Sunday, October 18, 2026
MiningNewsTerminal
Sunday, October 18, 2026 Admin

EDR.TO ·

Endeavour Silver Announces Q2 2022 Financial Results; Raises 2022 Production Guidance

Production Results Financials

VANCOUVER, British Columbia, Aug. 09, 2022 -- Endeavour Silver Corp. (“Endeavour” or the “Company”) (NYSE: EXK; TSX: EDR) is pleased to announce its financial and operating results for the three and six months ended June 30, 2022. As a result of the Company’s strong operating performance, Management has raised its 2022 production guidance. All dollar amounts are in US dollars (US$).

“We have continued to outperform our mine plans, by delivering an exceptional Q2 with production 15% above plan, stated Dan Dickson, CEO of Endeavour Silver. “This has prompted management to raise our production outlook for 2022 to 7.6 – 8.0 million silver equivalent ounces. The additional production has allowed us to maintain our cost guidance on per ounce metrics, but industry-wide inflation continues to be a challenge. We are seeing the largest inflationary impacts on energy costs, plant reagents and steel prices which are affecting both operating and development costs. Cost control will continue to be a key focus as cost pressures are expected to continue for the remainder of the year.”

Added Mr. Dickson, “During the 2nd quarter, again we made the decision to withhold from sale a meaningful amount of silver, due to the drop in silver price. We are holding over 1.6 million silver equivalent ounces in finished goods inventory for future sale. Short term, the increased inventory has negatively impacted our quarterly financial metrics such as revenue, earnings, cash flow and our cash balance. Longer term, we anticipate selling the inventory at higher metal prices.”

Q2 2022 Highlights

  • Higher Production: 1,359,207 ounces (oz) of silver and 9,289 oz of gold for 2.1 million oz silver equivalent (AgEq)(1) reinforces delivery of improved consolidated production for the year.
  • Lower Revenue Due to Withholding Metal Sales: Revenue of $30.8 million from the sale of 602,894 oz of silver and 9,792 oz of gold at average realized prices of $22.72 per oz silver and $1,840 per oz gold.
  • Negative Earnings and Lower Cash Flow Due to Lower Revenue and Non-Cash Items: Net loss of $11.9 million, or $0.07 per share. Adjusted net loss of $4.3 million(2) after adjusting for a $7.6 million change in the fair value of investments. $3.6 million in operating cash flow before working capital changes(2) and Mine operating cash flow before taxes(2) of $8.8 million.
  • Operating Costs per Ounce In-Line with Guidance, Despite Industry-Wide Inflation: Cash costs(2) of $10.08 per oz payable silver and all-in sustaining costs(2) of $19.56 per oz payable silver, net of gold credits.
  • Healthy Balance Sheet: Cash position of $116.2 million and working capital(2) of $149.7 million.
  • Guanacevi Continued to Outperform: Production exceeded plan driven by higher grades.
  • Bolañitos Remained Steady: Strong silver production from higher silver grades and increased throughput were offset by lower gold production and lower gold grades.
  • Withheld Significant Metal Inventories: Metal inventory at quarter end totaled 1,399,356 oz silver and 2,580 oz gold of bullion inventory and 12,408 oz silver and 587 oz gold in concentrate inventory. The market value of finished goods at June 30, 2022 was $34.5 million.
  • Advancing the Terronera Project: Work continued on the early works program initiated last year including engineering, critical contracts, procurement of long-lead items and extensive due diligence on the project financing. The Company intends to make a formal construction decision subject to completion of a financing package and receipt of additional amended permits in the coming months. $18 million has been spent as of June 30th 2022, with an additional budget of $23 million expected to be spent through to the end of October to continue the advancement of the project.

Subsequent to Quarter End

  • Closed the Acquisition of the Pitarrilla Project: The addition of the Pitarrilla project enhances the company’s growth profile while maintaining a silver focus.

Revision to Full Year 2022 Guidance

The following table summarizes the updated 2022 Production Guidance for Endeavour Silver:

GuanaceviBolanitosConsolidated
Tonnes per daytpd1,100 - 1,2001,000 - 1,2002,100 - 2,400
Silver productionM oz4.3 – 4.50.6 - 0.64.9 – 5.1
Gold productionk oz13.0 - 14.021.0 - 22.034.0 - 36.0
Silver Eq production1US$/oz5.3 – 5.62.3 - 2.47.6 - 8.0
Cash costs, net of gold by-product credits2US$/oz$9.00 - $10.00
AISC, net of gold by-product credits2US$/oz$19.00 - $20.00
  • Consolidated Silver Equivalent(1) Production has increased to 7.6 – 8.0 million oz from 6.7 – 7.6 million oz. The increase to consolidated production is primarily driven by higher than planned ore-grades along the El Curso orebody at Guanacevi. Production at Bolanitos has been slightly revised upwards to meet the upper end of its previous guidance.
  • Operating Costs Guidance is expected to remain unchanged with cash costs expected to average $9.00 - $10.00 per oz and AISC are expected to average $19.00 - $20.00 per oz. Management notes that the Company is tracking to meet the upper end of the guidance range, given persisting global inflationary pressures. Increases in prices of raw materials such as reagents, explosives, steel, diesel and power are driving continued cost escalation across the industry. The company has identified efficiencies to mitigate pressure on costs and cost metrics in the second half of the year, including enhanced monitoring and tracking at the mines, improved blasting in development, the gradual increase of tonnes milled and reduced waste handling at Guanacevi.

