Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

AG.TO ·

FR Frankfurt – FMV First Majestic Produces 6.6 Million Silver Equivalent Ounces in Third Quarter

Resource Estimates

New York – AG                     October 15, 2019 

Toronto – FR 

Frankfurt – FMV  

First Majestic Produces 6.6 Million Silver Equivalent Ounces in Third Quarter

Vancouver,  BC,  Canada  ‐  First  Majestic  Silver  Corp.  ("First  Maj estic"  or  the  "Company")  announces  total 

production in the third quarter of 2019 reached 6.6 million silver equivalent ounces, representing a 4% increase 

compared to the prior quarter. Total production consisted of 3.4 million ounces of silver, 35,791 ounces of gold, 

1.9 million pounds of lead and 1.0 million pounds of zinc. By t he end of the third quarter, total production in 

2019  has  reached  19.3  million  silver  equivalent  ounces,  or  approximately  77%  of  the  Company’s  guidance 

midpoint of producing 24.4 to 26.0 million ounces.   

THIRD QUARTER OPERATIONAL HIGHLIGHTS 

 Record consolidated average silver recoveries of 88%, the highest in the Company’s 17‐year history 

 Record production at Santa Elena of 1,859,170 silver equivalent ounces, up 27% from the prior quarter 

 Five‐year production high at La Encantada of 885,627 silver ounces, up 81% from the prior quarter 

 Achieved average silver recoveries of 82% at La Encantada, the  highest recovery rates in recent history 

at this mine 

 Reached steady state production of the new 3,000 tpd high‐intensity grinding (“HIG”) mill at Santa Elena, 

making it the only hard rock operating HIG mill in Latin America 

 Began initial earthwork activities at Santa Elena’s Ermitaño project for surface facilities and development 

of the underground portal 

“Total production increased 4% quarter over quarter due to higher grades and recoveries at both our Santa Elena 

and  La  Encantada  operations,”  said  Keith  Neumeyer,  President  and  C E O .  “ A t  L a  E n c a n t a d a ,  s i l v e r  r e c o v e r i e s  

a v e r a g e d  8 2 % ,  m a k i n g  i t  t h e  h i g h e s t  r e c o v e r y  r a t e  s i n c e  o w n i n g  this  operation,  following  successful  plant 

modifications  to  optimize  ore  handling  and  processing.  In  addition  to  higher  recoveries,  silver  grades  at  La 

Encantada increased 59% pushing silver production to the highes t level since 2014. Production at Santa Elena 

a l s o  r e a c h e d  a  n e w  r e c o r d  a s  h i g h e r  g o l d  g r a d e s  w e r e  p r o d u c e d  from  the  Main  Vein  and  overall  higher 

metallurgical recoveries were achieved following the start‐up o f the new HIG mill. This new mill is proving to be 

a major asset for this operation and I would like to recognize  our projects and innovations team for a job well 

done.”   

PRODUCTION TABLE 

Q3  Q3  Y/Y  Q2  Q/Q 

2019  2018  Change  2019  Change 

Ore processed/tonnes milled  655,967  864,056  ‐24%  736,896  ‐11% 

Total production ‐ ounces of silver eqv.  6,636,716  6,740,315  ‐2%  6,410,483  4% 

Silver ounces produced  3,367,740  3,505,344  ‐4%  3,193,566  5% 

Gold ounces produced  35,791  35,260  2%  33,576  7% 

Pounds of lead produced  1,907,305  4,443,290  ‐57%  2,452,803  ‐22% 

Pounds of zinc produced  1,026,739  1,234,385  ‐17%  1,398,922  ‐27% 

QUARTERLY REVIEW 

Total ore processed during the quarter at the Company's mines a mounted to 655,967 tonnes, representing an 

11% decrease compared to the previous quarter. The decrease in  tonnes processed was primarily due to the 

c o n t i n u e d  i n a c t i v i t y  a t  S a n  M a r t i n  a n d  a  d e c r e a s e  i n  p r o c e s s e d  ore  at  La  Parrilla  following  the  decision  to 

temporarily  halt  milling  operations  in  order  to  build  adequate  surface  stockpiles  to  be  used  during  t h e  

commissioning phase of the new high‐recovery microbubble flotation cells in early 2020.   

Consolidated silver grades in the quarter averaged 181 g/t compared to 159 g/t in the previous quarter. This 14% 

increase was primarily the result of a higher silver grades at La Encantada, San Dimas, Santa Elena and La Parrilla.  

