FR Frankfurt – FMV First Majestic Produces 3.5 Million Silver Equivalent Ounces from Partial Operations in Second Quarter; Updates 2020 Guidance & Announces Conference Call Details

Financials

New York – AG                          July 15, 2020 

Toronto – FR 

Frankfurt – FMV  

First Majestic Produces 3.5 Million Silver Equivalent Ounces from Partial Operations in Second

Quarter; Updates 2020 Guidance & Announces Conference Call Details

Vancouver,  BC,  Canada ‐   First  Majestic  Silver  Corp.  ("First  Majestic"  or  the  "Company")  announces  total 

production in the second quarter of 2020 reached 3.5 million silver equivalent ounces consisting of 1.8 million 

ounces of silver and 15,764 ounces of gold. Quarterly production was impacted following Mexico’s Ministry of 

Health’s Federal Decree requiring  all  non ‐essential  businesses,  including  mining,  to temporarily  suspend  

activities   throughout  most  of  April  and  May  in  response  to  the  global  pandemic.  Despite  having  limited 

operations in the quarter, total production was better than expected due to a slower ramp down at San Dimas 

compared to the other mining units. In the first half of 2020, the Company has produced a total of 9.7 million 

silver equivalent ounces consisting of 5.0 million ounces of silver and 47,967 ounces of gold.  

SECOND QUARTER HIGHLIGHTS 

 Total production reached 3.5 million silver equivalent ounces, consisting of 1.8 million ounces of silver 

and 15,764 ounces of gold. 

 As of June 30, 2020, the Company held 970,000 ounces of silver in inventory in anticipation of realizing 

higher selling prices in the second half of 2020  

 By  quarter  end,  all  operations  have  returned  to  near  full  production  rates  following  the  Mexican 

Government’s decision to allow the Company to restart mining activities on May 23, 2020.  

 San Dimas received delivery of a new 3,000 tpd High Intensity Grinding (“HIG”) mill with additional mill 

modernization components during the quarter.  

 Development activities resumed at Santa Elena’s Ermitaño project in June and successfully intersected 

the Ermitaño vein.  

 Civil construction activities resumed in June on the Liquid Natural Gas (“LNG”) plant at Santa Elena.  The 

LNG generators and storage tanks are estimated to be delivered to site in the third quarter. 

 At the end of the second quarter, 14 exploration drill rigs were active across the Company’s projects 

consisting of 11 rigs at San Dimas, two rigs at Santa Elena and one rig at La Encantada. The Company 

anticipates adding seven additional rigs in the third quarter with a primary focus on the regional potential 

around Santa Elena.  

 Preventative controls such as the practice of social distancing, the cancellation of any non‐essential visits 

to the mines, comprehensive sanitation measures for the workplace and  company transportation, as 

well as pre‐screening for virus symptoms remain in effect. 

“Despite the temporary shutdown of operations during the quarter, our production results were better than 

anticipated as a result of implementing an extended and safe ramp down of the San Dimas operation throughout 

the month of April”, said Keith Neumeyer, President and CEO.  “San Dimas produced a total of 2.4 million silver 

equivalent ounces, or 35% lower than the previous quarter. Total production at the Santa Elena and La Encantada 

operations  were  63%  and  45%  lower,  respectively,  compared  to  the  prior  quarter  as  a  result  of  suspending 

operations in early April.”  

Mr.  Neumeyer  continues,  “We  began  implementing  restart  procedures  in  mid‐May  following  the  Ministry  of 

Health’s announcement that mining activities were now deemed an essential business throughout Mexico.  As 

of today, our operations are back to pre‐pandemic production rates and our focus for the second half of 2020 is 

to try and fully recover the lost ounces due to the shutdown.”  

PRODUCTION TABLE 

Q2  Q2  Y/Y  Q1  Q/Q 

2020  2019  Change  2020  Change 

Ore processed/tonnes milled  333,559  736,896  ‐55%  599,142  ‐44% 

Total production ‐ ounces of silver eqv.  3,505,376  6,410,483  ‐45%  6,195,057  ‐43% 

Silver ounces produced  1,834,575  3,193,566  ‐43%  3,151,980  ‐42% 

Gold ounces produced  15,764  33,576  ‐53%  32,202  ‐51% 

QUARTERLY REVIEW 

Total ore processed during the quarter at the Company's mines amounted to 333,559 tonnes, representing a 

44%  decrease  compared  to  the  previous  quarter.  The  decrease  in  tonnes  processed  compared  to  the  prior 

quarter  was  due  to  Mexico’s  Ministry  of  Health’s  Decree  requiring  non‐essential  businesses  to  temporarily 

suspend activities in response to the global pandemic. 

