Asanko Gold Initiates Phase 1 of AGM and Appoints Key Contractors

Management Changes Shareholder Meetings

Highlights:  

  • DRA  and  Knight  Piesold  appointed  as  EPCM  contractor  and  Tailings  Storage  Facility  design  contractor, respectively
  • Phase  1  of  the  AGM  targeting  220,000  ounces  of  gold  production  per  year  for  the  first  five  years
  • 3Mtpa  CIL  plant  and  mine  site  fully  permitted,  with  capital  cost  estimate  of  US$298m1
  • Phase  1  fully  financed  with  US$255m2  in  cash  on  hand  and  debt  facility  of  US$150m3
  • Updates  to  Nkran  and  Adubiaso  resource  estimates  and  mine  plans  well  underway
  • Investment  Decision  to  proceed  with  Phase  1  expected  early  Q3  2014
  • First  gold  production  targeted  for  Q1  2016

Vancouver,   British   Columbia,   April   3,   2014   –   Asanko   Gold   Inc.   (“Asanko”)   (TSX,   NYSE   MKT:   AKG)   is pleased   to   announce   it   has   appointed   DRA   as   the   Engineering,   Procurement,   Construction   and Management  (“EPCM”)  contractor  for  the  design  and  construction  of  Phase  1  of  the  Asanko  Gold  Mine (“AGM”)  Project  in  Ghana,  following  a  competitive  bidding  process.

Based  in  Johannesburg,  South  Africa,  DRA  has  successfully  worked  with  the  leadership  team  at  Asanko  on multiple   projects   in   Africa   over   many   years   and   has   recently   completed   engineering   work   on   Asanko’s Esaase  project.    DRA  is  a  well-­‐known  and  highly  respected  EPCM  contractor,  with  a  strong  track  record  of successfully  building,  commissioning  and  operating  gold  plants  across  Africa.    Recently,  DRA  has  acted  as EPCM   contractor   for   Randgold   Resources  on  the  7.2  million  tonne  per  annum  (“Mtpa”)  gold   processing facilities  and  associated  infrastructure  at  the  recently  built  and  commissioned  Kibali  site  in  the  DRC  and  is currently  working  as  the  EPCM  contractor  for  Aureus  Mining  at  their  New  Liberty  Project  in  Liberia.

Peter  Breese,  President  and  CEO,  said  “The  appointment  of  DRA  as  EPCM  contractor  marks  the  initiation  of   Phase   1   at   our   flagship   project,   the   Asanko   Gold   Mine,   which   will   form   the   foundation   of   our   vision   to   become  a  mid-­‐tier  gold  producer.  My  team  and  I  have  worked  extensively  with  DRA  for  many  years  and   together  we  have  successfully  built  and  commissioned  mines  in  Africa  that  have  all  been  delivered  on  time   and  on  budget.  It  is  this  track  record  that  gives  us  confidence  that  we  will  be  able  to  deliver  first  gold  in  Q1   2016.  

Work  is  progressing  well  on  all  other  fronts  and  the  Board  is  targeting  to  make  an  investment  decision  mid-­‐ year.    We  are  fully  funded  for  Phase  1  with  US$255  million  cash  and  we  are  making  good  progress  with  Red   Kite  to  modify  the  security  provisions  and  loan  documentation  for  our  existing  agreements.    We  expect  to   have  these  revisions  completed  in  Q2  2014.”  

In   addition,   the   Company   has   appointed   Knight   Piesold   to   design   the   TSF   and   carry   out   detailed geotechnical  engineering  works  for  the  site.  Knight  Piesold  are  well  known  in  Ghana  and  have  designed, built   and   operated   several   tailings   storage   facilities   in   the   country.   They   have  reviewed   the  current   TSF design  and  concluded  that  the  selected  location  can  be  expanded  to  hold  tailings  from  both  Phase  1  and Phase  2  operations.

AGM  Phase  1  

Phase   1   is   based   on   PMI   Gold   Corporation’s   Definitive   Feasibility   Study   (“DFS”)   on   the   Obotan   Project, published  in  September  20121.    Asanko  is  currently  updating  the  DFS  capital  and  operating  cost  estimates.