Financial Overview (see appendix for consolidated financial statements)

Three Months Ended June 30Q2 2022 HighlightsSix Months Ended June 30
20222021% Change20222021% Change
Production
1,359,2071,073,72427%Silver ounces produced2,674,1622,121,82426%
9,28911,166(17%)Gold ounces produced17,98422,275(19%)
1,346,2761,062,26727%Payable silver ounces produced2,649,8162,098,97726%
9,11710,955(17%)Payable gold ounces produced17,66621,849(19%)
2,102,3271,967,0047%Silver equivalent ounces produced(1)4,112,8823,903,8245%
10.0813.03(23%)Cash costs per silver ounce(2)10.1410.48(3%)
14.2619.55(27%)Total production costs per ounce(2)14.6917.51(16%)
19.5625.39(23%)All-in sustaining costs per ounce (2)20.2222.69(11%)
201,361242,018(17%)Processed tonnes407,508451,471(10%)
132.63119.9411%Direct operating costs per tonne(2)127.69116.4310%
148.11141.615%Direct costs per tonne(2)148.32134.4810%
14.1218.52(24%)Silver co-product cash costs(2)14.7416.89(13%)
1,1441,289(11%)Gold co-product cash costs(2)1,1691,1165%
Financial
30.847.7(35%)Revenue ($ millions)88.582.28%
602,8941,120,266(46%)Silver ounces sold2,320,6621,743,64533%
9,7929,810(0%)Gold ounces sold18,17320,473(11%)
22.7226.82(15%)Realized silver price per ounce23.9526.95(11%)
1,8401,866(1%)Realized gold price per ounce1,9001,7817%
(11.9)6.7(279%)Net earnings (loss) ($ millions)(0.3)18.9(101%)
(4.3)2.4(280%)Adjusted net earnings (loss) (2) ($ millions)2.0(3.7)155%
4.510.256%Mine operating earnings ($ millions)24.715.956%
8.817.2(49%)Mine operating cash flow before taxes ($ millions) (2)35.530.516%
3.68.7(58%)Operating cash flow before working capital changes(2)24.213.974%
(4.3)15.9(127%)EBITDA(2) ($ millions)21.339.8(47%)
149.7146.82%Working capital (2) ($ millions)149.7146.82%
Shareholders
(0.07)0.04(275%)Earnings (loss) per share – basic ($)0.000.12(100%)

Operating cash flow before working capital 0.02 0.05 0.14 0.08 62% (61%) changes per share(2)

180,974,609 168,383,755 7% Weighted average shares outstanding 176,291,929 164,051,368 7%

(1) Silver equivalent (AgEq) is calculated using an 80:1 silver:gold ratio.

(2) These are non-IFRS financial measures and ratios. Further details on these non-IFRS financial measures and ratios are provided at the end of this press release and in the MD&A accompanying the Company’s financial statements, which can be viewed on the Company’s website, on SEDAR at www.sedar.com and on EDGAR at www.sec.gov.

For the three months ended June 30, 2022, net revenue, decreased by 35% to $30.8 million (Q2 2021: $47.7 million).

Gross sales of $31.7 million in Q2 2022 represented a 34% decrease over the $48.3 million in Q2 2021. Silver oz sold decreased by 46%, due to the buildup of the larger finished goods inventory held at June 30, 2022. There was a 15% decrease in the realized silver price, resulting in a 54% decrease in proceeds from silver sales. Gold oz sold were flat with a 1% decrease in the realized gold price, resulting in a 1% decrease in proceeds from gold sales. During the period, the Company sold 602,894 oz silver and 9,792 oz gold for realized prices of $22.72 and $1,840 per oz, respectively, compared to Q2 2021 sales of 1,120,266 oz silver and 9,810 oz gold for realized prices of $26.82 and $1,866 per oz, respectively. In Q2 2022, London spot prices for silver and gold averaged $22.60 and $1,877, respectively.

The Company significantly increased its finished goods silver inventory and slightly decreased its finished goods gold inventory to 1,411,764 oz and 3,167 oz, respectively, at June 30, 2022 compared to 668,382 oz silver and 3,841 oz gold at March 31, 2022. The cost allocated to these finished goods was $20.8 million at June 30, 2022 compared to $13.5 million at March 31, 2022. At June 30, 2022, the finished goods inventory fair market value was $34.5 million, compared to $24.1 million at March 31, 2022. Earnings and other financial metrics, including mine operating cash flow(2), operating cash flow(2) and EBITDA(2) were impacted by the withholding of sales during Q2 2022.

