Resource Estimates Technical Reports (NI 43-101) Economic Studies

FIRST MAJESTIC SILVER CORP.

Suite 1805 – 925 West Georgia Street Vancouver, B.C., Canada V6C 3L2 Telephone: (604) 688-3033 Fax: (604) 639-8873 Toll Free: 1-866-529-2807 Web site: www.firstmajestic.com; E-mail: [email protected]

NEWS RELEASE

NYSE - AG TSX – FR May 22, 2012 Frankfurt – FMV (WKN: A0LHKJ)

Del Toro NI 43-101 Technical Report & Pre-Feasibility Study

FIRST MAJESTIC SILVER CORP. (AG: NYSE; FR: TSX) (the "Company" or “First Majestic”) is pleased to announce a new NI 43‐101 Technical Report (TR) and Pre‐Feasibility Study (PFS) for the Del Toro Silver Mine.

REPORTED HIGHLIGHTS 

  • Silver Equivalent Measured & Indicated Resources increased by 186% to 74.5 million ounces
  • Silver Equivalent Inferred Resources increased by 79% to 79.0 million ounces
  • Total estimated production to reach 9.7 million silver equivalent ounces in 2014
  • Estimated total operating costs at $34.96 per tonne and cash costs of $7.32 per ounce of silver on a by‐product basis
  • Post Tax NPV at 5% discount = US$147.1 million using a US$25 silver price
  • Internal Rate of Return (IRR) is 43% with a payback period of 2.5 years from completion
  • Life of Mine (LOM) currently estimated at 6.5 years taking into consideration mine dilution from underground mining operations and metallurgical silver recoveries of 77% in Sulfides and 81% in Oxides
  • Total capital requirement over three years of $124.2 million including a 5% contingency
  • The Del Toro Silver Mine is 100% owned by First Majestic Silver and there are no Royalties payable

This new NI 43‐101 TR and PFS considers exploration and development work completed as at the cut‐off date of March 31, 2012.  These estimates include all work completed as at the cut‐off date, including a total of 35,230 metres of diamond drilling over 117 holes and development metres totalling 7,133.  Assays for 33 holes did not make the cut‐off date and were not included in this report.  Seven drill rigs remain actively drilling on site. The new Resource estimates as at the cut‐off consists of 74.5 million ounces of silver equivalent in Measured and Indicated Resources, representing an increase of 186% from the 2008 estimates  plus  an  additional  79.0  million  ounces  contained  in  Inferred  Resources  representing  a  79%  increase  from  the previous estimate.

Construction of the new 4,000 tpd dual circuit processing mill commenced in April 2011. As of today’s date, construction remains on time with first phase of production scheduled to commence in the fourth quarter 2012. Ramp up of production used in the PFS was as follows; Phase 1 ‐ starting in October 2012 through the first half of 2013 includes only sulfide ore processing through the flotation circuit at a capacity of 1,000 tpd; Phase 2 – includes the last half of 2013 through 2017 which includes oxide ore processing through cyanide leaching at a capacity of 2,000 tpd plus sulfide ore processing through flotation at a capacity of 2,000 tpd for total throughput of 4,000 tpd; Phase 3 ‐ Year 2018 includes only 4,000 tpd of sulfide ore though flotation.

Total estimated throughput, described in more detail in the table below, reaches a production level in 2014 of approximately 9.7  million  equivalent  ounces  of  silver  represented  by  6.7  million  ounces  of  pure  silver  annually  plus  approximately  39.4 million pounds of lead and 39.9 million pounds of zinc.  Life of Mine (LOM) calculated in the Report is estimated at 6.5 years taking into consideration mine dilution and metallurgical silver recoveries of 77% in sulfides and 81% in oxides and lead and zinc recoveries from sulfides of 50% and 40%, respectively.

Keith Neumeyer, CEO and President of First Majestic Silver, states: “it should be apparent from the great strides being made with Del Toro that First Majestic is well on its way to achieving its objective of becoming the next senior silver producer.  Our greatest challenge with the Del Toro is keeping ahead of reporting the rapid growth in the underground resources.  As we continue to drill and further define the resources we anticipate it will be necessary to file yet another Technical Report by the end of this year.  When we commission Del Toro later this year, and with the pending acquisition of Silvermex, First Majestic will have five producing mines with annual silver production exceeding ten million ounces and rapidly ramping up to over 15 million  ounces  by  2014.    Our  primary  focus  remains  to  continually  expand  production  while  driving  costs  downward  to maintain  our  status  of  having  our  costs  within  the  first  quartile  amongst  our  mid‐tier  and  senior  peers.    As  always,  my continuing congratulations go out to our entire First Majestic team for its outstanding achievements.”

