Monday, September 14, 2026
MiningNewsTerminal
Monday, September 14, 2026 Admin

ABA.V ·

Abasca Announces Positive Preliminary Economic Assessment for the Loki Flake Graphite Deposit: After-Tax NPV of US$130 Million and 16.7% IRR Study projects Loki Flake Graphite Deposit as a long-life graphite development project with positive economics; project to

Economic Studies Mergers & Acquisitions

On Wednesday, August 19, 2026 at 7:00AM ET

Abasca Announces Positive Preliminary Economic

Assessment for the Loki Flake Graphite Deposit: After-Tax

NPV of US$130 Million and 16.7% IRR

Study projects Loki Flake Graphite Deposit as a long-life graphite development project with positive economics; project to

advance toward Feasibility Study

SASKATOON, SK / ACCESS Newswire / August 19, 2026 / Abasca Resources Inc. ("Abasca" or the "Company")

(TSXV:ABA) announces positive results from an independent Preliminary Economic Assessment (the "PEA") for its 100%-

owned Loki Flake Graphite Deposit ("Loki Deposit" or the "Project"), approximately 15 kilometres south of the Key Lake mill,

Figure 1. The study projects the Loki Deposit as a long-life graphite development project with an after-tax net present value

(NPV) of US$130 million and 16.7% internal rate of return (Table 1).

The Company's focus will now shift to continuing to acquire the technical data required for preparing a feasibility study ("FS"),

while also obtaining an updated environmental impact assessment and the permits necessary to support future project

advancement.

"Loki has continued to exceed our expectations. We are pleased to reach this significant milestone in our fast ‑ track journey to

develop the deposit and to vest the staged project value. The PEA also provides Abasca with the technical data needed to support

financing and offtake strategic processes, while advancing a long ‑ life graphite development project that aligns with our vision of

establishing a reliable, long ‑ term source of graphite to support the federal and provincial governments' critical ‑ minerals

supply ‑ chain security strategies," said Dawn Zhou, President and CEO of Abasca.

PEA Highlights

Long-Life Graphite Project: 2,750 tonnes-per-day ("tpd") open-pit mining and processing operation with a 19-year mine

life, averaging 66,500 tonnes of graphite concentrate (with an average 95% grade) produced annually and 1.2 million

tonnes of payable graphite over the life of mine. The Project's scale and longevity provide exposure to multiple graphite

price cycles.

Positive Project Economics: Positive economics under the base case graphite price assumptions, generating

approximately US$662 million in cumulative after-tax free cash flow under the base case.

Table 1: Loki Flake Graphite Project PEA Pre-Tax and After-Tax Economic Results Summary.

Graphite Price (US$/tonne) US$1,450/tonne

Pre-Tax Net Present Value (NPV) @ 8% US$161M

Pre-Tax Internal Rate of Return (IRR) 16.6%

After-Tax Net Present Value (NPV) @ 8% US$130M

After-Tax Internal Rate of Return (IRR) 16.7%

Note: Project economics are presented on an unleveraged basis and do not assume project debt or other financing arrangements.

Description of the PEA

The PEA outlines a conceptual development scenario for the Project based on the updated Mineral Resource Estimate (see

"Mineral Resources" below), incorporating conventional open-pit mining and onsite graphite concentrate recovery through a

2,750 tonne-per-day processing facility.

The PEA was prepared by Tetra Tech Canada Inc. ("Tetra Tech") in accordance with National Instrument 43-101 - Standards of

Disclosure for Mineral Projects ("NI 43-101"). The geology and mineral resources sections of the PEA were prepared by

Understood Mineral Resources Inc. ("UMR").

This PEA is preliminary in nature. It includes Inferred Mineral Resources that are considered too speculative geologically to have

economic considerations applied to them that would enable them to be categorized as mineral reserves. There is no certainty that

the PEA will be realized. Mineral resources that are not mineral reserves do not have demonstrated economic viability.

A technical report supporting the PEA will be filed on SEDAR+ (www.sedarplus.ca) and on the Company's website within 45

days of this news release.

Project Overview

The Loki Flake Graphite Deposit is located approximately 15 kilometres south of the Key Lake mill. Provincial Highway 914, a

north-south all-weather highway in Saskatchewan, crosses the project, providing ideal access. The Project consists of 12

contiguous claims (23,974 hectares or approximately 240 sq. km) which were staked during 2011 to 2012 and have been held and

explored by a private company ("SaskCo") until the end of 2022. Abasca subsequently acquired the Project by reverse takeover

leading to holding 100% interest in the Project.