After cost of sales of $26.3 million (Q2 2021 - $37.5 million), a decrease of 30%, mine operating earnings were $4.5 million (Q2 2021 - $10.2 million). The decrease in cost of sales was impacted by the decrease in the quantity of silver ounces sold during the period offset by increased labour, power and consumables costs with lower royalty costs. Royalties decreased 49% to $2.2 million primarily due to the decrease in silver ounces sold during the period.

The Company had an operating loss of $1.3 million (Q2 2021: operating earnings of $0.8 million) after exploration and evaluation costs of $3.8 million (Q2 2021: $5.0 million), general and administrative costs of $1.3 million (Q2 2021: $4.3 million) a write off of exploration properties of $0.5 million (Q2, 2021 - $Nil), and care and maintenance cost of $0.2 million (Q2 2021: $0.1 million).

The loss before income taxes was $8.8 million (Q2 2021: earnings before taxes of $8.9 million) after finance costs of $0.3 million (Q2 2021: $0.2 million), a foreign exchange loss of $0.3 million (Q2 2021: gain of $0.7 million), and investment and other expense of $6.9 million (Q2 2021: investment and other income of $1.8 million). The investment and other expenses during Q2 2022 primarily resulted from an unrealized loss on marketable securities and warrants of $7.6 million (Q2 2021: $1.5 million).

The Company realized a net loss for the period of $11.9 million (Q2 2021: net earnings of $6.7 million) after an income tax expense of $3.1 million (Q2 2021: $2.2 million). Current income tax expense increased to $1.3 million (Q2 2021 - $1.1 million) due to increased profitability impacting the income tax and special mining duty, while deferred income tax expense of $1.8 million is primarily due to the estimated use of loss carryforwards to reduce taxable income generated at both Guanacevi and Bolanitos (Q2 2021 – $1.1 million).

Direct operating costs(2) on a per tonne basis increased to $132.63, up 11% compared with Q2 2021 due to higher operating costs at Guanaceví and Bolañitos. Guanaceví and Bolañitos have seen increased labour, power and consumables costs and at Guanaceví, increased third party ore purchased and operating development have increased compared to the prior year.

Consolidated cash costs per oz(2), net of by-product credits, decreased to $10.08 driven by increased silver grades, reduced royalty costs and increased by-product gold sales, offset by increased direct operating costs per tonne(2) AISC(2) decreased by 23% on a per oz basis compared to Q2 2021 as a result of a 27% increase in ounces produced driven by a 51% increase in silver grade, decreased allocated general and administrative costs and a decrease in mine site exploration offset by increased sustaining capital expenditures.

The complete financial statements and management’s discussion & analysis can be viewed on the Company’s website, on SEDAR at www.sedar.com and on EDGAR at www.sec.gov. All shareholders can receive a hard copy of the Company’s complete audited financial statements free of charge upon request. To receive this material in hard copy, please contact Investor Relations at 604-640-4804, toll free at 1-877-685-9775 or by email at [email protected].

Conference Call

A conference call to discuss the Company’s Q2 2022 financial results will be held today at 10:00 a.m. PT / 1:00 p.m. ET. To participate in the conference call, please dial the numbers below.

Date & Tuesday, August 9, 2022 at 10:00 a.m. PT / 1:00 p.m. ET Time:

Telephone: Toll-free in Canada and the US +1-800-319-4610 Local or International +1-604-638-5340 Please allow up to 10 minutes to be connected to the conference call.

Replay: A replay of the conference call will be available by dialing (toll-free) +1-800-319-6413 in Canada and the US (tollfree) or +1-604-638-9010 outside of Canada and the US. The replay passcode is 9151#. The replay will also be available on the Company’s website at www.edrsilver.com.

About Endeavour Silver – Endeavour Silver Corp. is a mid-tier precious metals mining company that operates two highgrade underground silver-gold mines in Mexico. Endeavour is currently advancing the Terronera project towards a development decision, pending financing and final permits and exploring its portfolio of exploration and development projects in Mexico, Chile and the United States to facilitate its goal to become a premier senior silver producer. Our philosophy of corporate social integrity creates value for all stakeholders.

SOURCE Endeavour Silver Corp.

Contact Information

Galina Meleger, Vice President of Investor Relations Tel: (604)640-4804 Email: [email protected] Website: www.edrsilver.com

Follow Endeavour Silver on Facebook, Twitter, Instagram and LinkedIn

Endnotes

1 Silver equivalent (AgEq)

AgEq is calculated using an 80:1 silver:gold ratio.

2 Non-IFRS and Other Financial Measures and Ratios

Certain non-IFRS and other non-financial measures and ratios are included in this press release, including cash costs per silver ounce, total production costs per ounce, all-in costs per ounce, all-in sustaining cost (“AISC”) per ounce, direct operating costs per tonne, direct costs per tonne, silver co-product cash costs, gold co-product cash costs, realized silver price per ounce, realized gold price per ounce, adjusted net earnings (loss) adjusted net earnings (loss) per share, mine operating cash flow before taxes, working capital, operating cash flow before working capital adjustments, operating cash flow before working capital changes per share, earnings before interest, taxes, depreciation and amortization (“EBITDA”), adjusted EBITDA per share and sustaining and growth capital.