Total Resources as at the cut‐off date reached a silver equivalent Measured & Indicated Resource of 74.5 million ounces plus an additional silver equivalent Inferred Resources of 79.0 million ounces. More details can be seen in the table below.

The following three summary tables were taken from the complete Del Toro Silver Mine NI 43‐101 TR and PFS prepared by Pincock Allan & Holt, Lakewood, Colorado (PAH). Shareholders and interested parties are encouraged to read this positive report in its entirety which can be viewed on SEDAR (www.sedar.com) and the Company's web site at www.firstmajestic.com.

Mineral Resources “In‐Situ” as of March 31, 2012  

DepositTonnes MWidth mAu g/tAg g/tPb %Zn %Ag (only) ozAg oz eqTotal Ag oz eq
Measured Sulfide Resources1,042,7056.730.00901.663.723,021,9274,448,8167,470,744
Indicated Sulfide Resources5,457,0789.030.111552.553.1227,158,77025,716,43452,875,205
Total Measured + Inidicated Sulfides6,499,7838.660.091442.403.2130,180,69830,165,25160,345,948
Measured Oxide Resources1,111,44110.030.001361.381.744,866,9885264,867,514
Indicated Oxide Resources1,837,75911.540.011561.982.089,222,39524,4219,246,816
Total Measured + Indicated Oxides2,949,20010.970.001491.751.9514,089,38324,94714,114,330
Total Measured + Indicated Sulfides + Oxides9,448,9839.380.061462.202.8244,270,08130,190,19874,460,278
Inferred Sulfide Resources8,617,9658.420.091202.123.8333,233,69542,234,88175,468,576
Inferred Oxide Resources641,1366.490.001732.331.863,573,46403,573,464
Total Inferred Sulfides + Oxides9,259,1018.290.081242.123.8336,807,15942,234,88179,042,040

PAH review = Mineral Resources "In Situ", including mine dilution, but no mine and metallurgical recoveries.

Resource estimate based on Cutoff grade of Ag eqv. = Sulfides 118 g/tonne; Oxides 63 g/tonne. Metal prices: Silver $25/oz, Gold $1600/oz, Lead $0.90/lb, Zinc $0.90/lb.

Due to the uncertainty that may be attached to Inferred Mineral Resources, it cannot be assumed that all or any part of an Inferred Mineral Resource will be upgraded to an Indicated or Measured Mineral Resource as a result of continued exploration.

Inferred Mineral Resources do not have economic value and these have not been included in this TR as part of the economic analysis.

In PAH’s opinion, and as described in the Report, numerous prospective mineralized structures and alteration zones within the Del  Toro  property  holdings  remain  either  under‐explored  or  unexplored  such  as  the  already  know  areas  of  San  Juan, Perseverancia  and  San  Nicolas  and  the  areas  for  future  exploration  such  as  the  extension  to  depth  of  the  Perseverancia chimney, the extension to the Northeast  of the San Nicolas Vein, the newly purchased Dolores mine, in addition to Lourdes, Las Cotorras, La Nueva, India, Tayoltita, El Huitrón, and La Verdiosa structures.

Estimated Capital Expenditures  

CategoryYEARSTOTALS
201220132014
Mine Development Exploration San Francisco Shaft and Mine Equipment Process Plant$5,259,339 $4,000,000 $12,510,000 $32,227,500$3,707,559 $2,000,000 $7,715,000 $44,345,295$1,322,283 $2,000,000$10,289,181 $8,000,000 $20,225,000 $76,572,795
Total Direct Costs$53,996,839$57,767,854$3,322,283$115,086,976
Owner Costs First Fills (Process + Mine)$1,200,000 $500,000$1,000,000$500,000$1,200,000 $2,000,000
Total Indirect Costs$1,700,000$1,000,000$500,000$3,200,000
Subtotal Capital Expenditures$55,696,839$58,767,854$3,822,283$118,286,976
Contingencies @ 5%$2,784,842$2,938,393$191,114$5,914,349
TOTAL CAPITAL EXPENDITURE$58,481,681$61,706,247$4,013,397$124,201,325