Consolidated silver grades in the quarter averaged 193 g/t compared to 185 g/t in the previous quarter. This 4% 

increase  was  primarily  the  result  of  higher  grades  at  San  Dimas.  Consolidated  gold  grades  averaged  1.52  g/t 

compared to 1.74 g/t in the prior quarter representing a 12% decrease primarily due to lower gold grades at 

Santa Elena.   

Consolidated silver and gold recoveries were consistent averaging 89% and 96%, respectively, during the quarter. 

MINE BY MINE PRODUCTION TABLE 

*Certain amounts shown may not add exactly to the total amount due to rounding differences. 

*The following prices were used in the calculation of silver equivalent ounces: Silver: $16.37 per ounce, Gold: $1,711 per ounce. 

At the San Dimas Silver/Gold Mine: 

 During the quarter, San Dimas produced 1,102,931 ounces of silver and 12,042 ounces of gold for a total 

production  of  2,395,633  silver  equivalent  ounces,  reflecting  a  35%  decrease  compared  to  the  prior 

quarter due to the COVID‐19 related shutdown.  

 The mill processed a total of 114,390 tonnes with average silver and gold grades of 318 g/t and 3.38 g/t, 

respectively.  

 Silver and gold recoveries were slightly higher during the quarter averaging 94% and 97%, respectively.   

 Initial production from the Tayoltita mine began in June and is expected to ramp‐up to 300 tpd by the 

end of 2020.  

 Mill  modernization  and  optimization  programs  have  resumed  at  San  Dimas,  including  the  mid‐May 

delivery  of  the  3,000  tpd  HIG  mill  and  several  components.  As  a  result  of  the  temporary  suspension 

during the quarter, assembly and installation of the new HIG mill is now expected to be completed in the 

second quarter of 2021.       

 In mid‐June, production was temporarily suspended due to a union work stoppage. Following a two‐ 

week standstill period, the Company and union came to a mutually negotiated bonus agreement at the 

end of June, and at which time production returned to normal operating levels.  

 A total of 11 drill rigs, consisting of one surface rig and 10 underground rigs, were active at the end of 

the quarter. Drilling is currently begin focused in the Central, Sinaloa and Tayoltita blocks.  

At the Santa Elena Silver/Gold Mine: 

 During the quarter, Santa Elena produced 222,100 ounces of silver and 3,677 ounces of gold for a total 

production of 595,651 silver equivalent ounces, or approximately 63% below the previous quarter. 

 The mill processed a total of 89,590 tonnes, consisting of 58,223 tonnes of underground ore and 31,366 

tonnes from the above ground heap leach pad.  

 Silver and gold grades from underground ore averaged 109 g/t and 1.70 g/t, respectively, while silver 

and gold grades from the above ground heap leach pad averaged 32 g/t and 0.62 g/t, respectively.  

 Silver and gold recoveries averaged 92% and 95%, respectively, during the quarter.  

 To  help  minimize  health  risks  and  accommodate  Santa  Elena  workers  that  travel  from  outside 

communities,  the  Company  established  a  temporary  camp  at  Santa  Elena.  In  addition,  a  second 

temporary camp was constructed near Ermitaño to assist with housing of the development contractors 

and construction workers. 

 Development  and  construction  activities  resumed  at  the  Ermitaño  project  in  June  and  successfully 

intersected  the  Ermitaño  vein.  At  the  end  of  the  quarter,  a  total  of  468  metres  of  underground 

Mine

 Ore 

Processed 

 Tonnes 

per Day 

 Ag Grade 

(g/t) 

 Au Grade 

(g/t) 

 Ag 

Recovery 

 Au    

Recovery 

 Ag Oz 

Produced 

 Au Oz 

Produced 

 Equivalent 

Ag Ounces 

San Dimas 114,390         1,257           318              3.38             94% 97% 1,102,931       12,042         2,395,633    

Santa Elena 89,590           985              83                 1.34             92% 95% 222,100          3,677            595,651        

La Encantada 129,579         1,424           158              0.01             78% 90% 509,544          45                  514,092        

Total 333,559         3,665           193              1.52             89% 96% 1,834,575       15,764         3,505,376    

development have been completed and approximately 480 metres of main ramp and 80 metres of lateral 

development remain to be developed in order to access the high‐grade portion of the Ermitaño ore body. 