Please see the June 30, 2022 MD&A for explanations and discussion of these non-IFRS and other non-financial measures and ratios. The Company believes that these measures and ratios, in addition to conventional measures and ratios prepared in accordance with International Financial Reporting Standards (“IFRS”), provide management and investors an improved ability to evaluate the underlying performance of the Company. The non-IFRS and other non-financial measures and ratios are intended to provide additional information and should not be considered in isolation or as a substitute for measures or ratios of performance prepared in accordance with IFRS. These measures and ratios do not have any standardized meaning prescribed under IFRS, and therefore may not be comparable to other issuers. Certain additional disclosures for these non-IFRS measures have been incorporated by reference and can be found in the section “Non-IFRS Measures” in the June 30, 2022 MD&A available on SEDAR at www.sedar.com.

Reconciliation of Working Capital

Expressed in thousands US dollarsAs at June 30, 2022As at December 31, 2021
Current assets$ 186,454$ 161,762
Current liabilities36,73340,554
Working capital$ 149,721$ 121,208

Reconciliation of Adjusted Net Earnings (Loss) and Adjusted Net Earnings (Loss) Per Share

Expressed in thousands US dollarsThree Months Ended June 30Six Months Ended June 30
(except for share numbers and per share amounts)2022202120222021
Net earnings (loss) for the period per financial statements($ 11,923)$ 6,656($ 261)$ 18,905
Impairment (reversal) of non-current assets, net of tax---(16,791)
Gain on disposal of El Cubo mine and equipment, net of tax-(5,807)-(5,807)

Change in fair value of investments 7,626 1,539 2,269 9

Adjusted net earnings (loss)($ 4,297)$ 2,388$ 2,008($ 3,684)
Basic weighted average share outstanding180,974,609168,383,755176,291,929164,051,368
Adjusted net earnings (loss) per share($ 0.02)$ 0.01$ 0.01($ 0.02)

Reconciliation of Mine Operating Cash Flow Before Taxes

Expressed in thousands US dollarsThree Months Ended June 30Six Months Ended June 30
2022202120222021
Mine operating earnings per financial statements$ 4,472$ 10,205$ 24,741$ 15,869
Share-based compensation113111240229
Amortization and depletion4,1756,62410,48114,120
Write down of inventory to net realizable value-272-272
Mine operating cash flow before taxes$ 8,760$ 17,212$ 35,462$ 30,490

Reconciliation of Operating Cash Flow Before Working Capital Changes and Operating Cash Flow Before Working Capital Changes Per Share

Expressed in thousands US dollarsThree Months Ended June 30Six Months Ended June 30
(except for per share amounts)2022202120222021
Cash from (used in) operating activities per financial statements($ 18,548)$ 9,467$ 3,185$ 5,544
Net changes in non-cash working capital per financial statements(22,160)806(21,046)(8,360)
Operating cash flow before working capital changes$ 3,612$ 8,661$ 24,231$ 13,904
Basic weighted average shares outstanding180,974,609168,383,755176,291,929164,051,368
Operating cash flow before working capital changes per share$ 0.02$ 0.05$ 0.14$ 0.08

Reconciliation of EBITDA and Adjusted EBITDA

Expressed in thousands US dollarsThree Months Ended June 30Six Months Ended June 30
2022202120222021
Net income for the period per financial statements($ 11,923)$ 6,656($ 261)$ 18,905
Depreciation and depletion – cost of sales4,1756,62410,48114,120
Depreciation and depletion – exploration9872205151
Depreciation and depletion – general & administration51389972
Depreciation and depletion – care & maintenance30(11)604
Depreciation and depletion – inventory write down-6-6
Finance costs212216389507
Current income tax expense1,3251,1462,3401,817
Deferred income tax expense1,7521,1167,9744,243
EBITDA($ 4,280)$ 15,863$ 21,287$ 39,825
Share based compensation9721,0282,4992,193
Impairment (reversal) of non-current assets, net of tax---(16,791)
Gain on disposal of El Cubo mine and equipment, net of tax-(5,807)-(5,807)
Change in fair value of investments7,6261,5392,2699
Adjusted EBITDA$ 4,318$ 12,623$ 26,055$ 19,429
Basic weighted average shares outstanding180,974,609168,383,755176,291,929164,051,368
Adjusted EBITDA per share$ 0.02$ 0.07$ 0.15$ 0.12

Reconciliation of Cash Cost Per Silver Ounce, Total Production Costs Per Ounce, Direct Operating Costs Per Tonne, Direct Costs Per Tonne

Expressed in thousands US dollarsThree Months Ended June 30, 2022Three Months Ended June 30, 2021
GuanacevíBolañitosTotalGuanacevíBolañitosEl CompasTotal

Direct production costs per financial $ 7,797 $ 12,031 $ 19,828 $ 15,713 $ 7,770 $ 2,740 $ 26,223 statements

