NEWS RELEASE LUNDIN MINING RELEASES 2010 THIRD QUARTER RESULTS  

Toronto,  October  27,  2010  (TSX:  LUN;  OMX:  LUMI)  Lundin  Mining  Corporation  (“Lundin”  or  the “Company”) today reported an unaudited net income of $59.0 million ($0.10 per share) for the third quarter of 2010, up from $3.7 million ($0.01 per share) in the third quarter of 2009.

Mr.  Phil  Wright,  President  and  CEO  commented,  “Net  income  this  quarter  is  well  up  on  last  year, reflecting improved metal prices and a much greater contribution from our equity investment in Tenke.

“Copper  and  nickel  production  this  quarter  was  below  our  expectations  owing  to  unexpected  delays affecting two high‐grade stopes at Neves‐Corvo and industrial action, and geotechnical issues in the pit, affecting Aguablanca.  Production lost during the quarter cannot be made up in the fourth quarter and consequently we are revising down our full year guidance on copper by 3,000 tonnes and nickel by 1,000 tonnes.

“On the exploration front, we are very pleased to report the discovery of a new high‐grade massive sulphide  deposit  at  Neves‐Corvo.   The  new  deposit,  named  Semblana,  is  located  approximately  one kilometre northeast of the Zambujal orebody in an area which has not previously been drilled.

“Initial results are outlining a large deposit with a strong sulphide system containing high‐grade copper mineralization indicating this has the potential to be a significant new orebody.

“The deposit is the first such copper discovery at Neves‐Corvo in 20 years and it reaffirms our belief that Neves‐Corvo remains under‐explored.

“Needless to say, we are very pleased to see the Tenke contract review reaching a conclusion, allowing renewed consideration of development options for this world‐class asset,” Mr. Wright said.

Summary financial results for the quarter are as follows:

US $ millions (except per share amounts)Three Months Ended Sept 30Nine months ended Sept 30
2010200920102009
Sales215.1171.1540.0489.3
Operating earnings120.291.8265.6221.0
Net income from continuing operations59.03.7172.533.0
Net income59.03.7172.538.6

Basic & diluted income per share:

From continuing operations0.100.010.300.06
From discontinued operations‐‐‐0.01
Total:0.100.010.300.07
Cash provided by operations47.340.0208.440.4

Third Quarter Highlights 

  • Copper and nickel production for the quarter was below expectations owing to: unexpected delays at  Neves‐Corvo  affecting  two  high‐grade  stopes  (+7%  copper  grade)  limiting  ore  production  and resulting in replacement material coming from lower‐grade sources; and Aguablanca ore production was significantly reduced owing to the decision, as reported last quarter, to bring forward a push‐

back in the pit that was originally planned for next year.  In addition, 10 days of production were lost to industrial action at Aguablanca.

  • At  Tenke  Fungurume,  copper  and  cobalt  production  during  the  quarter  exceeded  nameplate capacity.    Milling  throughput  is  now  performing  consistently  above  design  capacity.    With  the procurement of more mine equipment and changes to the mine plan, Freeport‐McMoRan Copper & Gold  Inc.  (“FCX”  or  “Freeport”),  the  mine’s  operator,  is  expecting  copper  cathode  production  to increase from 115,000 tonnes per annum in 2010 to approximately 130,000 tonnes per annum in 2011.
  • Total production was as follows:
Wholly‐owned operations (tonnes)YTDQ3Q2Q1FY Q4 Q3 Q2 Q1 2009 2009 2009 2009 2009
2010201020102010
Copper Zinc Lead Nickel55,12720,50921,77412,84493,451 23,868 21,351 23,992 24,240 101,401 20,011 15,151 31,962 34,277 43,852 10,393 8,111 12,478 12,870 8,029 2,324 1,784 1,960 1,961
66,64722,57124,45819,618
30,09810,90210,9538,243
5,2341,3631,7152,156

Tenke attributable (24.75%)

Copper Cobalt21,8597,7017,0387,12017,325 7,227 6,019 4,079 ‐ 638 477 159 2 ‐
1,560599409552
  • Operating earnings1 increased by $28.4 million from $91.8 million in the third quarter of 2009 to $120.2  million  in  2010.  Favourable  price  and  price  adjustments  ($51.4  million  effect)  and  more favourable exchange rates ($6.8 million effect) were partially offset by lower sales volumes ($6.0 million effect) and higher unit costs ($17.4 million effect, excluding a 2008 royalty charge).
  • Net  income  of  $59.0  million  (Q3‐2009:  $3.7  million)  or  $0.10  per  diluted  share  (Q3‐2009:  $0.01) includes:
    • a pre‐tax loss on foreign exchange of $19.1 million, an increase of $21.9 million from the prior corresponding quarter;
    • a royalty charge for Neves‐Corvo of $8.1 million related to 2008.  The base used for the purpose of  calculating  the  royalty  was  re‐assessed  by  the  Portuguese  government  to  exclude  certain costs deducted during 2008 related to the funding of the development of the Aljustrel Mine. The after‐tax impact of this charge is $5.8 million;
    • gains on the disposal of non‐core assets in Spain of $5.4 million ($3.8 million after tax).

