  20.6 – 22.9  $9.52 – $10.10  $14.81 – $15.99 

* Certain amounts shown may not add exactly to the total amount due to rounding differences. 

 * Cash Costs and AISC are non‐GAAP measures. Consolidated AISC includes Corporate General & Administrative cost estimates and 

non‐cash costs of $1.74 to $1.94 per payable silver equivalent ounce.   The Company calculates consolidated AISC in the manner set 

out in the table below.

The Company is projecting its 2021 AISC to be within a range of $14.81 to $15.99 on a per consolidated payable 

silver equivalent ounce basis. Excluding non‐cash items, the Company anticipates its 2021 AISC to be within a 

range of $14.17 to $15.29 per payable silver equivalent ounce. An itemized AISC cost table is provided below:  

1. AISC  is  a  non‐GAAP  measure  and  is  calculated  based  on  the  Company’s  consolidated  operating 

performance.  Other  mining  companies  may  calculate  AISC  differently  as  a  result  of  differences  in 

underlying  accounting  principles,  the  definition  of  “sustaining  costs”  and  the  distinction  between 

sustaining and expansionary capital costs. 

2. Total  cash  cost  per  payable  silver  equivalent  ounce  includes  estimated  royalties  and  0.5%  mining 

environmental fee of $0.11 per payable silver equivalent ounce. 

Ermitaño Development and Construction Remain Key Focus in 2021  

Since its initial discovery in 2016, the high‐grade Ermitaño project has been a major priority exploration project 

for the Company. Located only four kilometres east of the existing Santa Elena milling facility, the project has the 

potential to add significant mine life to the Santa Elena operation.  

Since 2016, the Company has completed approximately 72,270 metres of diamond drilling on the property to 

define the current Indicated Resource of 4.7 million ounces of silver and 311,000 ounces of gold, or 30.4 million 

silver equivalent ounces grading an average 449 AgEq g/t (70 g/t silver and 4.59 g/t gold). In addition, Inferred 

Resources  totaling  7.0  million  ounces  of  silver  and  370,000  ounces  of  gold,  or  37.5  million  silver  equivalent 

All‐In Sustaining Cost Calculation (1)  FY 2021            

($ /AgEq oz) 

Total Cash Costs per Payable Silver Equivalent Ounce (2)  9.52 – 10.10 

General and Administrative Costs  1.10 – 1.23 

Sustaining Development Costs  1.37 – 1.53 

Sustaining Property, Plant and Equipment Costs  1.04 – 1.16 

Sustaining Exploration Costs  0.02 – 0.03 

Workers Participation Costs  0.74 – 0.82 

Lease Payments  0.37 – 0.42 

Share‐based Payments (non‐cash)  0.52 – 0.58 

Accretion of Reclamation Costs (non‐cash)  0.12 – 0.13 

All‐In Sustaining Costs:    $14.81 – $15.99 

All‐In Sustaining Costs: (excluding non‐cash items)  $14.17 – $15.29 

7 

ounces grading an average 312 AgEq g/t (58 g/t silver and 3.08 g/t gold) have been defined. The Company is 

planning to release a Preliminary Economic Assessment (“PEA”) for Ermitaño with an effective cut‐off date of 

June 30, 2020 and an updated Resource statement, with an effective cut‐off date of December 31, 2020, by the 

end  of  the  first  quarter  of  2021.  Furthermore,  the  Company  is  currently  conducting  hydrogeological  and 

geotechnical drilling which will be used as key study work for an upcoming Pre‐Feasibility Study (“PFS”) on the 

project. The PFS is expected to be released in the second half of 2021 and will define initial Reserves, production 

rates, costs and estimated life of mine for the Ermitaño project. 

In 2021, the Company has budgeted a total of $42.1 million to be invested at Ermitaño and expects to begin 

initial test block mining by mid‐2021 to assess the geotechnical conditions, subject to delineation drilling results, 

and extract approximately 30,000 to 60,000 tonnes of material to be used for industrial metallurgical testing. 

Investment in development will prepare Ermitaño for initial limited mine production in the second half of 2021 

followed by additional stope preparation and ramp up activities in early 2022. Procurement for the underground 

mining fleet is expected to occur in the first half of 2021. In addition, blending and batching test work is expected 

to be completed by mid‐year to determine the ideal processing procedure to apply at the Santa Elena processing 

plant.      