Smelting and refining costs included in net revenue-937937-51468582
Opening finished goods(7,908)(2,995)(10,903)(5,935)(204)(442)(6,581)
Finished goods NRV adjustment-----266266
Closing finished goods16,16468116,8456,9854081,1458,538
Direct operating costs16,05310,65426,70716,7638,4883,77729,028
Royalties2,128662,1944,158701124,340
Special mining duty (1)795127922684257(38)903
Direct costs18,97610,84729,82321,6058,8153,85134,271
By-product gold sales(5,719)(12,302)(18,021)(4,209)(11,909)(2,187)(18,305)
Opening gold inventory fair market value3,7243,7637,4871,9253096622,896
Closing gold inventory fair market value(4,662)(1,061)(5,723)(3,349)(633)(1,038)(5,020)
Cash costs net of by-product12,3191,24713,56615,972(3,418)1,28813,842
Amortization and depletion9403,2354,1752,4873,8003376,624
Share-based compensation575611354516111
Opening finished goods depreciation and depletion(1,689)(897)(2,586)(1,137)(118)(133)(1,388)
NRV depreciation cost adjustment-----6-
Closing finished goods depreciation and depletion3,7331993,9321,333220301,583
Total production costs$ 15,360$ 3,840$ 19,200$ 18,709$ 535$ 1,534$ 20,772
Three Months Ended June 30, 2022Three Months Ended June 30, 2021
GuanacevíBolañitosTotalGuanacevíBolañitosEl CompasTotal
Throughput tonnes94,017107,344201,361111,893107,91222,213242,018
Payable silver ounces1,190,568155,7081,346,276936,424112,45613,3871,062,267
Cash costs per silver ounce$ 10.35$ 8.01$ 10.08$ 17.06($ 30.39)$ 96.21$ 13.03
Total production costs per ounce$ 12.90$ 24.66$ 14.26$ 19.98$ 4.76$ 114.59$ 19.55
Direct operating costs per tonne$ 170.75$ 99.25$ 132.63$ 149.81$ 78.66$ 170.04$ 119.94
Direct costs per tonne$ 201.84$ 101.05$ 148.11$ 193.09$ 81.69$ 173.37$ 141.61
Expressed in thousands US dollarsSix Months Ended June 30, 2022Six Months Ended June 30, 2021
GuanacevíBolañitosTotalGuanacevíBolañitosEl CompasTotal
Direct production costs per financial statements$ 25,681$ 20,868$ 46,549$ 23,773$ 14,875$ 6,303$ 44,951
Smelting and refining costs included in net revenue-1,5911,591-1,0032061,209
Opening finished goods(10,093)(2,857)(12,950)(1,509)(250)(642)(2,401)
Finished goods NRV adjustment-----266266
Closing finished goods16,16468116,8456,9854081,1458,538
Direct operating costs31,75220,28352,03529,24916,0367,27852,563
Royalties6,3621496,5116,3711382916,800
Special mining duty (1)1,5263711,897941408-1,349
Direct costs39,64020,80360,44336,56116,5827,56960,712
By-product gold sales(10,741)(23,790)(34,531)(7,673)(22,438)(6,352)(36,463)
Opening gold inventory fair market value1,9004,7846,6847357461,2832,764
Closing gold inventory fair market value(4,662)(1,061)(5,723)(3,349)(633)(1,038)(5,020)
Cash costs net of by-product26,13773626,87326,274(5,743)1,46221,993
Amortization and depletion4,8505,63110,4814,0807,5932,44714,120
Share-based compensation120120240939145229
Opening finished goods depreciation and depletion(1,965)(635)(2,600)(271)(104)(804)(1,179)

NRV depreciation and depletion cost

  • - - - - 6 6

adjustment

Closing finished goods depreciation and depletion3,7331993,9321,333220301,583
Total production costs$ 32,875$ 6,051$ 38,926$ 31,509$ 2,057$ 3,186$ 36,752
Six Months Ended June 30, 2022Six Months Ended June 30, 2021
GuanacevíBolañitosTotalGuanacevíBolañitosEl CompasTotal
Throughput tonnes195,270212,238407,508200,525205,60445,342451,471
Payable silver ounces2,321,016328,8002,649,8161,851,886211,44435,6472,098,977
Cash costs per silver ounce$ 11.26$ 2.24$ 10.14$ 14.19($ 27.16)$ 41.01$ 10.48
Total production costs per ounce$ 14.16$ 18.40$ 14.69$ 17.01$ 9.73$ 89.38$ 17.51
Direct operating costs per tonne$ 162.61$ 95.57$ 127.69$ 145.86$ 77.99$ 160.51$ 116.43
Direct costs per tonne$ 203.00$ 98.02$ 148.32$ 182.33$ 80.65$ 166.93$ 134.48
Expressed in thousands US dollarsJune 30, 2022June 30, 2021
GuanacevíBolañitosTotalGuanacevíBolañitosEl CompasTotal
Closing finished goods16,16468116,8456,9854081,1458,538
Closing finished goods depletion3,7331993,9321,333220301,583
Finished goods inventory$ 19,897$ 880$ 20,777$ 8,318$ 628$ 1,175$ 10,121