As  part  of  the  competitive  EPCM  tendering  process,  Asanko  received  and  reviewed  a  selection  of  bids  for the  process  facilities.    Based  on  this,  the  Company  believes  that  the  US$83.7  million  capital  cost  for  the construction  of  the  processing  plant  included  in  the  DFS  capital  cost  estimate  of  US$298  million  is  still  valid. As  well,  the  Company  is  modifying  certain  technical  elements  to  incorporate  Phase  2’s  future  requirements.

Asanko  has  also  undertaken  work  on  enhancing  the  information  utilized  to  complete  the  Mineral  Resource Estimate  at  Nkran  and  Adubiaso.  The  updated  Mineral  Resource  Estimate  for  these  two  deposits  will  form the  basis  of  the  detailed  mine  plan,  which  will  be  completed  by  mid-­‐year  along  with  the  Project’s  Control Budget  Estimate  to  allow  Asanko’s  Board  to  make  the  full  investment  decision.    A  full  update  on  all  the Company’s  Mineral  Reserves  and  Resources  will  be  published  as  normal  course  of  business  with  our  2014 year-­‐end  filings.

The  September  2012  Feasibility  Study  for  Phase  1  targeted  approximately  220,000  ounces  of  annual  gold production  over  the  first  five  years  of  mine  life  via  an  open  pit  contractor  mining  operation  and  a  3  Mtpa carbon-­‐in-­‐leach  (“CIL”)  processing  plant  (see  attached  flow  sheet).    The  primary  source  of  feed  material  for the   CIL   plant   will   be   the   Nkran   and   Adubiaso   pits.   In   addition,   the   Company   will   be   investigating   the potential  for  the  newly  discovered  Dynamite  Hill  deposit  to  provide  additional  feed  material  in  the  early years  of  production.

Nkran   is   an   existing   pit   that   was   mined   from   1998-­‐2002   and   requires   approximately   four   months   of dewatering  prior  to  starting  the  pre-­‐strip.    The  Company  has  a  permit  to  dewater  the  pit  and  expects  to commence  pumping  later  in  2014.

The  plant,  mine  and  associated  infrastructure,  such  as  the  tailings  storage  facility  (“TSF”)  and  waste  rock dumps,  have  been  fully  permitted  for  construction  to  start.  Detailed  design  of  the  plant  is  well  advanced and  is  in  the  process  of  being  transitioned  to  DRA.

The  SAG  and  ball  mills,  which  were  ordered  in  2012,  have  been  fabricated.  The  manufacture  of  the  SAG  mill liners  and  girth  gears  for  both  mills  will  start  as  soon  as  the  Company  has  made  an  investment  decision. Due  to  the  advanced  nature  of  the  mills  fabrication,  it  is  expected  that  the  mills  will  be  ready  for  delivery well  ahead  of  the  dates  required  in  the  final  project  schedule.

An   investment   decision   to   proceed   with   Phase   1   is   expected   by   the   Asanko   Board   in   early   Q3   2014, followed  by  a  21  month  construction  and  commissioning  period,  with  first  gold  targeted  during  Q1  2016. Early  works  site  preparation  activities  are  due  to  commence  shortly.

Project  Schedule  and  Key  Milestones  

The  Company  is  working  towards  the  following  milestones:

  • Commencement  of  early  works   Q2  2014
  • Commencement  of  near  mine  resource  definition  drilling  on  Dynamite  Hill   Q2  2014
  • Finalize  revisions  to  the  Red  Kite  financing  arrangements   Q2  2014
  • Investment  Decision  for  Phase  1   Q3  2014
  • Evaluate  trade  off  studies  for  Phase  2   Q4  2014
  • Project  Construction     Q3  2014  to  Q1  2016
  • Commissioning  and  Ramp-­‐up   Q1  2016
  • Steady  State  Production  of  >200,000  oz/year   Q2  2016

Notes:  

1. PMI  Gold  Corporation’s  Definitive  Feasibility  Study  (“DFS”)  on  the  Obotan  Project,  published  in September  2012.    See  filing  on  www.sedar.com

2. Estimated  cash  balance  as  at  February  6,  2014  which  was  the  time  of  the  close  of  the  PMI  Gold acquisition  by  Plan  of  Arrangement.