Life of Mine Production Schedule 

CATEGORYYEARSTOTALS
20122013201420152016201720182019
Total Sulfide Tonnes Mined/Milled82,000350,000660,000660,000660,000851,3811,234,158131,3754,628,914
Average Head Grades Silver - gpt Lead - % Zinc - % Gold - gpt173 2.71 2.74 0.11178 2.80 2.68 0.09173 2.71 2.74 0.11173 2.71 2.74 0.11179 2.81 2.67 0.09179 2.82 2.66 0.10170 2.65 2.78 0.12167 2.60 2.82 0.13174 2.73 2.72 0.11
Total Oxide Tonnes Mined/Milled240,000660,000660,000660,000468,61985,8422,774,461
Head Grades * Silver - gpt146141141141144140142
Total Sulfide + Oxide Tonnes Mined & Milled82,000590,0001,320,0001,320,0001,320,0001,320,0001,320,000131,3757,403,375
Average Head Grades Silver - gpt Lead - % ** Zinc - % ** Gold - gpt**173 2.71 2.74 0.11165 2.33 2.30 0.06157 2.19 2.31 0.06157 2.19 2.31 0.06160 2.24 2.27 0.05167 2.40 2.36 0.06168 2.59 2.73 0.11167 2.60 2.82 0.13162 2.33 2.40 0.07
Annual Production Silver ounces Pounds of Lead Pounds of Zinc Gold ounces456,214 4,891,963 4,959,313 3113,130,257 21,603,721 20,649,525 1,1196,665,423 39,380,449 39,912,041 2,4126,665,423 39,380,449 39,912,041 2,4126,790,157 40,954,419 38,784,370 1,9677,077,160 52,943,786 49,949,239 2,4637,127,143 72,055,528 75,767,342 4,804706,185 7,525,497 8,169,082 55038,617,962 278,735,812 278,102,953 16,038
TOTAL Equivalent Ounces of Silver Produced829,5114,720,2369,675,3939,675,3939,789,40510,941,69412,756,9801,306,38359,694,995
  • PAH has not reported Pb, Zn grades of oxide ores because no mill recovery of them will be done. San Juan Zinc deposit is not included in the Reserves.

** Average grades for sulfide ore only.

Metal average price assumptions for calculating equivalent ounces: Silver $25.00/oz, Lead $0.90/lb, Zinc $0.90/lb, Gold $1,600/oz

For the purposes of this PFS, Measured and Indicated Resources have been treated as Reserves therefore are inclusive of the estimated  Mineral  Reserves  after  deducting  12%  of  ore  left  in  pillars  and  adding  back  5%  for  mining  dilution,  and  also deducting an ore body of zinc that is in the process of being defined. The result of these changes reduces the Measured and Indicated Resources of 9.4 million tonnes or 74.5 million ounces to 7.4 million tonnes equaling 59.7 million ounces of silver equivalent.

Current Construction Program

Mine and mill production is planned at 4,000 tpd, based on 330 working days per year.  Full production is planned to be about 660,000  tonnes  per  year  of sulfide  ore  and  660,000  tonnes  per year of  oxide  ore. Achievement of  this production  rate  is scheduled for 2014, with a ramp‐up period commencing in late 2012 to early 2014.

The estimated remaining capital costs for 2012 as at March 31, 2012 to bring the Del Toro mine on stream and achieve the Phase 1 production rate of 1,000 tpd is estimated at an additional $47.8 million. To achieve full production at a rate of 4,000 tpd (1,320,000 tonnes per year) total estimated capital is $124.2 million, consisting of $38.5 million for the mine, $76.6 million for the mill facility, $3.2 million indirect cost, and $5.9 million contingency.  Of the $124.2 million of capital investment, about $9.0  million  (without  contingency)  is  budgeted  for  developing  and  equipping  the  main  San  Francisco  Shaft  and  ancillary installations, including an underground crusher station. LOM sustaining capital is estimated at about $17.48 million. Of the $124.2 million budget, $10.7 million has been spent in 2012 up to March 31, 2012.  The remainder of the $124.2 capital expenditure  from  April  1,  2012  onward  is planned  to be  spent  as follows;  $47.8  million  for  the  balance  of  2012,  $61.7  is budgeted for 2013 and the balance of $4.0 is planned on being spent in 2014. It is expected that current cash flows and cash on hand are sufficient to finance this expenditure.