Reconciliation of All-In Costs Per Ounce and AISC per ounce

Expressed in thousands US dollarsThree Months Ended June 30, 2022Three Months Ended June 30, 2021
GuanacevíBolañitosTotalGuanacevíBolañitosEl CompasTotal
Cash costs net of by-product$ 12,319$ 1,247$ 13,566$ 15,972($ 3,418)$ 1,288$ 13,842
Operations share-based compensation5756113394039118
Corporate general and administrative4011555562,0131,0932773,383
Corporate share-based compensation52721474146025064773
Reclamation - amortization/accretion69531221311327
Mine site expensed exploration3603086685383052845
Intangible payments(0)0(0)8029(16)94
Equipment loan payments246488734300524-824
Capital expenditures sustaining7,0502,7889,8383,6963,366-7,062
All-In-Sustaining Costs$ 21,028$ 5,310$ 26,338$ 23,112$ 2,200$ 1,656$ 26,968
Growth exploration and evaluation2,9013,963
Growth capital expenditures5,6131,102
All-In-Costs$ 34,852$ 32,033
Three Months Ended June 30, 2022Three Months Ended June 30, 2021
GuanacevíBolañitosTotalGuanacevíBolañitosEl CompasTotal
Throughput tonnes94,017107,344201,361111,893107,91222,213242,018
Payable silver ounces1,190,568155,7081,346,276936,424112,45613,3871,062,267
Silver equivalent production (ounces)1,488,550613,7772,102,3271,185,961660,284120,7591,967,004
Sustaining cost per ounce$ 17.66$ 34.10$ 19.56$ 24.68$ 19.56$ 123.73$ 25.39
All-In-costs per ounce$ 25.89$ 30.16
Expressed in thousands US dollarsSix Months Ended June 30, 2022Six Months Ended June 30, 2021
GuanacevíBolañitosTotalGuanacevíBolañitosEl CompasTotal

Cash costs net of by-product $ 26,137 $ 736 $ 26,873 $ 26,274 ($ 5,743) $ 1,462 $ 21,993

Operations share-based compensation120120240939145229
Corporate general and administrative2,4681,0313,4993,6221,9664986,086
Corporate share-based compensation1,4446032,0479875361361,658
Reclamation - amortization/accretion1341062402522552
Mine site expensed exploration7125581,2709945391951,728
Intangible payments2912411116015187
Equipment loan payments4919771,4686081,092-1,700
Capital expenditures sustaining12,6965,21417,9107,9006,100-14,000
All-In-Sustaining Costs$ 44,230$ 9,358$ 53,588$ 40,615$ 4,663$ 2,355$ 47,633
Growth exploration and evaluation5,3146,970
Growth capital expenditures10,5381,434
All-In-Costs$ 69,440$ 56,037
Six Months Ended June 30, 2022Six Months Ended June 30, 2021
GuanacevíBolañitosTotalGuanacevíBolañitosEl CompasTotal
Throughput tonnes195,270212,238407,508200,525205,60445,342451,471
Payable silver ounces2,321,016328,8002,649,8161,851,886211,44435,6472,098,977
Silver equivalent production (ounces)2,900,5601,212,3224,112,8822,323,6181,261,071319,1353,903,824
Sustaining cost per ounce$ 19.06$ 28.46$ 20.22$ 21.93$ 22.05$ 66.07$ 22.69
All-In-costs per ounce$ 26.21$ 26.70

Reconciliation of Sustaining Capital and Growth Capital

Expressed in thousands US dollarsThree Months Ended June 30Six Months Ended June 30
2022202120222021
Capital expenditures sustaining$ 9,838$ 7,062$ 17,910$ 14,000
Growth capital expenditures5,6131,10210,5381,434
Property, plant and equipment expenditures per Consolidated Statement of Cash Flows$ 15,451$ 8,164$ 28,448$ 15,434

Reconciliation of Silver Co-Product Cash Costs and Gold Co-Product Cash Costs

Expressed in thousands US dollarsThree Months Ended June 30, 2022Three Months Ended June 30, 2021
GuanacevíBolañitosTotalGuanacevíBolañitosEl CompasTotal
Direct production costs per financial statements$ 7,797$ 12,031$ 19,828$ 15,713$ 7,770$ 2,740$ 26,223
Smelting and refining costs included in net revenue-937937-51468582
Royalties2,128662,1944,158701124,340
Special mining duty (1)795127922684257(38)903
Opening finished goods(7,908)(2,995)(10,903)(5,935)(204)(442)(6,581)
Finished goods NRV adjustment-----266266
Closing finished goods16,16468116,8456,9854081,1458,538
Direct costs$ 18,976$ 10,847$ 29,823$ 21,605$ 8,815$ 3,851$ 34,271
Three Months Ended June 30, 2022Three Months Ended June 30, 2021
GuanacevíBolañitosTotalGuanacevíBolañitosEl CompasTotal
Silver production (ounces)1,194,150165,0571,359,207939,241120,04414,4391,073,724

Average realized 22.72 22.72 22.72 26.82 26.82 26.82 26.82 silver price ($)