Consolidated gold grades averaged 1.76 g/t compared to 1.48 g/t in the prior quarter representing a 19% increase 

primarily due to higher gold grades from the Main Vein at Santa Elena.    

C o n s o l i d a t e d  s i l v e r  a n d  g o l d  r e c o v e r i e s  a v e r a g e d  8 8 %  a n d  9 6 % ,  respectively,  during  the  quarter.  Higher 

recoveries were achieved at Santa Elena following the successfu l installation and ramp up of the new 3,000 tpd 

HIG  mill.  In  addition,  La  Encantada  achieved  average  silver  recoveries  of  82%,  representing  a  significant  23% 

increase compared to the prior quarter and the highest recovery  rate in recent history at this mine, following 

several plant optimization modifications.   

MINE BY MINE PRODUCTION TABLE 

*Certain amounts shown may not add exactly to the total amount due to rounding differences. 

*The following prices were used in the calculation of silver eq uivalent ounces: Silver: $16.98 per ounce; Gold: $1,472 per oun ce; Lead: $0.92 per pound; 

Zinc: $1.07 per pound.  

Mine

 Ore 

Processed 

 Tonnes 

per Day 

 Silver Oz 

Produced 

 Gold Oz 

Produced 

 Pounds of 

Lead 

 Pounds of 

Zinc 

 Equivalent 

Silver Ounces 

San Dimas 173,679         1,888            1, 639,481        21,534           ‐                   ‐                    3, 502,102    

Santa Elena 229,094         2,490            632,216             14, 154            ‐                       ‐                    1, 859,170      

La Encantada 191,926         2,086            885,627             65                     ‐                       ‐                    891,205          

La Parrilla 33,439           363               135,420             17                     1, 005,300        1, 026,739     258,683           

Del Toro 27,829           302               74, 997               22                     902,005           ‐                    125,557          

Total 655,967         7,130            3, 367,740         35, 791            1, 907,305        1, 026,739     6,636,716       

At the San Dimas Silver/Gold Mine: 

 During the quarter, San Dimas produced 1,639,481 ounces of silver and 21,534 ounces of gold for a total 

production  of  3,502,102  silver  equivalent  ounces,  reflecting  a  4%  decrease  compared  to  the  prior 

quarter.  

 The mill processed a total of 173,679 tonnes with average silver and gold grades of 315 g/t and 4.00 g/t, 

respectively. Silver grades improved by 1% while gold grades de creased by 7% when compared to the 

prior quarter to a level consistent with budget expectations.      

 Silver and gold recoveries were consistent during the quarter averaging 93% and 97%, respectively. 

At the Santa Elena Silver/Gold Mine: 

 During the quarter, Santa Elena produced 632,216 ounces of silver and 14,154 ounces of gold for a total 

production  of  1,859,170  silver  equivalent  ounces,  reflecting  a  27%  increase  compared  to  the  prior 

quarter. This significant increase was primarily due to higher gold grades from the Main Vein.   

 The  mill processed a total of 229,094 tonnes, consisting of 132 ,437 tonnes (or approximately 58% of 

production)  of  underground  ore  and  96,657  tonnes  (or  approximately  42%  of  production)  from  the 

above ground heap leach pad.  

 Silver and gold grades from underground ore averaged 141 g/t and 3.02 g/t, respectively. Silver and gold 

grades from the above ground heap leach pad averaged 32 g/t and 0.61 g/t, respectively.  

 Silver and gold recoveries averaged 91% and 96%, respectively, during the quarter.  

 The new 3,000 tpd HIG mill reached steady state production duri ng the quarter following a successful 

ramp up. The total project took less than one year to achieve commercial production and is currently the 

only  operating  HIG  mill  processing  fresh  ore  in  Latin  America. Quarterly  average  recovery  rates  are 

expected to increase in the fourth quarter with the mill operating for the full period.   

 Four surface drill rigs were active at the Ermita ño project during the quarter. In addition, above ground 

earthwork  activities  began  to  prepare  the  area  for  the  installa tion  of  surface  facilities  and  portal 

construction.  

 The Company is expected to release a Preliminary Economic Asses sment study and updated Resource 

estimates on the Ermitaño project by the end of the first quarter in 2020.       

At the La Encantada Silver Mine: 

 During the quarter, La Encantada produced 885,627 ounces of silver representing an 81% increase from 

the  previous  quarter  and  the  highest  quarterly  production  in  ove r  f i v e  y e a r s .  T h e  i n c r e a s e  i n  s i l v e r  

production was primarily due to a 59% increase in silver grades and a 23% increase in silver recoveries.  

