ALASKA ENERGY METALS PROVIDES UPDATE ON FIELD

WORK IN SUPPORT OF ACCESS INFRASTRUCTURE PERMITS

AT THE NIKOLAI NICKEL PROJECT, ALASKA

CEO: “The access infrastructure improvements are expected to materially reduce

exploration costs, improve operational efficiency and safety, and accelerate the timelines

for advanced exploration and development of one of the most significant domestic critical

mineral resources in the United States”

HIGHLIGHTS

• Under the US federal FAST-41 transparency dashboard permitting program, AEMC is

seeking permits to upgrade and extend the existing Rainy Creek Mining Trail, a

gravel trail that leads westward 25 kilometers from the paved Richardson Hwy to

the Company’s Eureka nickel-rich, multi-critical, polymetallic deposit.

• Field work in support of the permitting effort will be done by AEMC contractors in

late July and August 2026.

• Studies will include a cultural resources survey and additional wetland delineation

work along the proposed access corridor.

• Permitting activities continue under the schedule established by the federal FAST-41

program, with ongoing coordination amongst federal and state agencies on track.

• Permitting decisions are expected in late Fall 2026.

• Ground access to the Eureka deposit will significantly reduce future exploration costs,

increase safety and accelerate timelines for advanced exploration and future project

development.

• Construction activities could begin as early as winter 2026/2027, depending on

permitting and field conditions.

VANCOUVER, BRITISH COLUMBIA, July 23, 2026 – Alaska Energy Metals Corporation (TSX-

V: AEMC, OTCQB: AKEMF) (“AEMC” or the “Company”) is pleased to provide an update on

permitting and related field activities supporting the proposed rehabilitation and extension

ALASKA ENERGY METALS CORP. | Suite 300 – 1055 West Hastings St. | Vancouver, BC V6E 2E9

Direct: 604 609 7149 | Toll-Free: 877 217 8978 | www.alaskaenergymetals.com

Field work in support of permit

Page 2

LEGAL_48538203.1

of the existing Rainy Creek Mining Trail and associated infrastructure at its Nikolai Nickel

Project, Alaska.

The Nikolai Nickel Project was accepted for coverage under the Federal Permitting

Improvement Steering Council's (“Permitting Council” or “Council”) FAST-41 transparency

dashboard (“Dashboard”) program in November 2025. The FAST-41 listing is intended to

improve transparency and coordination amongst federal agencies and establish clear

timelines for the environmental review and permitting process associated with the

proposed access infrastructure.

During the summer of 2026, AEMC is required to complete field surveys along the

proposed access corridor, including a cultural resources survey and supplemental wetland

delineation work. These studies will provide important information to support the federal

and state permitting efforts. The Company currently anticipates that permits required for

the proposed road upgrade and extension, temporary bridge installations and camp

infrastructure could be issued in late 2026, subject to agency review schedules and

completion of all necessary studies and consultations.

Upon receipt of the required permits, and subject to weather conditions and contractor

availability, construction activities could commence as early as winter 2026/2027.

AEMC CEO Gregory Beischer commented: "The permitting and baseline work being

completed this year represents another important step toward establishing reliable ground

access to the Eureka deposit. The access infrastructure improvements are expected to materially

reduce exploration costs, improve operational efficiency and safety, and accelerate the timelines

for advanced exploration and development of one of the most significant domestic critical

mineral resources in the United States. We appreciate the continued cooperation and

coordination of the state and federal agencies participating in the FAST-41 process."

