Reassessment of Historic Data Outlines Gold Zone at Majuba Hill, Nevada: Bam Bam Updates Drilling Plans

Exploration Programs

Reassessment of Historic Data Outlines Gold Zone

at Majuba Hill, Nevada:

Bam Bam Updates Drilling Plans

VANCOUVER, BC—April 27, 2020— Bam Bam Resources Corp. (CSE: BBR / OTC: NPEZF /

FSE: 4NPA) (“Bam Bam” or the “Company”) is pleased to announce that, after reassessment

of historic drilling and exploration, the geological team at Majuba Hill are pleased to report

that they have outlined three gold zones associated with the Majuba Hill copper (gold)

porphyry project in Pershing County, Nevada. The ongoing, historical data review highlighted

significant gold values associated with the copper in historic drill holes, surface rock chips,

and soil sampling. This data suggests that Majuba Hill is best classified as a copper-gold

porphyry.

Mr. David Greenway, CEO, reports: “This is an amazing development for our Majuba Hill

Copper Project. The reassessment of historic results and our improved understanding of the

data is good news for Bam Bam. Once we understood that, prior to Heap Leach in Nevada,

gold grades were ignored in “copper” plays, we went in and had another look. Our shock was

in the complete discounting of gold intercepts and we are madly working to re-incorporate

those numbers and, more importantly, coordinate them with our drill program. Gold in copper

porphyry projects can add value quickly. Majuba Hill is an exciting opportunity during these

times of improving copper sentiment and we are pleased to be able to incorporate the historic

gold results.”

Historic exploration includes drilling, surface rock chip sampling and surface soil sampling

assay results that also contain gold assays:

• Gold in historic drill assay results were significant in 14 of the 37 holes drilled

• Historic rock chip sampling (163 samples) returned 10.15 to <0.005 g/t gold

• Historic soil sampling (994 samples) returned 0.425 to <0.005 g/t gold

Three gold zones are outlined

based on the historic data.

The gold zone in the main

target area overlaps with the

oxide copper target zone that

will be drilled in the upcoming

program.

The highest gold grades were

reported in historic drill hole

MH-11 with 5 ft @6.44 g/t Au

from 155 to 160 feet and 15

ft @3.173 g/t Au from 585 to

500 feet.

Holes MM-06 and MM-07

contain gold overlapping with

significant copper reported

earlier (BBR NR-March 25,

2020).

• MM-05: 89.2 m @ 0.27% Cu from 0 to 89.2 m

• MM-06: 47.4 m at 1.06% Cu from 0 to 47.4 m

• MH-7: 97.5 m at 0.33% Cu from 25.9 to 123.4 m

• MG1703: 20.4 m at 0.71% Cu from 102.9 to 123.3 m

• MMX-24: 112.8 m at 0.45% Cu from 222.5 to 335.3

Hole Interval >1.0 g/t Gold

MH-2 10ft@ 0.235 g/t Au: 275-285 ft

MH-3 15ft@ 0.144 g/t Au: 265-280 ft

10ft@ 0.107 g/t Au: 315-325 ft

MH-6 15ft@ 0.181 g/t Au: 135-150 ft

MH-7 25ft@ 0.318 g/t Au: 150-175 ft

15ft@ 0.2 g/t Au: 180-195 ft

20ft@ 0.14 g/t Au: 340-360 ft

MH-10 15ft@ 0.133 g/t Au: 590-605 ft

MH-11 5ft@ 6.44 g/t Au: 155-160 ft

15ft@ 3.173 g/t Au: 585-600

ft

MM-02 10ft@ 0.164 g/t Au: 365-375 ft

MM-03 10ft@ 0.233 g/t Au: 260-270 ft

20ft@ 0.22 g/t Au: 340-360 ft

Hole Interval >1.0 g/t Gold

MM-06 10ft@ 0.339 g/t Au: 70-80 ft

15ft@ 0.471 g/t Au: 100-115

ft

20ft@ 0.239 g/t Au: 130-150 ft

10ft@ 0.331 g/t Au: 235-245 ft

MM-07 20ft@ 0.242 g/t Au: 250-270 ft

10ft@ 0.134 g/t Au: 290-300 ft

13ft@ 0.333 g/t Au: 322-335 ft

45ft@ 0.699 g/t Au: 350-395

ft

10ft@ 0.417 g/t Au: 405-415

ft

MM-16 25ft@ 0.342 g/t Au: 175-200 ft

MM-17 10ft@ 0.427 g/t Au: 15-25 ft

MM-20 6ft@ 0.182 g/t Au: 99.1-105.5 ft

7ft@ 0.128 g/t Au: 114.3-121.4 ft

Hole Interval >1.0 g/t Gold

10ft@ 0.131 g/t Au: 250-260 ft

10ft@ 0.151 g/t Au: 270-280 ft

20ft@ 0.442 g/t Au: 285-305

ft

10ft@ 0.2 g/t Au: 320-330 ft

10ft@ 0.128 g/t Au: 580-590 ft

10ft@ 0.198 g/t Au: 715-725 ft

80ft@ 0.19 g/t Au: 765-845 ft

20ft@ 0.183 g/t Au: 880-900 ft

Hole Interval >1.0 g/t Gold

20ft@ 0.148 g/t Au: 905-925 ft

10ft@ 0.129 g/t Au: 930-940 ft

40ft@ 0.27 g/t Au: 945-985 ft

35ft@ 0.157 g/t Au: 995-1030 ft

15ft@ 0.161 g/t Au: 1035-1050 ft

MG1703 10ft@ 0.193 g/t Au: 337.7-347.7

ft

10ft@ 0.155 g/t Au: 761-771 ft

10ft@ 0.145 g/t Au: 1079-1089 ft

Majuba Hill drilling plans and logistics for the core drilling portion of the upcoming program

are in place. Pad site and road access construction is complete. The hole sites are located on

the private, patented mining claims. Harris Exploration Drilling & Associate, Inc. has been

engaged to drill two core holes. Bam Bam field personnel and contractors will use operational

health and safety protocols consistent with ensuring the health and safety of its people and

the local community.

The Company intends to complete the drilling and initiate a National Instrument 43-101

Technical peport on the project which will further delineate the next steps to be taken by the

Company and advance the project.

Further, the Company has issued 1,890,000 incentive stock options at a strike price of $0.07 per

share to consultants of the Company. The options are valid for a one-year term and are governed

by the terms of the Company’s stock option plan.

About Bam Bam Resources Corp.

Bam Bam Resources Corp. (CSE: BBR / OTC: NPEZF / FSE: 4NPA) is engaged in the

identification, review and acquisition of latter stage copper and copper/gold assets. With its

flagship project being Majuba Hill copper gold project located 156 miles outside Reno, Nevada,

USA. Management has been mandated to focus on safe, mining friendly jurisdictions and

government regulations supportive of mining operations.

On Behalf of the Board of Bam Bam Resources Corp.

“David Greenway”

President & CEO

For further information, please contact:

E: [email protected]

P: (604) 318-0114

Neither the Canadian Securities Exchange nor its Market Regulator (as that term is defined in the policies of the

Canadian Securities Exchange) accepts responsibility for the adequacy or accuracy of this release.

This news release may contain forward-looking statements based on assumptions and judgments of management

regarding future events or results. Such statements are subject to a variety of risks and uncertainties, which could

cause actual events or results to differ materially from those reflected in the forward-looking statements. The

Company disclaims any intention or obligation to revise or update such statements.