 Silver recoveries averaged 82% during the quarter, the highest recovery rate since acquiring the mine in 

2006,  due  to  a  revised  throughput  methodology  which  included  selective  stockpiling,  focus  on  finer 

grinding and a change in the management reporting structure of personnel at the processing plant.  

 Silver  grades  during  the  quarter  averaged  176  g/t  compared  to  11 0  g / t  i n  t h e  p r i o r  q u a r t e r .  T h i s  

significant increase was the driven by higher grades from the S an Javier and La Prieta sub‐level caving 

areas which produced 105,405 tonnes with an average silver grade of 228 g/t. 

 A final redesign report from Hatch, an engineering firm, related to the roaster materials handling system 

is expected to be delivered to the Company in the coming weeks. During this design analysis, production 

from the roaster remains suspended until the necessary modifications can be concluded and have been 

completed.  

At the La Parrilla Silver Mine: 

 During the quarter, the flotation circuit processed 33,439 tonnes with an average silver grade of 169 g/t 

and a 75% recovery for total production of 258,683 silver equivalent ounces.  

 The lead circuit processed an average lead grade of 2.1% with recoveries of 64% for total lead production 

of  1.0  million  pounds,  representing  a  41%  decrease  compared  to the  previous  quarter,  due  to  lower 

throughput rates related to the temporary suspension of milling activities in September.  

 The zinc circuit processed an average zinc grade of 2.0% with recoveries of 68% for total zinc production 

of 1.0 million pounds, representing a 27% decrease compared to the previous quarter.  

 The Company continues to review toll milling opportunities from  third party suppliers and is stockpiling 

fresh ore to be used during the commissioning phase of the new  high‐recovery microbubble flotation 

cells in early 2020. The Company is also evaluating methods to produce a new bulk concentrate from Del 

Toro to be shipped to La Parrilla’s microbubble flotation cells for further processing. 

At the Del Toro Silver Mine: 

 During  the  quarter,  Del  Toro  produced  a  total  of  125,557  silver  equivalent  ounces  reflecting  a  2% 

increase compared to the prior quarter primarily due to a 5% increase in tonnes milled, slightly offset by 

a 6% decrease in silver recoveries.  

 Silver grades and recoveries during the quarter averaged 115 g/t and 73%, respectively.  

 Lead grades and recoveries averaged 2.3% and 63%, respectively, producing a total of 0.9 million pounds 

of lead representing a 21% increase compared to the previous quarter.  

At the San Martin Silver Mine: 

 During the quarter, all mining and processing activities at the San Martin operation remained suspended. 

T h e  C o m p a n y  c o n t i n u e s  t o  w o r k  w i t h  a u t h o r i t i e s  t o  s e c u r e  t h e  a re a  i n  a n t i c i p a t i o n  o f  r e s t a r t i n g  t h e  

operation in early 2020. 

Q3 EARNINGS ANNOUNCEMENT 

The Company is planning to release its third quarter 2019 unaudited financial results on Thursday, November 7, 

2019. 

ABOUT THE COMPANY 

First Majestic is a publicly traded mining company focused on s ilver production in Mexico and is aggressively 

pursuing the development of its existing mineral property assets. The Company presently owns and operates the 

San Dimas Silver/Gold Mine, the Santa Elena Silver/Gold Mine, the La Encantada Silver Mine, the La Parrilla Silver 

Mine, the San Martin Silver Mine and the Del Toro Silver Mine. Production from these mines are projected to be 

between 12.8 to 13.5 million silver ounces or 24.4 to 26.0 million silver equivalent ounces in 2019. 

FOR FURTHER INFORMATION contact [email protected], visit our website at www.firstmajestic.com or call 

our toll‐free number 1.866.529.2807. 

FIRST MAJESTIC SILVER CORP.