The effects of the non‐recurring items are shown below:

Q3 2010Q3 2009Q2 2010
Reported Net Income59.03.775.6
Derivative losses (gains)0.524.9(11.2)
(Gain) loss on sale of non‐core assets and investments(5.4)18.7(32.4)
Royalty charge related to 20088.1‐‐
Legacy property closure accrual2.8‐‐
Tax on above items(0.9)(6.6)7.7
Other non‐recurring tax adjustments‐‐13.6*
Adjusted Net Income64.140.753.3
Basic and diluted income per share$0.11$0.07$0.09
  • increase in future tax liability related to the 2.5% tax rate increase in Portugal

1 Operating earnings is a Non‐GAAP measure defined as sales, less operating costs, accretion of ARO and other provisions, selling, general and administration costs and stock‐based compensation.

  • Sales for the quarter were $215.1 million compared to sales of $171.1 million in the third quarter of 2009.  Metal price improvements and price adjustments ($50.0 million) were partially offset by the effect of lower volume ($9.2 million). Copper inventory levels were slightly higher than normal due to a shipment in transit at quarter end.

Average metal prices in the third quarter of 2010 were 15% to 25% higher than the same quarter in 2009 except for lead which increased only 6%.

  • Cash inflow from operations was $47.3 million for the quarter, compared to $40.0 million for the corresponding period in 2009. Excluding changes in non‐cash working capital items, cash inflow this quarter was $90.6 million compared to $53.0 million for the prior corresponding period.

Net  cash1  as  at  September  30,  2010  of  $125.7  million  represents  an  increase  of  $17.9  million compared  to  the  previous  quarter,  and  an  increase  of  $175.0  million  against  net  debt1  of  $49.3 million at December 31, 2009.

  • During the quarter, the Company’s revolving credit facility agreement was amended, increasing the facility to $300 million from $225 million, and extending the term to September 2013.  The amended facility provides additional flexibility for future growth projects and reduced carrying costs.

The $300 million revolving credit facility was undrawn at quarter‐end.

Tenke Fungurume 

  • On  October  22,  2010,  the  Government  of  the  DRC  and  Freeport  announced  the  successful conclusion  of  the  review  of  Tenke  Fungurume  Mining's  (“TFM”)  contracts.    The  announcement outlined  several  additional  commitments  agreed  by  TFM,  including:      an  increase  in  Gécamines ownership interest in TFM from 17.5% to 20%; an additional royalty of $1.2 million for each 100,000 metric tonnes of proven and probable copper reserves above 2.5 million metric tonnes; additional payments  totaling  $30.0  million  to  be  paid  in  six  installments  upon  reaching  certain  production milestones;  conversion  of  $50.0  million  in  intercompany  loans  to  equity;  and  a  payment  of  $5.0 million  for  surface  area  fees.  Included  in  the  announcement  was  the  agreement  to  increase  the annual interest rate on advances (to TFM by FCX and Lundin Mining) from the current rate of LIBOR +2% to LIBOR +6%.

The  Company  notes  that  the  shareholding  change  benefiting  Gécamines  will  be  shared proportionately by Lundin Mining and Freeport. As a result Lundin Mining's equity interest in TFM will reduce from 24.75% to 24%.

  • The  Tenke  Fungurume  mine  is  now  running  consistently  above  design  capacity  and,  with  the procurement of more mine equipment and changes to the mine plan, Freeport is expecting annual copper production to increase from 115,000 tpa in 2010 to approximately 130,000 tpa in 2011.

For the quarter ended September 30, 2010, the Tenke Fungurume mine produced 31,115 tonnes of copper, and 33,044 tonnes were sold at an average realized price of $3.36 per pound.

The  amount  outstanding  at  September  30,  2010  on  the  Excess  Over‐run  Costs  facility  (“EOC facility”), related to the Company’s proportionate share of the Phase I development at Tenke, was $148.9 million, a reduction of $40.0 million during the quarter.

1 Net cash/debt is a Non‐GAAP measure defined as available unrestricted cash less financial debt, including capital leases and other debt‐ related obligations.