The Loki Flake Graphite Deposit is underlain by the prospective uranium hosting rocks of the Wollaston-Mudjatik contacting

zone (WMCZ) in the southeastern Athabasca Basin. The world's largest high-grade uranium deposits are associated with the

unconformity between the Athabasca Basin and the Wollaston-Mudjatik basement as well as strongly graphitic fault zones. Most

of the uranium occurrences and deposits associated with the Athabasca Basin are located near the boundary between the Mudjatik

and Wollaston domains as either unconformity-related or basement-hosted type. The Project is located in the southern strike

extent of these deposits and in the same regional magnetic low structure that hosts them.

On July 14, 2026, Abasca announced an updated Mineral Resource Estimate (the "MRE") for the Loki Flake Graphite Deposit.

The pit-constrained MRE conforms to the Reasonable Prospects of Eventual Economic Extraction (RPEEE) requirements of NI

43-101 and includes an Indicated resource of 6.99 Mt at 8.27 % Cg in addition to Inferred resource of 15.83 Mt at 6.93 % Cg1.

PEA Economic Results

The Loki Deposit's PEA Economic Results are presented in Table 2. All dollar figures are expressed in US dollar and all units in

metric, unless otherwise noted.

The PEA is preliminary in nature. It includes Inferred Mineral Resources that are considered too speculative geologically to have

the economic considerations applied to them that would enable them to be categorized as Mineral Reserves. There is no certainty

that the PEA will be realized. Mineral resources that are not mineral reserves do not have demonstrated economic viability.

[1] Please refer to the Company's news release dated July 14, 2026 and titled: "Abasca Increases Loki Flake Graphite Resource

and Confirms Second Mineralized Trend at Thor Zone"

Figure 1: Map showing the location of the Key Lake South Project that hosts the Loki Flake Graphite Deposit

Table 2: Loki Flake Graphite Project PEA Economic Results

Description Unit Value

Metal Price

Graphite Price (Average) US$/t 1,450

Production

Mine Life Year 19

Mill Feed Tonnage, Life of Mine (LOM) Mt 17.9

Mill Feed Grade, Life of Mine (LOM) % Cg 7.27

Concentrate Grade, Life-of-mine Average % Cg 95.0

Graphite Recovery to Concentrate % 92.3

Graphite Produced, Life of Mine (LOM) dry tonnes 1,263,000

Annual dry tonnes 66,500

Operating Costs, Life of Mine (LOM) US $M 828

Unit US$/t proc. 46.34

Operational Revenue US $M 940

Capital Costs

Initial Capex US $M 216

Sustaining US $M 64

Closure & Reclamation US $M 27

Total Capital Costs US $M 307

Economic Results

Discount Rate % 8%

Pre-Tax Unlevered Free Cash Flow (UCF) US $M 633

Description Unit Value

Pre-Tax Net Present Value (NPV) @ 8% US $M 161

Pre-Tax Internal Rate of Return (IRR) % 16.6%

Pre-Tax Simple Payback Year 6.2

After-Tax Unlevered Free Cash Flow (UCF) US $M 477

After-Tax Net Present Value (NPV) @ 8% US $M 130

After-Tax Internal Rate of Return IRR % 16.7%

After-Tax Simple Payback Year 4.7

Notes

1. Initial Capex represents upfront expenditures to construct and commission the mine, plant, and supporting infrastructure.

2. Sustaining Capex represents ongoing capital expenditures required to maintain production during the life of mine.

3. Payback represents years from start of commercial production to achieve cumulative positive after-tax free cash flow,

including sustaining capital.

4. Exchange rate assumption: $0.72 USD per $1.00 CAD.

5. Non-GAAP financial measures are presented for additional information and benchmarking purposes only. See "Use of

Non-GAAP Financial Measures."

Capital and Operating Costs

Initial CAPEX: US$216M, including contingency of US$24.3M and US$22.5M mining initial operating costs and

equipment lease downpayment.

Sustaining Capital and Closure Costs: US$56.4M from Year 1 to Year 19, followed by a 4-year period of closure and

reclamation.

Operating Costs: US$46.34/t processed, including mining and waste management (44%), processing (28%), G&A and site

services (27%), and interest on mining equipment lease (1%).

Mineral Resources

An updated MRE, effective date April 23, 2026, was prepared by UMR in accordance with CIM and NI 43-101 Guidelines and

replaces the previous mineral resource estimate with an effective date of April 10, 2025, Table 3.

The updated MRE incorporates the current geological interpretation and forms the basis of the 19 year mine plan evaluated in the

PEA.

Table 3: Loki Flake Graphite Project PEA Mineral Resource Statement, effective date April 23, 2026.