Silver value ($)27,131,5803,750,16330,881,74325,186,4723,219,073387,19328,792,738
Gold production (ounces)3,6805,6099,2893,0846,7531,32911,166
Average realized gold price ($)1,8401,8401,8401,8661,8661,8661,866
Gold value ($)6,772,59810,322,69117,095,2895,754,59912,600,7812,479,85220,835,232
Total metal value ($)33,904,17814,072,85447,977,03230,941,07215,819,8542,867,04549,627,970
Pro-rated silver costs (%)80%27%64%81%20%14%58%
Pro-rated gold costs (%)20%73%36%19%80%86%42%
Pro-rated silver costs ($)15,1852,89119,19617,5871,79452019,883
Pro-rated gold costs ($)3,7917,95610,6274,0187,0213,33114,388
Silver co-product cash costs ($)12.7217.5114.1218.7214.9436.0218.52
Gold co-product cash costs ($)1,0301,4191,1441,3031,0402,5061,289
Expressed in thousands US dollarsSix Months Ended June 30, 2022Six Months Ended June 30, 2021
GuanacevíBolañitosTotalGuanacevíBolañitosEl CompasTotal
Direct production costs per financial statements$ 25,681$ 20,868$ 46,549$ 23,773$ 14,875$ 6,303$ 44,951
Smelting and refining costs included in net revenue-$ 1,591$ 1,591-1,0032061,209
Royalties6,3621496,5116,3711382916,800
Special mining duty (1)1,5263711,897941408-1,349
Opening finished goods(10,093)(2,857)(12,950)(1,509)(250)(642)(2,401)
Finished goods NRV adjustment-----266266
Closing finished goods16,16468116,8456,9854081,1458,538
Direct costs39,64020,80360,44336,56116,5827,56960,712
Six Months Ended June 30, 2022Six Months Ended June 30, 2021
GuanacevíBolañitosTotalGuanacevíBolañitosEl CompasTotal
Silver production (ounces)2,328,000346,1622,674,1621,857,458226,27138,0952,121,824
Average realized silver price ($)23.9523.9523.9526.9526.9526.9526.95
Silver value ($)55,757,7528,290,90064,048,65250,053,9846,097,4541,026,56857,178,006
Gold production (ounces)7,15710,82717,9845,82712,9353,51322,275
Average realized gold price ($)1,9001,9001,9001,7811,7811,7811,781
Gold value ($)13,599,20620,572,67034,171,87610,378,05423,037,6066,256,75439,672,414

Total metal value ($) 69,356,958 28,863,570 98,220,528 60,432,038 29,135,060 7,283,321 96,850,420

Pro-rated silver costs (%)80%29%65%83%21%14%59%
Pro-rated gold costs (%)20%71%35%17%79%86%41%
Pro-rated silver costs ($)31,8685,97639,41430,2823,4701,06735,843
Pro-rated gold costs ($)7,77214,82721,0296,27913,1126,50224,869
Silver co-product cash costs ($)13.6917.2614.7416.3015.3428.0016.89
Gold co-product cash costs ($)1,0861,3691,1691,0781,0141,8511,116

Reconciliation of Realized Silver Price Per Ounce and Realized Gold Price Per Ounce

Expressed in thousands US dollarsThree Months Ended June 30Six Months Ended June 30
2022202120222021
Gross silver sales$ 13,698$ 30,052$ 55,582$ 46,987
Silver ounces sold602,8941,120,2662,320,6621,743,645
Realized silver price per ounces$ 22.72$ 26.82$ 23.95$ 26.95
Expressed in thousands US dollarsThree Months Ended June 30Six Months Ended June 30
2022202120222021
Gross gold sales$ 18,021$ 18,305$ 34,531$ 36,463
Gold ounces sold9,7929,81018,17320,473
Realized gold price per ounces$ 1,840$ 1,866$ 1,900$ 1,781

Cautionary Note Regarding Forward-Looking Statements

This news release contains “forward-looking statements” within the meaning of the United States private securities litigation reform act of 1995 and “forward-looking information” within the meaning of applicable Canadian securities legislation. Such forward-looking statements and information herein include but are not limited to statements regarding Endeavour’s anticipated performance in 2022 including changes in mining operations and forecasts of production levels, anticipated production costs and all-in sustaining costs, the timing and results of various activities and the impact of the COVID 19 pandemic on operations. The Company does not intend to and does not assume any obligation to update such forward-looking statements or information, other than as required by applicable law.

Forward-looking statements or information involve known and unknown risks, uncertainties and other factors that may cause the actual results, level of activity, production levels, performance or achievements of Endeavour and its operations to be materially different from those expressed or implied by such statements. Such factors include but are not limited to the ultimate impact of the COVID 19 pandemic on operations and results, changes in production and costs guidance, national and local governments, legislation, taxation, controls, regulations and political or economic developments in Canada and Mexico; financial risks due to precious metals prices, operating or technical difficulties in mineral exploration, development and mining activities; risks and hazards of mineral exploration, development and mining; the speculative nature of mineral exploration and development, risks in obtaining necessary licenses and permits, and challenges to the Company’s title to properties; as well as those factors described in the section “risk factors” contained in the Company’s most recent form 40F/Annual Information Form filed with the S.E.C. and Canadian securities regulatory authorities.