New Copper Discovery at Neves‐Corvo 

  • Surface  exploration  drilling  focussing  on  a  prospective  area  close  to  the  Neves‐Corvo  mine  has discovered a new copper‐rich massive sulphide deposit only one kilometre to the northeast of the Zambujal copper‐zinc orebody. The new “Semblana” deposit is the first potential new orebody to be found  since  the  discovery  of  Lombador  in  1988.    Testing  a  borehole  electromagnetic  (“BHEM”) anomaly, Hole SO48 intercepted a narrow bed of massive pyrite and stockwork type sulphides, after which four drill rigs were mobilised and directed to drilling wide step‐out holes targeting the BHEM anomaly.    Three  of  the  step‐out  holes  to  date  have  intercepted  high‐grade  copper  sulphide mineralization.  Highlighted assay results are as noted in the table below:
Hole No.From (metres)To (metres)Thickness (metres)Copper (%)Zinc (%)Lead (%)Tin (%)
PSK50‐1931.0952.021.04.160.270.050.15
PSL48A‐1923.0927.04.04.580.820.180.27
PSL48900.0936.536.51.440.730.270.12
including902.0909.07.02.320.200.050.13
and929.5935.56.03.392.641.150.28

Importantly,  in  addition  to  these  high  copper  grades,  each  of  these  drill  holes  has  intercepted concentrated  values  of  tin  ‐  Hole  PSL50‐1  contains  a  3.0  metre  interval  averaging  1.22%  tin  ‐ suggesting that the Semblana deposit is geologically similar to the very high‐grade Corvo orebody located approximately 1 km to the west. Drilling with four rigs continues with assays pending on three  additional  completed  holes.    Exploration  drilling  has  now  outlined  an  area  of  at  least  600 metres  by  250  metres  of  massive  sulphide  +  stockwork  mineralization  in  7  drill  holes.    This  new deposit remains open in almost all directions and appears to be almost flat‐lying.  Drill intersections shown above are interpreted to be true widths.

Financial Position and Financing 

  • The increase in liquidity during the quarter was primarily attributable to cash flow from operations of $47.3, after allowing for investment in mineral properties, plant and equipment of $31.8 million and  a  contribution  of  $8.5  million  to  Tenke  to  cover  2010  exploration,  expansion  studies  and sustaining capital investment.
  • Cash on hand at September 30, 2010 was $172.8 million, an increase of $23.2 million over the prior quarter‐end, despite an increase of $43.3 million in working capital related to higher receivables and inventories.

CEO Succession 

The CEO has advised the Board that he plans to retire sometime during the first half of 2011 and the Board has appointed a committee to address the timing and manner of succession to ensure an orderly and effective transition.

Outlook 

Production lost during the quarter cannot be made up in the fourth quarter and as a consequence:

  • Neves‐Corvo:  copper  production  guidance  is  reduced  by  2,000  tonnes  to  75,000  reflecting delays affecting two large, high‐grade stopes during the third quarter;
  • Zinkgruvan: unchanged;
  • Aguablanca: outlook reduced owing to: the need to bring forward into 2010 a push‐back that was  originally  scheduled  for  2011  as  a  result  of  geotechnical  issues  related  to  hydraulic pressure and faulting in the pit; and 10 days of production lost to industrial action;
  • Galmoy: minor change to reflect latest plans for delivery of ore to adjacent mines.

The revised guidance for 2010 is as follows:

(contained tonnes)Revised 2010 Guidance Tonnes C1 Cost1,2Previous Guidance Tonnes C1 Cost1,2
Neves‐CorvoCu75,000$ 1.3077,000$ 1.25
Zn6,0006,000
Zinkgruvan Zn Pb Cu75,000 $ 0.30 36,000 1,00075,000 $ 0.30 36,000 1,000
AguablancaNi6,500$6.257,500$ 6.25
Cu5,5006,500
Galmoy Zn (in ore) Pb12,000 4,00014,000 4,000
Total: Wholly‐owned operationsCu81,50084,500
Zn93,00095,000
Pb40,00040,000
Ni6,5007,500
Tenke: 24.75% attributable share Cu28,50028,500

Tenke’s attributable share will be reduced to 24.0% from 24.75% upon completion of the agreement announced on October 22, 2010, as noted in the Tenke Fungurume highlights discussion above, dealing with the resolution of the Tenke contract review.