Total operating costs are projected at US$34.97 per tonne for LOM and cash costs of $7.32 per ounce of silver on a by‐product basis including smelting and refining costs. Mine operating costs are estimated at an average of US$19.88 per tonne and mill operating costs are budgeted at US$13.56 per tonne with indirect cost at US$1.56 per tonne.  Mine development is a very small  component  of  the  operating  costs  as  most  Del  Toro  mine  development  will  be  capitalized  over  LOM.    The  mine development, construction of the mill and process plant for both sulfide and oxide ore and construction of ancillary facilities is currently underway. The processing plant is scheduled to initiate operations at a rate of 1,000 tpd by Q4 2012 and ramp up to 4,000 tpd by mid‐2014.

The  Company's  independent  Qualified  Person  under  the  policies  of  National  Instrument  43‐101  who  has  reviewed  the contents of this news release and who is responsible for the preparation of this Technical Report is Leonel López, C.P.G., P.G., who is an employee of Pincock Allen & Holt, and is independent of the Company.

First Majestic is a producing silver company focused on silver production in México and is aggressively pursuing its business plan of becoming a senior silver producer through the development of its existing mineral property assets and the pursuit through acquisition of additional mineral assets which contribute to the Company achieving its aggressive corporate growth objectives.

FOR FURTHER INFORMATION contact [email protected], visit our website at www.firstmajestic.com or call our toll free number 1.866.529.2807.

FIRST MAJESTIC SILVER CORP.

“signed”

Keith Neumeyer, President & CEO

SPECIAL NOTE REGARDING FORWARD‐LOOKING INFORMATION

This news release includes certain "Forward‐Looking Statements" within the meaning of the United States Private Securities Litigation Reform Act of 1995 and applicable Canadian securities laws. When used in this news release, the words “anticipate”, “believe”, “estimate”, “expect”, “target”, “plan”, “forecast”, “may”, “schedule” and similar words or expressions, identify forward‐looking statements or information. These forward‐looking statements or information relate to, among other things: the price of silver and other metals; the accuracy of mineral reserve and resource estimates and estimates of future production and costs of production at our properties; estimated production rates for silver and other payable metals produced by us, the estimated cost of development of our development projects; the effects of laws, regulations and government policies on our operations, including, without limitation, the laws in Mexico which  currently  have  significant  restrictions  related  to  mining;  obtaining  or  maintaining  necessary  permits,  licences  and  approvals  from  government authorities; and continued access to necessary infrastructure, including, without limitation, access to power, land, water and roads to carry on activities as planned.

These statements reflect the Company’s current views with respect to future events and are necessarily based upon a number of assumptions and estimates that, while considered reasonable by the Company, are inherently subject to significant business, economic, competitive, political and social uncertainties and contingencies. Many factors, both known and unknown, could cause actual results, performance or achievements to be materially different from the results, performance or achievements that are or  may be expressed or implied by such forward‐looking statements or information and the Company has made assumptions and estimates based on or related to many of these factors. Such factors include, without limitation: fluctuations in the spot and forward price of silver, gold, base metals or certain other commodities (such as natural gas, fuel oil and electricity); fluctuations in the currency markets (such as the Canadian dollar and Mexican peso versus the U.S. dollar); changes in national and local government, legislation, taxation, controls, regulations and political or economic developments in Canada, Mexico; operating or technical difficulties in connection with mining or development activities; risks and hazards associated with the business  of  mineral  exploration,  development  and  mining  (including  environmental  hazards,  industrial  accidents,  unusual  or  unexpected  formations, pressures, cave‐ins and flooding); risks relating to the credit worthiness or financial condition of suppliers, refiners and other parties with whom the Company does business; inability to obtain adequate insurance to cover risks and hazards; and the presence of laws and regulations that may impose restrictions on mining, including those currently enacted in Mexico; employee relations; relationships with and claims by local communities and indigenous populations; availability and increasing costs associated with mining inputs and labour; the speculative nature of mineral exploration and development, including the risks of obtaining necessary licenses, permits and approvals from government authorities; diminishing quantities or grades of mineral reserves as properties are mined; the Company’s title to properties; and the factors identified under the caption “Risk Factors” in the Company’s Annual Information Form, under the caption “Risks Relating to First Majestic's Business”.

Investors are cautioned against attributing undue certainty to forward‐looking statements or information. Although the Company has attempted to identify important  factors  that  could  cause  actual  results  to  differ  materially,  there  may  be  other  factors  that  cause  results  not  to  be  anticipated,  estimated  or intended. The Company does not intend, and does not assume any obligation, to update these forward‐looking statements or information to reflect changes in assumptions or changes in circumstances or any other events affecting such statements or information, other than as required by applicable law.