Classification Cg Grade

Cut-off (%) Tonnes (Mt) Cg Grade (%) Contained

Cg (Mt)

Indicated 2.30 6.99 8.27 0.58

Inferred 2.30 15.83 6.93 1.10

Notes

1. The reporting standard for the Mineral Resource Estimate uses the terminology, definitions and guidelines given in the

Canadian Institute of Mining, Metallurgy and Petroleum (CIM) Standards on Mineral Resources and Mineral Reserves

(May 2014) as required by NI 43-101.

2. Reported Mineral Resources are constrained to a conceptual pit-shell above a cut-off grade of 2.30% Cg.

3. Numbers may not add up due to rounding.

4. The effective date of this Mineral Resource estimate is April 23, 2026.

5. The qualified person knows of no environmental, permitting, legal, title, taxation, socio-economic, marketing, political or

other relevant factors that may materially affect the Mineral Resource Estimate in this release.

6. Mineral Resources are not Mineral Reserves and have not demonstrated economic viability.

Mining Method

The Company plans to develop the Loki Flake Graphite Project using conventional open-pit mining methods, including drilling,

blasting, loading, and hauling with conventional mining equipment. Material will be drilled and blasted, then loaded into diesel-

powered haul trucks using a fleet of hydraulic shovels and front-end wheel loaders.

To identify the optimal pit size and mining sequence, Tetra Tech employs the Lerchs-Grossmann (LG) algorithm to evaluate the

net value of individual blocks within the block model. An assumed graphite concentrate price of US$1,450 per tonne has been

applied. Life of mine (LOM) operating costs were estimated from both first principles and based on similar projects or

operations. Figure 2 shows the PEA mine production plan.

Figure 2: Loki Flake Graphite Deposit PEA Mine Production Plan

The life-of-mine plan comprises 17 years of active mining operations followed by two years of stockpile processing. Mining is

conducted at a consistent rate of 10.0 Mt of material annually during the first seven years and slowly diminishing from Y8 to

Y17, with a LOM average strip ratio of 6.1:1. The process plant is designed for a nominal throughput of 2,750 tonnes per day

(approximately 1.0 million tonnes per year). Average payable graphite production over the 19-year mine life is estimated at

approximately 1.23 million dry tonnes per year. Mill throughput is planned at 75% of nameplate capacity in Year 1, 85% in Year

2, and 100% from Year 3 onward, allowing for a controlled start-up and optimization of plant performance. The mill feed grade

fluctuates between 6% to 8% from Year 1 to Year 17, before reaching 4% to 5% during the processing of the stockpiled material

from Year 18 to Year 19.

Processing

A preliminary test program for recovering the graphite from the Abasca deposit was conducted by SGS Lakefield during 2025

and 2026. The test program included chemical characterization, mineralogical analyses, grindability testing, and flotation testing,

graphite concentrate and flotation tailings characterisation.

The test results indicate that the samples respond well to conventional flotation concentration. The flowsheet uses separate

flotation with staged regrinding for coarse and fine fractions respectively. The final concentrates are expected to be approximately

95% or higher.

Based on the test work results, a preliminarily optimized flowsheet was developed for this study. The process flowsheet is

designed for 2,750 tpd and follows a conventional flotation circuit with staged regrinding process to produce sized high-grade

graphite concentrate, which will be further processed at an offsite purification facility. The processing plant (Figure 3 shows

simplified process flow diagram) will consist of the following:

A run-of-Mine (ROM) mill feed stockpile,

A primary crusher operating in open circuit,

A secondary crusher operating in closed circuit with a vibrating screen,

A crushed mill feed stockpile with reclaim feeders,

A ball mill grinding circuit operating with flash flotation and a classification hydrocyclone cluster,

A rougher flotation circuit comprising rougher and rougher-scavenger flotation, followed by a rougher-scavenger tailings

dewatering circuit, including thickening and filtration processes to generate tailings filter cakes for tailings dry stacking at a

lined tailings management facility (TMF) to mitigate the impacts of tailings acid generation potentials on environment,

A rougher concentrate upgrading circuit comprising

one-stage polishing regrinding followed by one stage of cleaner flotation,

second-stage polishing mill followed by three stages of cleaner flotation,

A fourth-cleaner concentrate sizing circuit to separate the upgraded rougher concentrate into coarse and fine graphite

concentrate streams,

A coarse concentrate regrind mill, followed by four additional stages of cleaner flotation (5th to 8th cleaners) to produce a

final coarse graphite concentrate,

A fine concentrate regrind mill, followed by five additional stages of cleaner flotation (5th to 9th cleaners) to produce a

final fine graphite concentrate,

A concentrate dewatering and product handling circuit, including concentrate thickening, filtration, drying, final product

sizing, and packaging.