 The  LNG  power  generation  plant  resumed  civil  construction  activities  in  June.  Delivery  of  the  LNG 

generators and storage tanks are expected to be onsite in the third quarter of 2020. As a result of the 

temporary suspension, the LNG plant is now estimated to be completed and commissioned in the first 

quarter of 2021. 

 Due to the temporary suspension of activities in the quarter, the Ermitaño pre‐feasibility study is now 

expected to be completed in the first half of 2021. In addition, initial production from Ermitaño has been 

extended to mid‐2021.  

At the La Encantada Silver Mine: 

 During  the  quarter,  La  Encantada  processed  129,579  tonnes  of  ore  and  produced  509,544  ounces  of 

silver, or approximately 45% below the previous quarter. 

 Silver grades and recoveries during the quarter averaged 158 g/t and 78%, respectively. 

 Silver recoveries continue to exceed historical rates primarily due to optimal blending of stockpiles and 

maintaining an efficient pumping level on the precipitate tanks. 

OUTLOOK 

The Company is revising its second half and full year 2020 guidance to reflect changes due to the temporary 

suspension of production and sales as well as adjustments to metal price assumptions, foreign exchange rates, 

and the fixed exchange ratio on the San Dimas streaming agreement. Details of the changes and their expected 

impacts are presented below:   

1. Deferred a total of approximately 340,000 tonnes of ore production, consisting of 1.6 million ounces of 

silver and 15,000 ounces of gold, due to the temporary shutdown in the second quarter of 2020  

2. As of June 30, 2020, the Company held 970,000 ounces of silver in inventory in anticipation of realizing 

higher selling prices in the second half of 2020  

3. Increased the gold price assumption to $1,700 per ounce (up from $1,450), reflecting a 100:1 silver to 

gold ratio 

4. Increased the MXN:USD ratio assumption to 21:1 (up from 19:1) 

5. Effective  April  1,  2020,  the  silver  to  gold  fixed  exchange  ratio  related  to  the  San  Dimas  streaming 

agreement with Wheaton Precious Metals was adjusted to 90:1 (from 70:1) due to the silver to gold ratio 

averaging above 90:1 for the previous six months. This ratio adjustment is expected to have a positive 

effect on revenues by approximately $3.0 million for the remainder of 2020, subject to achieving the 

mid‐point of the new production guidance and realizing silver and gold prices per ounce of $17.00 and 

$1,700, respectively.  

As a result of these adjustments, our 2020 total production remains relatively unchanged at 21.4 to 22.9 million 

silver equivalent ounces compared to the prior guidance of 21.5 to 24.0 million silver equivalent ounces. The 

Company is also anticipating a reduction in annualized cash costs of approximately 30% due to the higher gold 

by‐product revenues and the weaker Mexican Peso.  

The Company is also providing guidance below on a mine‐by‐mine basis for the second half of 2020.  Cash cost 

and AISC guidance is shown per payable silver ounce. Assumptions used for calculating silver equivalent ounces 

are: silver: $17.00/oz and gold: $1,700/oz.  

GUIDANCE FOR SECOND HALF OF 2020  

Mine  Silver Oz (M)    Gold Oz (k)  Silver Eqv Oz (M)  Cash Costs ($)  AISC ($) 

San Dimas  3.3 – 3.6  42 – 47  7.5 – 8.3  (0.95) – 0.23  4.72 – 6.55 

Santa Elena  1.1 – 1.2  16 – 18  2.7 – 3.0  2.53 – 3.72  6.75 – 8.43 

La Encantada  1.7 – 1.8  –  1.7 – 1.8  10.86 – 11.56  12.82 – 13.75 

Totals:  6.1 – 6.6  58 – 65  11.9 – 13.1  $2.93 – $3.99  $10.57 – $12.49 

*Certain amounts shown may not add exactly to the total amount due to rounding differences. 

*Consolidated AISC includes general and administrative cost estimates and non‐cash costs of $2.35 to $2.62 per payable silver ounce. 

In the second half of 2020, the Company expects silver production to range between 6.1 to 6.6 million ounces, 

representing  an  increase  of  approximately  27%  when  compared  the  first  half  of  2020.  Additionally,  total 

production is now expected to range between 11.9 to 13.1 million silver equivalent ounces in the second half of 

2020,  representing  an  increase  of  approximately  29%  when  compared  the  first  half  of  2020.  The  increase  in 

production is primarily due to the operations returning to regular production rates in the second half of 2020, as 

well as a higher contribution of gold credits due to an increase in the gold to silver ratio. 

Cash costs in the second half of 2020 are expected to be significantly lower to within the range of $2.93 to $3.99 

per ounce, primarily due to higher gold by‐product credits at San Dimas and Santa Elena and the weaker Mexican 

Peso. In addition, AISC are expected to be within a range of $10.57 to $12.49 per ounce in the second half of 

2020. 