"signed"

Keith Neumeyer, President & CEO

Cautionary Note Regarding Forward Looking Statements

This  press  release  contains  “forward‐looking  information”  and  " forward‐looking  statements”  under  applicable  Canadian  and  U.S.  securities  laws 

(collectively,  “forward‐looking  statements”).  These  statements  r e l a t e  t o  f u t u r e  e v e n t s  o r  t h e  Company's  future  performance,  business  prospects  or 

opportunities that are based on forecasts of future results, es timates of amounts not yet determinable and assumptions of management made in light of 

management's experience and perception of historical trends, current conditions and expected future developments. Forward‐looking statements include, 

but are not limited to, statements with respect to: that overal l metallurgical recoveries will improve in the fourth quarter o f 2019 following the adoption 

of fine grinding technology; expectations that development activities will commence in the fourth quarter of 2019 with portal excavation for underground 

access; expectations that the Company will receive a formal rec ommendation report from Hatch in  the fourth quarter of 2019 regarding potential design 

improvements to resolve the cooling and material handling issue s encountered with the La Encantada roasters material handling  system; expectations 

that the temporary suspension of the San Martin mine will restart in early 2020; ongoing evaluation of methods to produce a new bulk concentrate at Del 

Toro to be shipped to La Parrilla  and further processed through the microbubble flotation cells t o create separate concentrates of lead and zinc from Del 

Toro; the Company’s business strategy; future planning processes; commercial mining operations; cash flow; budgets; the timing and amount of estimated 

future  production;  recovery  rates;  mine  plans  and  mine  life;  the  future  price  of  silver  and  other  metals;  costs  of  production; c o s t s  a n d  t i m i n g  o f  t h e  

development of new deposits; cap ital projects and  exploration a ctivities and the possible  result s thereof. Assumptions may pro ve to be incorrect and 

actual results may differ materi ally from those anticipated. Co nsequently, guidance cannot be guaranteed. As such, investors a re cautioned not to place 

undue reliance upon guidance and forward‐looking statements as there can be no assurance that the plans, assumptions or expectations upon which they 

are  placed  will  occur.  All  statements  other  than  statements  of historical  fact  may  be  forward‐looking  statements.  Statements  concerning  proven  and 

probable mineral reserves and mi neral resource estimates may also be deemed to constitute forwa rd‐looking statements to the ex tent that they involve 

estimates of the mineralization that will be encountered as and if the property is developed, and in the case of measured and indicated mineral resources 

o r  p r o v e n  a n d  p r o b a b l e  m i n e r a l  r e s e r v e s ,  s u c h  s t a t e m e n t s  r e f l e ct  the  conclusion  based  on  certain  assumptions  that  the  mineral  deposit  can  be 

economically exploited. Any statements that express or involve discussions with respect to predictions, expectations, beliefs, plans, projections, objectives 

or future events or performance  (often, but not always, using w ords or phrases such as “seek”, “ anticipate”, “plan”, “continue ”, “estimate”, “expect”, 

“may”,  “will”,  “project”,  “predict”,  “forecast”,  “potential”,  “target”,  “intend”,  “could”,  “might”,  “should”,  “believe”  and  similar  expressions)  are  not 

statements of historical fact and may be “forward‐looking statements”. 

Actual results may vary from for ward‐looking statements. Forward‐looking statements are subject to known and unknown risks, un certainties and other 

factors that may cause actual results to materially differ from  those expressed or implied by suc h forward‐looking statements,  including but not limited 

to:  risks  related  to  the  integration  of  acquisitions;  actual  results  of  exploration  activities;  conclusions  of  economic  evaluations;  changes  in  project 

parameters as plans continue to be refined; commodity prices; variations in ore reserves, grade or recovery rates; actual performance of plant, equipment 

or  processes  relative  to  specifications  and  expectations;  accidents;  labour  relations;  relations  w i t h  l o c a l  c o m m u n i t i e s ;  c h a n ges  in  national  or  local 

governments; changes in applicable legislation or application t hereof; delays in obtaining approvals or financing or in the co mpletion of development or 

construction activities; exchange rate fluctuations; requirements for additional capital; government regulation; environmental risks; reclamation expenses; 

outcomes of pending litigation; limitations on insurance covera ge as well as those factors discussed in the section entitled " Description of the Business ‐ 

Risk Factors" in the Company's most recent Annual Information Form, available on www.sedar.com, and Form 40‐F on file with the United States Securities 

and Exchange Commission in Washington, D.C.  Although First Majestic has attempted to identify important factors that could cause actual results to differ 

materially  from  those  contained i n  f o r w a r d ‐ l o o k i n g  s t a t e m e n t s ,  there  may  be  other  factors  that  cause  results  not  to  be  as  anticipated,  estimated  or 

intended. 

The  Company  believes  that  the  expectations  reflected  in  these  forward‐looking  statements  are  reasonable,  but  no  assurance  can be  given  that  these 

expectations will prove to be correct and such forward‐looking statements included herein should not be unduly relied upon. These statements speak only 

as of the date hereof. The Company does not intend, and does not assume any obligation, to update these forward‐looking statements, except as required 

by applicable laws.