Preliminary  plans  for  2011  indicate:  copper  production  for  2011,  including  our  attributable  share  of Tenke, of 115,000 tonnes; zinc production, including Galmoy, of 125,000 tonnes; and lead production, including Galmoy, of 40,000 tonnes.  For individual mines:

  • Neves‐Corvo: copper production, similar levels to 2010;  zinc increasing to around 30,000 tonnes taking into account the commissioning of the expanded zinc capacity in June 2011;
  • Zinkgruvan: zinc and lead, similar to 2010; with copper ramping up to around 3,000 tonnes;
  • Aguablanca:  the  mine  plan  is  undergoing  comprehensive  review;  however,  production  is  not likely to be less than present guidance for 2010
  • Tenke:  Freeport  is  forecasting  copper  production  of  around  130,000  tonnes  in  2011  (Lundin

1 Cash costs are dependent upon exchange rates, assumed as follows:  €/US$: 1.40.

2 Cash cost per pound is a non‐GAAP measure reflecting the sum of direct costs and inventory changes less by‐product credits.

24.75%  current  share  ‐  moving  to  24.0%  upon  completion  of  the  agreement  announced  on October 22, 2010 as noted in the Tenke Fungurume highlights section above)

This guidance will be updated in December 2010 once plans for 2011 are finalized.

  • Lombador feasibility study remains on‐track for completion in Q1 2011 and a start‐up date of 2013 is still being targeted.
  • Studies are underway at Zinkgruvan to allow the recently completed copper plant to treat zinc ores in addition to copper, thereby significantly increasing the flexibility of the Zinkgruvan operation.
  • Capital expenditure outlook for the year continues to be in the $190 million range.  This includes:
    • Sustaining capital in European operations of $90 million.
    • New investment in European operations of $60 million.
    • Investment in Tenke of a maximum of $40 million under current work programs.

Selected Quarterly Financial Information 

Three months ended September 30  Nine months ended September 30 

20102009 171.1 91.8 (46.5) (6.5) 0.7 (24.9) (18.7) ‐ (1.0) (5.1) 8.8 3.7 ‐ 3.7 2,913.1 40.0 54.7 3,744.4 (132.2) 5.03 0.01 0.01 ‐ 78% 579,510,141 579,645,695 579,574,131
215.1
120.2
(30.9)
(6.3)
(24.6)
(0.5)
‐
5.4
17.5
80.880.8
(21.8)
59.0
‐
59.0
3,039.0
3,039.0
47.3
40.2
3,696.3
125.7
5.24
0.10
0.10
0.10
‐
82%
579,889,803
580,262,754
579,924,803
20102009 489.3 221.0 (128.6) (16.0) 1.5 (34.1) (18.7) ‐ (5.3) 19.8 13.2 33.0 5.6 38.6 2,913.1 40.4 146.1 3,744.4 (132.2) 5.03 0.07 0.06 ‐ 78% 540,030,936 540,057,884 579,574,131
540.0
265.6
(99.7)
(16.6)
(5.0)
10.2
33.0
5.0
43.0
235.5235.5
(63.0)
172.5
‐
172.5
3,039.0
3,039.0
208.4
117.4
3,696.3
125.7
5.24
0.30
0.30
0.30
‐
82%
579,814,786
580,222,350
579,924,803

(USD  millions, except per share amounts)

Sales  Operating earnings1

Depletion, depreciation & amortization General exploration and project investigation Other income and expenses Gain (loss) on derivative contracts Gain (loss) on sale of  investments and other assets Gain (loss) on sale of non‐core assets Income (loss) from equity investment in Tenke

Income from continuing operations before   income taxes

Income tax (expense) recovery

Income from continuing operations 

Gain from discontinued operations

Net income  

Shareholders’ Equity  Cash flow from operations  Capital expenditures (incl. Tenke) 

Total assets  Net cash (debt)2

Key Financial Data: 

Shareholders’ equity per share3 Basic and diluted income  per share Basic and diluted income per share from continuing operations Dividends Equity ratio4

Shares outstanding: 

Basic weighted average Diluted weighted average End of period

($ millions, except per share data)Q3‐10Q2‐10Q1‐10Q4‐09Q3‐09Q2‐09Q1‐09Q4‐08Q3‐08
Sales215.1183.1141.7256.7171.1194.8123.443.5191.9
Operating earnings120.280.864.6152.291.891.038.2(65.8)68.9
Impairment charges (after tax)5‐‐‐(37.1)‐‐‐(651.5)(201.1)
Income (loss) from continuing operations59.075.638.035.13.743.5(14.1)(707.7)(190.2)
Net income (loss)59.075.638.035.13.743.5(8.6)(728.5)(199.0)
Income (loss) per share from continuing operations, basic and diluted0.100.130.070.060.010.08(0.03)(1.72)(0.49)
Income (loss) per share, basic6 and0.100.130.070.060.010.08(0.02)(1.77)(0.51)
diluted6
Cash flow from (used in) operations47.378.884.997.040.063.7(63.3)46.546.8
Capital expenditure (incl. Tenke)40.239.138.139.054.757.833.6105.7146.8
Net cash (debt)2125.7107.810.2(49.3)(132.2)(110.7)(259.5)(145.5)(194.8)

1 Operating earnings is a Non‐GAAP measure defined as sales, less operating costs, accretion of asset retirement obligation (“ARO”) and other provisions, selling, general and administration costs and stock‐based compensation.