A mine‐by‐mine breakdown of the revised full year 2020 production guidance is included in the table below and 

assumes the same metal prices and foreign currency assumptions as stated previously. 

GUIDANCE FOR FULL YEAR 2020  

Mine  Silver Oz (M)    Gold Oz (k)  Silver Eqv Oz (M)  Cash Costs ($)  AISC ($) 

San Dimas  6.0 – 6.4  75 – 80  13.5 – 14.4  0.75 – 1.49  7.09 – 8.22 

Santa Elena  1.9 – 2.0  31 – 33  4.8 – 5.2  3.60 – 4.38  8.33 – 9.43 

La Encantada  3.1 – 3.3  –  3.1 – 3.3  10.42 – 10.77  12.59 – 13.07 

Totals:  11.0 – 11.7  106 – 113  21.4 – 22.9  $3.95 – $4.59  $12.29 – $13.45 

*Certain amounts shown may not add exactly to the total amount due to rounding differences. 

*Consolidated AISC includes general and administrative cost estimates and non‐cash costs of $2.81 to $2.99 per payable silver ounce. 

For the full year of 2020, the Company now estimates silver production will range between 11.0 to 11.7 million 

ounces  compared the  prior guidance of 11.8 to 13.2 million ounces. Additionally, total  production in 2020 is 

estimated to range between 21.4 to 22.9 million silver equivalent ounces compared to the prior guidance of 21.5 

to 24.0 million silver equivalent ounces.  

Annual cash costs are now expected to be within the range of $3.95 to $4.59 per ounce, or approximately 30% 

below the previous guidance of $5.76 to $6.97 per ounce, primarily due to higher gold by‐product credits at San 

Dimas and Santa Elena and the weaker Mexican Peso. In addition, annual AISC are expected to be within a range 

of  $12.29  to  $13.45  per  ounce,  or  approximately  10%  below  the  previous  guidance  of  $13.37  to  $15.46  per 

ounce. 

REVISED CAPITAL BUDGET 

In an effort to maintain its strong balance sheet, the Company has updated its annual 2020 capital budget to 

include the reallocation of development and exploration expenditures across its operations and investments in 

innovative projects. As a result, the Company now plans to invest a total of $131.8 million, representing a 23% 

decrease compared with previous guidance of $171.5 million, on capital expenditures in 2020 consisting of $45.7 

million of sustaining investments and $86.1 million of expansionary investments.  

The  revised  2020  annual  budget  includes  total  capital  investments  of  $54.0  million  on  underground 

development,  $27.4  million  towards  property,  plant  and  equipment,  $21.4  million  on  exploration  and  $29.0 

million towards automation and efficiency projects. 

In the first half of 2020, the Company completed 15,555 metres of underground development and 50,709 metres 

of  exploration  drilling.  Under  the  revised  2020  budget,  the  Company  is  planning  to  complete  a  total  of 

approximately  35,100  metres  of  underground  development,  representing  a  9%  decrease  compared  to  the 

original guidance. In addition, the Company is now planning to complete a total of approximately 139,000 metres 

of exploration drilling in 2020, representing an 28% decrease compared to the original guidance. 

CONFERENCE CALL 

The Company will be holding a conference call and webcast today, July 15, 2020 at 8 am PST (11 am EST) to 

discuss the quarterly results.   

To participate in the conference call, please dial the following: 

Toll Free Canada & USA:   1‐800‐319‐4610 

Outside of Canada & USA:  1‐604‐638‐5340 

Toll Free Germany:   0800 180 1954 

Toll Free UK:   0808 101 2791 

Participants should dial in 10 minutes prior to the conference.  

Click on WEBCAST on the First Majestic homepage as a simultaneous audio webcast of the conference call will 

be posted at www.firstmajestic.com. 

The conference call will be recorded, and you can listen to an archive of the conference by calling:  

  Canada & USA Toll Free:   1‐800‐319‐6413 

  Outside Canada & USA:     1‐604‐638‐9010 

  Access Code:        4820 followed by the # sign 

The  replay  will  be  available  approximately  one  hour  after  the  conference  and  will  available  for  seven  days 

following the conference.  The replay will also be available on the Company’s website for one month. 

Q2 EARNINGS ANNOUNCEMENT 

The Company is planning to release its second quarter 2020 unaudited financial results on Thursday, August 6, 

2020. 