The Eureka deposit of the Nikolai Project is situated approximately 80 kilometers (60 miles)

south of the town of Delta Junction and 32 kilometers (20 miles) west of the Richardson

Highway. The Rainy Creek Mining Trail leads from the Richardson Highway to present and

past-producing alluvial gold mines at Rainy Creek and Broxson Gulch. AEMC proposes to

rehabilitate the existing roadway, parts of which were initially laid down more than a

ALASKA ENERGY METALS CORP. | Suite 300 – 1055 West Hastings St. | Vancouver, BC V6E 2E9

Direct: 604 609 7149 | Toll-Free: 877 217 8978 | www.alaskaenergymetals.com

Field work in support of permit

Page 3

LEGAL_48538203.1

century ago, and extend it approximately 8 kilometers (6 miles) from Broxson Gulch

southward to the Eureka deposit.

The proposed access improvements are expected to facilitate advanced exploration and

future development of the Eureka deposit, which hosts multiple critical minerals, including

nickel, copper, cobalt, chromium, platinum and palladium, as well as iron. Through drilling

done to date, the Company has established the Eureka deposit as a large nickel resource

(2025 Mineral Resource Estimate (“MRE”) containing 5.605 billion pounds of in-situ nickel in

the Indicated Resource Category and 9.384 biillon pounds of in-situ nickel in the Inferred

Resource Category (1,190 million tonnes grading 0.21% nickel and 2.087 million tonnes

grading 0.20% nickel respectively). See official MRE at this link. The Company believes,

based on its own research, that Eureka is the largest known nickel resource in the United

States and a therefore a strategically important domestic source of critical minerals

essential to the national economy and national defense. Cautionary Note: The Company

has done research to document other large nickel resources in the US. Because it is

relatively recent news, AEMC’s 2025 MRE for the Nikolai project does not yet appear

in publications of the United States Geological Survey in which nickel resources are

ranked. The Company’s research shows that the Nikolai project has the largest

known nickel resource in the US by a substantial margin but presently cannot point

to an official source to confirm this contention.

FAST-41 Permitting. In November 2025 AEMC’s Nikolai Nickel project was accepted for

coverage under the FAST-41 Transparency Dashboard by the Federal Permitting

Improvement Steering Council. An Environmental Assessment (“EA”) is to be completed by

the agencies with US Army Corp of Engineers (“USACE” or “Corps”) as the lead coordinating

agency. The Transparency Dashboard listing is intended to focus initially on infrastructure

improvements supporting Nikolai, beginning with the rehabilitation and extension of the

existing Rainy Creek Mining Trail, including installation of two temporary bridges, and an

on-site camp.

Subsequent to the listing, the USACE determined that a Section 404 Clean Water Permit

would be required following an Environmental Assessment. The Bureau of Land

Management (“BLM”) was also identified as the US federal agency that would have

responsibility to review the project and if appropriate, to grant a Right of Way (“ROW”).

ALASKA ENERGY METALS CORP. | Suite 300 – 1055 West Hastings St. | Vancouver, BC V6E 2E9

Direct: 604 609 7149 | Toll-Free: 877 217 8978 | www.alaskaenergymetals.com

Field work in support of permit

Page 4

LEGAL_48538203.1

That ROW application has been filed and accepted by the BLM Field Office in Glennallen,

Alaska. In accordance with the Fast-41 process, a schedule was determined amongst the

Permitting Council, USACE and BLM and published on the Dashboard. Public comments for

the road project were solicited by USACE. The comment period closed on February 27,

2026. AEMC is scheduled to carry out wetlands mapping and an archaeological survey in

summer 2026. USACE and BLM are subsequently scheduled to complete their review by

late August 2026.

While not part of the FAST-41 permitting process, State of Alaska agencies also have

regulatory authority and must provide consultation and input in order for the federal

agencies to issue permits. AEMC is working with the State’s Large Mine Permitting Team

within the Office of Project Management and Permitting (“OPMP”) for authorizations and

permits that are to be issued by the State. Late last year, OPMP and the Governor of Alaska

signed a Memorandum of Understanding with the Permitting Council to maximize

coordination between State regulatory agencies and the federal Fast-41 program to reduce

permitting timelines.