2 Net cash (debt) is a Non‐GAAP measure defined as available unrestricted cash less financial debt, including capital leases and other debt‐ related obligations.

3 Shareholders’ equity per share is a Non‐GAAP measure defined as shareholders’ equity divided by total number of shares outstanding at end of period.

4 Equity ratio is a Non‐GAAP measure defined as shareholders’ equity divided by total assets at the end of period.

5 Includes impairment from discontinued operations.

6 Income (loss) per share is determined for each quarter.  As a result of using different weighted average number of shares outstanding, the sum of the quarterly amounts may differ from the year‐to‐date amount.

The 2010 third quarter consolidated interim financial statements and management’s discussion and analysis are available on SEDAR (www.sedar.com) or the Company’s website (www.lundinmining.com).

About Lundin Mining 

Lundin  Mining  Corporation  is  a  diversified  base  metals  mining  company  with  operations  in  Portugal, Sweden, Spain and Ireland, producing copper, zinc, lead and nickel. In addition, Lundin Mining holds a development  project  pipeline  which  includes  expansion  projects  at  its  Zinkgruvan  and  Neves‐Corvo mines  along  with  its  equity  stake  in  the  world  class  Tenke  Fungurume  copper/cobalt  project  in  the Democratic Republic of Congo.

On Behalf of the Board,

Phil Wright President and CEO

For further information, please contact:

Sophia Shane, Investor Relations North America:  +1‐604‐689‐7842 John Miniotis, Senior Business Analyst:  +1‐416‐342‐5565 Robert Eriksson, Investor Relations Sweden:  +46 8 545 015 50

Forward Looking Statements 

Certain of the statements made and information contained herein is “forward‐looking information” within the meaning of the  Ontario  Securities  Act.  Forward‐looking  statements  are  subject  to  a  variety  of  risks  and  uncertainties  which  could cause  actual  events  or  results  to  differ  from  those  reflected  in  the  forward‐looking  statements,  including,  without limitation,  risks  and  uncertainties  relating  to  foreign  currency  fluctuations;  risks  inherent  in  mining  including environmental hazards, industrial accidents, unusual or unexpected geological formations, ground control problems and flooding; risks associated with the estimation of mineral resources and reserves and the geology, grade and continuity of mineral deposits; the possibility that future exploration, development or mining results will not be consistent with the Company’s  expectations;  the  potential  for  and  effects  of  labour  disputes  or  other  unanticipated  difficulties  with  or shortages of labour or interruptions in production; actual ore mined varying from estimates of grade, tonnage, dilution and metallurgical and other characteristics; the inherent uncertainty of production and cost estimates and the potential for  unexpected  costs  and  expenses,  commodity  price  fluctuations;  uncertain  political  and  economic  environments; changes in laws or policies, foreign taxation, delays or the inability to obtain necessary governmental permits; and other risks and uncertainties, including those described under Risk Factors Relating to the Company’s Business in the Company’s Annual  Information  Form  and  in  each  management  discussion  and  analysis.  Forward‐looking  information  is  in  addition based on various assumptions including, without limitation, the expectations and beliefs of management, the assumed long  term  price  of  copper,  nickel,  lead  and  zinc;  that  the  Company  can  access  financing,  appropriate  equipment  and sufficient  labour  and  that  the  political  environment  where  the  Company  operates  will  continue  to  support  the development and operation of mining projects. Should one or more of these risks and uncertainties materialize, or should underlying  assumptions  prove  incorrect,  actual  results  may  vary  materially  from  those  described  in  forward‐looking statements. Accordingly, readers are advised not to place undue reliance on forward‐looking statements.

Sampling and Analytical Protocol 

NQ sized drill core was logged, cut in half with a diamond saw and sampled by Company personnel at its facilities at the Neves‐Corvo mine. Mineralized intervals are analyzed for a suite of elements including Zn, Cu, Pb and Sn at the Neves‐ Corvo laboratory using XRF methods.

Qualified Person 

Bob Carmichael, P.Eng., General Manager, Resource Exploration, is the Qualified Person as defined by National Instrument 43‐101 and has reviewed and approved the technical information contained in this release.