ABOUT THE COMPANY 

First  Majestic  is  a  publicly  traded  mining  company  focused  on  silver  production  in  Mexico  and  is  aggressively 

pursuing the development of its existing mineral property assets. The Company presently owns and operates the 

San Dimas Silver/Gold Mine, the Santa Elena Silver/Gold Mine and the La Encantada Silver Mine.  Production  from  

these  mines  are  projected  to be between  11.0  to 11.7  million  silver  ounces  or 21.4  to 22.9  million  silver  

equivalent  ounces  in 2020.  

FOR FURTHER INFORMATION contact [email protected], visit our website at www.firstmajestic.com or call 

our toll‐free number 1.866.529.2807. 

FIRST MAJESTIC SILVER CORP.

"signed"

Keith Neumeyer, President & CEO

Cautionary Note Regarding Forward Looking Statements

This press release contains “forward‐looking information” and "forward‐looking statements” under applicable Canadian and U.S. securities laws (collectively, 

“forward‐looking statements”). These statements relate to future events or the Company's future performance, business prospects or opportunities that 

are  based  on  forecasts  of  future  results,  estimates  of  amounts  not  yet  determinable  and  assumptions  of  management  made  in  light  of  management's 

experience and perception of historical trends, current conditions and expected future developments. Forward‐looking statements include, but are not 

limited to, statements with respect to: the Company’s business strategy; future planning processes; commercial mining operations; cash flow; budgets; the 

timing and amount of estimated future production; recovery rates; mine plans and mine life; the future price of silver and other metals; costs of production; 

costs and timing of the development of new deposits; capital projects and exploration activities and the possible results thereof. Assumptions may prove to 

be incorrect and actual results may differ materially from those anticipated. Consequently, guidance cannot be guaranteed. As such, investors are cautioned 

not to place undue reliance upon guidance and forward‐looking statements as there can be no assurance that the plans, assumptions or expectations upon 

which they are placed will occur. All statements other than statements of historical fact may be forward‐looking statements. Statements concerning proven 

and probable mineral reserves and mineral resource estimates may also be deemed to constitute forward‐looking statements to the extent that they involve 

estimates of the mineralization that will be encountered as and if the property is developed, and in the case of measured and indicated mineral resources 

or proven and probable mineral reserves, such statements reflect the conclusion based on certain assumptions that the mineral deposit can be economically 

exploited. Any statements that express or involve discussions with respect to predictions, expectations, beliefs, plans, projections, objectives or future events 

or performance (often, but not always, using words or phrases such as “seek”, “anticipate”, “plan”, “continue”, “estimate”, “expect”, “may”, “will”, “project”, 

“predict”, “forecast”, “potential”, “target”, “intend”, “could”, “might”, “should”, “believe” and similar expressions) are not statements of historical fact and 

may be “forward‐looking statements”. 

Actual results may vary from forward‐looking statements. Forward‐looking statements are subject to known and unknown risks, uncertainties and other 

factors that may cause actual results to materially differ from those expressed or implied by such forward‐looking statements, including but not limited to: 

the duration and effects of the coronavirus and COVID‐19, and any other pandemics on our operations and workforce, and the effects on global economies 

and society, risks related to the integration of acquisitions; actual results of exploration activities; conclusions of economic evaluations; changes in project 

parameters as plans continue to be refined; commodity prices; variations in ore reserves, grade or recovery rates; actual performance of plant, equipment 

or  processes  relative  to  specifications  and  expectations;  accidents;  labour  relations;  relations  with  local  communities;  changes  in  national  or  local 

governments; changes in applicable legislation or application thereof; delays in obtaining approvals or financing or in the completion of development or 

construction activities; exchange rate fluctuations; requirements for additional capital; government regulation; environmental risks; reclamation expenses; 

outcomes of pending litigation; limitations on insurance coverage as well as those factors discussed in the section entitled "Description of the Business ‐ Risk 

Factors" in the Company's most recent Annual Information Form, available on www.sedar.com, and Form 40‐F on file with the United States Securities and 

Exchange Commission in Washington, D.C.  Although First Majestic has attempted to identify important factors that could cause actual results to differ 

materially from those contained in forward‐looking statements, there may be other factors that cause results not to be as anticipated, estimated or intended. 

The  Company  believes  that  the  expectations  reflected  in  these  forward‐looking  statements  are  reasonable,  but  no  assurance  can  be  given  that  these 

expectations will prove to be correct and such forward‐looking statements included herein should not be unduly relied upon. These statements speak only 

as of the date hereof. The Company does not intend, and does not assume any obligation, to update these forward‐looking statements, except as required 

by applicable laws.