3. Project  debt  facility  arranged  with  Red  Kite  Mine  Finance.    See  news  release  dated  October  24,  2013.

Enquiries:  

For  further  information  please  visit  www.asanko.com  or  contact:

Alex  Buck,  Manager  –  Investor  Relations   Greg  McCunn,  Chief  Financial  Officer Telephone:  +44-­‐7932-­‐740-­‐452   Telephone:  +1-­‐778-­‐729-­‐0604 Email:  [email protected]   Email:  [email protected]

General  enquiries:  [email protected]

About  Asanko  Gold  

Asanko’s  vision  is  to  become  a  mid-­‐tier  gold  mining  company  that  maximizes  value  for  all  its  stakeholders. Asanko’s   flagship   project   is   the   fully   financed,   multi-­‐million   ounce   Asanko   Gold   Mine   Project   located   in Ghana,  West  Africa.

Asanko  is  managed  by  highly  skilled  and  successful  technical,  operational  and  financial  professionals.  The Company   is   strongly   committed   to   the   highest   standards   for   environmental   management,   social responsibility,  and  health  and  safety  for  its  employees  and  neighboring  communities.

About  DRA  

Based  in  Johannesburg,  South  Africa,  DRA  is  a  well-­‐known  and  highly  respected  EPCM  contractor,  with  a strong   track   record   of   successfully   building,   commissioning   and   operating   gold   plants   across   Africa. Recently,   DRA   has   acted   as   EPCM   contractor   for   Randgold   Resources   on   the   7.2Mtpa   gold   processing facilities  and  associated  infrastructure  at  the  recently  built  and  commissioned  Kibali  site  in  the  DRC  and  is currently  working  as  an  EPCM  contractor  for  Aureus  Mining  at  their  New  Liberty  Project  in  Liberia.

About  Knight  Piesold  

Knight  Piésold  is  an  international  consulting  company  providing  engineering  and  environmental  services  for the  mining,  power,  water,  transportation  and  construction  sectors.    Knight  Piésold  has  been  involved  in  the design  of  tailings  management  facilities  for  over  400  mining  projects  throughout  the  world.  Knight  Piésold has  established  strong  working  relationships  with  specialist  groups  that  provide  support  for  the  design  of tailings  thickeners,  slurry  pipelines,  filtering  plants,  and  paste  tailings  plants  in  order  to  provide  complete and  comprehensive  design  and  operational  expertise  for  tailings  management.

Attachment  -­‐  Flow  Sheet  for  the  3Mtpa  CIL  Process  Plant  

Forward-­‐Looking  and  other  Cautionary  Information  

This   release   includes   certain   statements   that   may   be   deemed   "forward-­‐looking   statements".   All   statements   in   this   release,  other  than  statements  of  historical  facts,  that  address  estimated  resource  quantities,  grades  and  contained   metals,  possible  future  mining,  exploration  and  development  activities,  are  forward-­‐looking  statements.  Although  the   Company  believes  the  forward-­‐looking  statements  are  based  on  reasonable  assumptions,  such  statements  should  not   be  in  any  way  construed  as  guarantees  of  future  performance  and  actual  results  or  developments  may  differ  materially   from  those  in  the  forward-­‐looking  statements.  Factors  that  could  cause  actual  results  to  differ  materially  from  those  in   forward-­‐looking   statements   include   market   prices   for   metals,   the   conclusions   of   detailed   feasibility   and   technical   analyses,  lower  than  expected  grades  and  quantities  of  resources,  mining  rates  and  recovery  rates  and  the  lack  of   availability  of  necessary  capital,  which  may  not  be  available  to  the  Company  on  terms  acceptable  to  it  or  at  all.  The   Company   is   subject   to   the   specific   risks   inherent   in   the   mining   business   as   well   as   general   economic   and   business   conditions.  For  more  information  on  the  Company,  Investors  should  review  the  Company's  annual  Form  20-­‐F  filing  with   the  United  States  Securities  Commission  and  its  home  jurisdiction  filings  that  are  available  at  www.sedar.com.  

Neither  Toronto  Stock  Exchange  nor  the  Investment  Industry  Regulatory  Organization  of  Canada  accepts  responsibility   for  the  adequacy  or  accuracy  of  this  release.