Forward-looking statements are based on assumptions management believes to be reasonable, including but not limited to: the continued operation of the Company’s mining operations, no material adverse change in the market price of commodities, mining operations will operate and the mining products will be completed in accordance with management’s expectations and achieve their stated production outcomes, and such other assumptions and factors as set out herein. Although the Company has attempted to identify important factors that could cause actual results to differ materially from those contained in forward- looking statements or information, there may be other factors that cause results to be materially different from those anticipated, described, estimated, assessed or intended. There can be no assurance that any forward-looking statements or information will prove to be accurate as actual results and future events could differ materially from those anticipated in such statements or information. Accordingly, readers should not place undue reliance on forward-looking statements or information.

Appendix

ENDEAVOUR SILVER CORP.

CONDENSED CONSOLIDATED INTERIM STATEMENTS OF COMPREHENSIVE EARNINGS (unaudited – prepared by management)

(expressed in thousands of US dollars, except for shares and per share amounts)

Three months endedSix months ended
June 30, June 30,June 30, June 30,
2022 20212022 2021
$ 88,522 $ 82,241
Revenue$ 30,782 $ 47,775$ 88,522
Cost of sales:
Direct production costs19,828 26,22346,54944,951
Royalties2,194 4,3406,5116,800
Share-based payments113 111240229
Depreciation, depletion and amortization4,175 6,62410,48114,120
Write down of inventory to net realizable value- 272-272
26,310 37,57063,78166,372
Mine operating earnings4,472 10,20524,74115,869
Expenses:
Exploration and evaluation3,784 5,0257,0009,155
General and administrative1,348 4,2935,6457,816
Care and maintenance costs189 55379576
Impairment (reversal of impairment) of non- current assets, net- --(16,791)
Write off of exploration properties500 -500-
5,821 9,37313,524756
Operating earnings (loss)(1,349) 83211,21715,113
Finance costs336 216634507
Other income (expense):
Foreign exchange(289) 659522(35)
Gain on asset disposal- 5,841-5,841
Investment and other(6,872) 1,802(1,052)4,553
(7,161) 8,302(530)10,359
Earnings (loss) before income taxes(8,846) 8,91810,05324,965
Income tax expense:
Current income tax expense1,325 1,1462,3401,817
Deferred income tax expense1,752 1,1167,9744,243
3,077 2,26210,3146,060
Net earnings (loss) and comprehensive earnings (loss) for the period$ (11,923) $ 6,656$ (261)$ 18,905
Basic earnings (loss) per share based on net earnings$ (0.07) $ 0.04$ (0.00)$ 0.12
Diluted earnings (loss) per share based on net earnings$ (0.07) $ 0.04$ (0.00)$ 0.11
Basic weighted average number of shares outstanding180,974,609 168,383,755176,291,929164,051,368
Diluted weighted average number of shares outstanding184,569,970 172,195,942179,018,499167,743,113

ENDEAVOUR SILVER CORP.

CONDENSED CONSOLIDATED INTERIM STATEMENTS OF FINANCIAL POSITION (unaudited – prepared by management)

(expressed in thousands of US dollars)

June 30, December 31,
20222021
ASSETS
Current assets
Cash and cash equivalents$ 116,226$ 103,303
Other investments8,29311,200
Accounts and other receivable13,48614,462
Income tax receivable1,219177
Inventories35,66427,485
Prepaid expenses11,5665,135
Total current assets186,454161,762
Non-current deposits595599
Non-current income tax receivable3,5703,570
Non-current other investments2,943-
Non-current IVA receivable7,5284,256
Deferred income tax asset-936
Intangible assets-40
Right-of-use leased assets614664
Mineral properties, plant and equipment141,806122,197
Total assets$ 343,510$ 294,024
LIABILITIES AND SHAREHOLDERS' EQUITY
Current liabilities
Accounts payable and accrued liabilities$ 26,383$ 31,991
Income taxes payable4,9954,228
Loans payable5,1794,128
Lease liabilities176207
Total current liabilities36,73340,554
Loans payable7,3926,366
Lease liabilities755794
Provision for reclamation and rehabilitation7,5767,397
Deferred income tax liability8,5451,506
Total liabilities61,00156,617
Shareholders' equity
Common shares, unlimited shares authorized, no par value, issued
and outstanding 181,051,354 shares (Dec 31, 2021 - 170,537,307 shares)631,751585,406
Contributed surplus5,3496,331
Retained earnings (deficit)(354,591)(354,330)
Total shareholders' equity282,509237,407
Total liabilities and shareholders' equity$ 343,510$ 294,024

ENDEAVOUR SILVER CORP.

CONDENSED CONSOLIDATED INTERIM STATEMENTS OF CASH FLOWS (unaudited – prepared by management)

(expressed in thousands of US dollars)