Investing for Future Growth 

In 2021, the Company plans to invest a total of $168.4 million on capital expenditures consisting of $55.7 million 

for sustaining investments and $112.7 million for expansionary projects (including $42.1 million on the Ermitaño 

project). This represents a 28% increase compared to the revised 2020 capital budget and is aligned with the 

Company’s future growth strategy of investments in fine grinding technology, processing plant modernizations 

and to prepare the Ermitaño project for production in early 2022.  

The  2021  annual  budget  includes  total  capital  investments  of  $75.9  million  to  be  spent  on  underground 

development;  $49.8  million  towards  property,  plant  and  equipment;  $27.6  million  in  exploration;  and  $15.1 

million  towards corporate  processing  innovation projects. Management  may revise the  guidance and budget 

during the year to reflect actual and anticipated changes in metal prices or to the business. 

The Company plans to increase underground development in 2021 to approximately 47,000 metres compared 

to 38,504 metres completed in 2020. The 2021 development program consists of approximately 27,800 metres 

at San Dimas; 8,800 metres at Santa Elena; 4,600 metres at La Encantada; and 5,800 metres at the Ermitaño 

project near Santa Elena. This year‐over‐year increase is primarily due to the return to normal operating levels 

following the two‐month national shutdown in the second quarter of 2020 as well as higher development rates 

at Santa Elena following haulage contractor challenges caused by the COVID‐19 pandemic. In addition, higher 

development rates are planned at the Ermitaño project in order to prepare the mine for initial production in 

early 2022.  

The Company also plans to increase exploration drilling in 2021 to approximately 184,150 metres compared to 

156,244 metres completed in 2020. The 2021 drilling program will consist of approximately 104,000 metres  at 

San Dimas with infill and step out holes focusing on near mine and brownfield targets in the West, Central, and 

Tayoltita blocks; 37,600 metres at Santa Elena with near mine, brownfield and greenfield holes continuing to test 

the Main, America and Alejandra veins and new targets north and south of the mine area; 14,550 metres at La 

Encantada with infill and step out holes testing the potential of several near mine and brownfield targets; 13,900 

8 

metres at the Ermitaño project intended to increase resource confidence and add new mineral resources; and 

7,600 metres at Del Toro and 6,500 metres at La Parrilla intended to test new brownfield and greenfield targets 

identified through generative exploration in 2020. 

Mr. Ramon Mendoza Reyes, Vice President Technical Services for First Majestic, is a "Qualified Person" as such 

term is defined under National Instrument 43‐101 and has reviewed and approved the technical information 

disclosed in this news release. 

Conference Call 

The Company will be holding a conference call and webcast today, January 20, 2021 at 8:00 am PT (11:00 am ET) 

to  discuss  the  quarterly  production  results  as  well  as  its  2021  production,  cost  and  capital  guidance.  To 

participate in the conference call, please dial the following: 

Toll Free Canada & USA:   1‐800‐319‐4610 

Outside of Canada & USA:  1‐604‐638‐5340 

Toll Free Germany:   0800 180 1954 

Toll Free UK:   0808 101 2791 

Participants should dial in 10 minutes prior to the conference.  

Click on “January 20, 2021 Webcast Link” on the First Majestic homepage as a simultaneous audio webcast of 

the conference call will be posted at www.firstmajestic.com.

The conference call will be recorded and you can listen to an archive of the conference by calling:  

  Canada & USA Toll Free:   1‐800‐319‐6413 

  Outside Canada & USA:     1‐604‐638‐9010 

  Access Code:        5906 followed by the # sign 

The  replay  will  be  available  approximately  one  hour  after  the  conference  and  will  available  for  seven  days 

following the conference.  The replay will also be available on the Company’s website for one month. 

ABOUT THE COMPANY 

First  Majestic  is  a  publicly  traded  mining  company  focused  on  silver  production  in  Mexico  and  is  aggressively 

pursuing the development of its existing mineral property assets. The Company presently owns and operates the 

San Dimas Silver/Gold Mine, the Santa Elena Silver/Gold Mine and the La Encantada Silver Mine.  Production  from  

these  mines  are  projected  to be between  12.5  to 13.9  million  silver  ounces  or 20.6  to 22.9  million  silver  

equivalent  ounces  in 2021.  