Figure 3: Loki Flake Graphite Deposit PEA Simplified Process Flowsheet

Infrastructure

The Project benefits from existing transportation infrastructure, proximity to provincial power network, and favourable site

characteristics that support future development, including:

Road Access: The Loki Flake Graphite Deposit is located approximately 15 kilometres south of the Key Lake mill.

Provincial Highway 914, a north-south all-weather highway in Saskatchewan, crosses the project, providing ideal access.

Power: The provincial power grid is 15 km from the Loki Flake Graphite Deposit, which can provide long-term cost-

effective and reliable electrical power for the Project.

Water: Several surface water bodies are located near the project site and are expected to provide suitable water sources for

future operations, subject to detailed engineering and permitting.

Waste Rock and Tailings Co-deposition Facility (WRTCF): The WRTCF was designed to accommodate 17.9 Mt of

tailings and 108.4 Mt of waste rock over the life of the mine. The WRTCF will consist of co-deposited dry stacked tailings

and waste rock, providing advantages over the conventional slurry Tailings Management Facility design.

Camp and Services: Existing accommodation camps nearby have the potential to support construction and operations.

Camp services are expected to be provided by third-party contractors, creating potential business and employment

opportunities for nearby Indigenous communities.

Overall Site General Arrangement: The overall site arrangement is presented in the Figure 4.

Figure 4: Loki Flake Graphite Deposit PEA Overall Site General Arrangement Plan.

Environmental, Social, and Permitting

In 2025, Abasca engaged CanNorth Environmental Services to conduct environmental studies on the Project. The purpose of the

studies was to initiate data collection for components that require baseline datasets, specifically hydrology, water chemistry, and

bathymetry to support a future Environmental Impact Assessment. Studies and data collection will continue into 2026 and 2027,

including further work on aquatic, terrestrial and heritage resources as well as work on meteorological, hydrogeological and

geochemical conditions. This work will advance project development and support future submissions to meet regulatory

requirements.

Opportunities and Exploration Potential

The PEA presents a conceptual development scenario for Loki Deposit based on current information. The following opportunities

may be evaluated in future technical studies to further optimize the Project's technical and financial performance.

Power Optimization

SaskPower funds community initiatives, educational programs, and clean energy development across Saskatchewan to align with

its strategic utility goals. As the province's principal electric utility, the crown corporation provides financial backing through

corporate sponsorships, capital grants, and energy-efficiency programs. Abasca will initiate business opportunity discussions with

SaskPower for funding power supply infrastructure for the project.

Government and Critical Minerals Funding Opportunities

Graphite is included on Canada's and Saskatchewan's critical minerals list. Abasca intends to evaluate available federal and

provincial funding, infrastructure and strategic investment programs that may support future engineering, infrastructure

development and project advancement.

Closure Cost Refinement

The PEA applies a conservative estimate for closure costs. Additional geochemical and hydrological and site-specific engineering

studies may allow estimates to be further refined in subsequent technical studies.

Mineral Resource Conversion to Mineral Reserve

There exists the opportunity to continue drilling the Loki Deposit to upgrade the Classification to Indicated by Infill drilling and

to expand the resource, providing opportunities to further evaluate and potentially enhance long-term project value through future

exploration.

Next Steps/Path Forward

Advancing Engineering

The completion of the PEA establishes a strong technical foundation for the next stage of engineering. The Company believes the

Project is well positioned to advance to feasibility-level engineering.

Future work is expected to focus on metallurgical optimization, geotechnical and hydrogeological investigations, detailed mine,

infrastructure and tailings engineering, environmental studies, and continued refinement of the Project's capital and operating cost

estimates.

Engineering Support Drilling

The Company anticipates evaluating a targeted drilling program to support feasibility-level engineering. The program would be

expected to focus primarily on infill drilling, geotechnical investigations and metallurgical sample collection, and mineral

resource expansion.

Environmental & Permitting

In parallel with the Feasibility Study, Abasca intends to advance the environmental assessment process and obtain the regulatory

approvals required to support future Project development, building on the substantial environmental studies and technical work

completed during the previous Environmental Assessment process. The Company will continue to engage with the Indigenous

Groups, regulators and local stakeholders throughout this process.

Strategic Development

The Company will continue evaluating opportunities to advance the Project through strategic partnerships, government-supported

critical mineral initiatives and engagement with potential customers and other industry participants.

Study Notes

The PEA was prepared by Tetra Tech Canada Inc. with an effective date of August 19, 2026. The study is based on an updated

Mineral Resource Estimate with an effective date of April 23, 2026, prepared in accordance with the CIM Definition Standards

and NI 43-101.