Sunday, September 20, 2026
MiningNewsTerminal
Sunday, September 20, 2026 Admin

FNI.CN ·

Fathom Nickel Albert Lake Exploration Update

Exploration Programs

Fathom Nickel Inc.

FATHOM SUCCESSFULY COMPLETES PHASE-1 OF THE 2021 SUMMER / FALL EXPLORATION

PROGRAM AT THE ALBERT LAKE PROPERTY

NOT FOR DISTRIBUTION TO UNITED STATES NEWSWIRE SERVICES OR FOR DISSEMINATION IN THE UNITED STATES.

ANY FAILURE TO COMPLY WITH THIS RESTRICTION MAY CONSTITUTE A VIOLATION OF U.S. SECURITIES LAWS.

• Phase-1 of the summer field program has been completed at the Albert Lake Project in

Saskatchewan. Field crews will be returning to initiate Phase-2 on July 23, 2021.

• Soil Geochemistry, BHEM, Gravity surveys, and heli-MAG surveys have added valuable

information and data necessary to generate and refine high quality drill targets for H2-2021 and

Q1-2022.

• The fall drill program will focus on the BHEM targets identified as well as locations where

significant ultramafic intersections occur. Drilling will commence by the first week of September.

Calgary, Alberta – July 22, 2021 – Fathom Nickel Inc. (the "Company" or "Fathom") (CSE:FNI) (FSE:

6Q5), is pleased to announce the completion of the initial phase of the summer / fall exploration program

(“Phase-1”), at its Saskatchewan Albert Lake Nickel Copper, Cobalt, PGE Project .

Phase-1 of the f ield exploration program which commenced June 15, 2021 and ran for four weeks was

focussed on the definition and refinement of drill targets to be drilled the second half of the 2021 program

and in the Q1-2022 winter drill program.

“We are extremely pleased with the progress and results of the Phase- 1 exploration as we continue to

refine existing targets and generate high quality new targets for follow-up,” stated Brad Van Den Bussche,

CEO. He added , “Our team is looking forward to a focussed drill program commencing the first week of

September and expected to continue through March/April 2022 as we test these quality targets.”

Specific exploration initiatives in Phase-1 included:

• Over 2,000 soil samples were collected for B -horizon soil geochemistry (Figure 1). Samples are

currently being analyzed and results are expected by the end of August. The Phase-1 soil

geochemistry survey focused on the area SW of the known Tremblay Olson Showing (mineralized

ultramafic occurrence similar to the historic Rottenstone Mine) and in an area 4- 5 km south-

southeast of the Rottenstone mine extension where the recently completed gradient MAG survey

has defined an area of complex folding and faulting.

• Geological mapping has confirmed surface outcrops of mafic (gabbro) - ultramafic occurrences

coincident with favorable, Rottenstone-like MAG features, approximately 10 km south- southwest

of the historic Rottenstone mine (Figure 1).

• The Gravity survey initiated on lake ice during the Q1-2021 drilling program has continued to cover

numerous islands within Rottenstone Lake and the area north of the historic Rottenstone mine and

further northeast to cover the Mawdsley Target area. Gravity measurements have been taken at

347 stations.

• Borehole electromagnetic surveys (BHEM) on 9 historic drillholes and on recently drilled AL21017

has been completed. BHEM results from AL21017 drilled south of the historic Rottenstone mine

(see June 7, 2021 press release) has confirmed the Ni-Co-Cu + PGE mineralization remaining at

2

Rottenstone does have a positive BHEM signal. Fathom deems this a very positive development

as this BHEM signal is now recognized in several off -hole BHEM responses detected in the Big

Island area, 400m west of the Rottenstone mine and in drillhole AL21021 (see June 7, 2021 press

release), 550m northwest of the Rottenstone mine and in a historic drillhole occurring 100m north

of the Rottenstone mine. Additional BHEM surveying of historic drillholes as well as BHEM of the

new holes will be part of the upcoming fall drill program.

• The fall drill program will focus on the BHEM targets identified, and areas where significant

ultramafic intersections were drilled by previous operators of the property. Drilling will commence

the first week of September.

• Phase-1 interpretation of the spr ing heli-MAG survey is in hand. The Company prioritized survey

interpretation in the areas targeted for 2021 field exploration. Within this area of interest, numerous

folds, deep rooted faults and shear zones have been recognized. Nineteen geophysical and

structural target areas are recommended with a specific focus on exploration for nickel -sulphide

mineralization. Interpretation of the property wide MAG survey flown in 2021 is ongoing.

Management will continue to provide regular updates to the exploration program as milestones are

achieved and material developments and results are available.

3

Figure – 1: 2021 Summer / Fall Exploration Progress

4

Qualified Person and Data Verification

Ian Fraser, PGeo., VP Exploration and a Director of the Company and the "qualified person" as such term

is defined by National Instrument 43- 101, has verified the data discl osed in this news release, and has

otherwise reviewed and approved the technical information in this news release on behalf of the Company.

About Fathom Nickel Inc.

Fathom Nickel is a resource development and exploration company that is targeting high- grade nickel

sulfide discoveries for use in the rapidly growing global electric vehicle market.

The Company is accelerating exploration on its flagship Albert Lake Project, host to the historic

Rottenstone mine, which is recognized as one of the highest ‐grade (Nickel, Copper, Platinum group

metals) deposits of its type ever mined in Canada. The Albert Lake Project consists of over 90,000 ha of

mineral claims located in the Trans-Hudson Corridor of Saskatchewan, which is home to numerous world-

class mining camps.

ON BEHALF OF THE BOARD

“Brad Van Den Bussche”

President and CEO, Director

For Further Information Please Contact:

Brad Van Den Bussche, President and CEO

or

Manish Grigo, Director of Corporate Development

+1-416-569-3292

Email: [email protected]

Forward Looking Statements :

This news release contains "forward-looking statements" that are based on expectations, estimates, projections and

interpretations as at the date of this news release. Forward-looking statements are frequently characterized by words

such as "plan", "expect", "project", "seek", "intend", "believe", "anticipate", "estimate", "suggest", "indicate" and other

similar words or statements that certain events or conditions "may" or "will" occur, and include, without limitation,

statements regarding the enhancement of the Company’s geologic model and extending the areas of known

mineralization and the Company’s work towards defining a resource base. Such forward looking statements involve

known and unknown risks, uncertainties and other factors which may cause the actual results, performance or

achievements of the Company to be materially different from any future results, performance or achievements

expressed or implied by such forward-looking statements. Such risks and other factors may include, but are not limited

to, the results of exploration activities; the ability of the Company to c omplete further exploration activities; timing and

availability of external financing on acceptable terms. The Company does not undertake to update any forward-looking

information except in accordance with applicable securities laws.