QUALIFIED PERSON

Gregory Beischer, the Company’s President & CEO, is the qualified person, as defined

under National Instrument 43-101 Standards of Disclosure for Mineral Projects,

responsible for, and having reviewed and approved, the technical information contained in

this news release.

For additional information, visit: https://alaskaenergymetals.com/

ABOUT ALASKA ENERGY METALS

Alaska Energy Metals Corporation (AEMC) is an Alaska -based corporation with offices in

Anchorage and Vancouver working to sustainably deliver the critical materials needed for

U.S. national security and a bright energy future, all while generating superior returns for

shareholders.

AEMC is focused on delineating and developing the large -scale, bulk tonnage, polymetallic

Nikolai Project and related Eureka deposit containing nickel, copper, cobalt, chromium, iron,

platinum, palladium, and gold. Located in Interior Alaska near existing transportation and

ALASKA ENERGY METALS CORP. | Suite 300 – 1055 West Hastings St. | Vancouver, BC V6E 2E9

Direct: 604 609 7149 | Toll-Free: 877 217 8978 | www.alaskaenergymetals.com

Field work in support of permit

Page 5

LEGAL_48538203.1

power infrastructure, its flagship project, Nikolai, is well -situated to become a significant

domestic source of strategic metals for North America. In January 2026, AEMC’s Nikolai

Project was accepted for Fast -41 Transparency Dashboard listing to streamline federal

permitting for overland access and man camp placement for the next phase of Eureka

deposit drilling. AEMC also holds a secondary project in western Quebec; the Angliers –

Belleterre project. Today, material sourcing demands excellence in environmental

performance, technological innovation, carbon mitigation and the responsible management

of human and financial capital. AEMC works every day to earn and maintain the respect and

confidence of the public and believes that environmental, social and governance

performance is measured by action and led from the top.

ON BEHALF OF THE BOARD

“Gregory Beischer”

Gregory Beischer, President & CEO

FOR FURTHER INFORMATION, PLEASE CONTACT:

Gregory A. Beischer, President & CEO

Toll-Free: 877-217-8978 | Local: 604-609-7149

Some statements in this news release may contain forward -looking information (within the

meaning of Canadian securities legislation) , including but not limited to: field work supporting

permitting activities, grant of permits, and road construction and upgrade, temporary bridge

installment, and further development activity . These statements address future events and

conditions and, as such, involve known and unknown risks, uncertainties, and other factors which

may cause the actual results, performance, or achievements to be materially different from any

future results, performance, or achievements expressed or implied by the statements. Forward -

looking statements speak only as of the date those statements are made. Although the Company

believes the expectations expressed in such forward-looking statements are based on reasonable

assumptions, such statements do not guarantee future performance and actual results may differ

materially from those in the forward -looking statements. Factors that could cause the actual

results to differ materially from those in forward-looking statements include but are not limited to

uncertainty relating to the estimation of mineral resources, regulatory actions, market prices, and

continued availability of capital and financing, and general economic, market or business

conditions. Investors are cautioned that any such statements are not guarantees of future

ALASKA ENERGY METALS CORP. | Suite 300 – 1055 West Hastings St. | Vancouver, BC V6E 2E9

Direct: 604 609 7149 | Toll-Free: 877 217 8978 | www.alaskaenergymetals.com

Field work in support of permit

Page 6

LEGAL_48538203.1

performance and actual results or developments may differ materially from those projected in the

forward-looking statements. Forward-looking statements are based on the beliefs, estimates and

opinions of the Company's management on the date the statements are made. Except as required

by applicable law, the Company assumes no obligation to update or to publicly announce the

results of any change to any forward -looking statement contained or incorporated by reference

herein to reflect actual results, future events or developments, changes in assumptions, or changes

in other factors affecting the forward -looking statements. If the Company updates any forward -

looking statement(s), no inference should be drawn that it will make additional updates with

respect to those or other forward-looking statements.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is

defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy

or accuracy of this press release.